Change of Use / Change of Occupancy Permit in Stevensville, Montana
Required for a change in occupancy classification or use of an existing commercial building or tenant space in Stevensville. Governed by the International Existing Building Code, 2021 edition, as locally adopted (Sec. 6-135, Town of Stevensville Code of Ordinances), which explicitly covers 'the repair, alteration, change of occupancy, addition and relocation of existing buildings.' There is no standalone change-of-use application or Certificate of Occupancy form separate from the Town's general Building Permit process — change-of-use projects are submitted on the standard Building Permit Application and billed under the flat 'Change of use' fee line already documented in this file's Building Permit entry.
Verified 2026-07-22 · Source
When you need this permit
- Per Sec. 6-135 (Chapter 6, Article VI - Existing Building Code): the International Existing Building Code, 2021 edition, is adopted 'for regulating and governing the repair, alteration, change of occupancy, addition and relocation of existing buildings ... within the town; and for providing for the issuance of permits and collections of fees therefor'
- Per Sec. 6-136, enforcement, permitting, and fees for change-of-occupancy work follow the same general process set out in Chapter 6, Articles II (Building Official) and III (Building Permits) — the same Building Official, application, and 180-day commencement / 12-month validity rules that govern the standard Building Permit (already documented in this file's Building Permit entry)
- The Town's Building FAQs page independently confirms that a permit is required 'to construct, enlarge, alter, repair, move, demolish, [or] change the occupancy of a building or structure'
- Per Sec. 10-187(c) (Development Code): as a condition of permit issuance for new commercial construction or a substantial remodel (floor-area increase of 20 percent or more, or modifications exceeding 50 percent of replacement value), required street frontage improvements (curb, gutter, sidewalk, pavement, storm drainage) must be installed or upgraded at the permittee's sole cost PRIOR TO the issuance of a certificate of occupancy — meaning a Certificate of Occupancy is the Town's actual sign-off document for qualifying commercial permits and can be conditioned on completion of infrastructure work
- No standalone 'Change of Use Permit' or 'Certificate of Occupancy' application form was found on the Town's Forms page separate from the general Building Permit Application
- Distinct from the Town's separate annual general Business License (Chapter 12 of the Code of Ordinances, $75.00/year, renewed each December 31) — a change-of-use permit is a one-time building-code compliance permit, while the business license is a recurring requirement to operate any business in town; the two are not interchangeable and both may be required
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final / Certificate of Occupancy Inspection
Building Official verifies the new occupancy classification and use comply with the International Existing Building Code (2021 edition, as locally adopted) and applicable zoning before issuing a Certificate of Occupancy; per Sec. 10-187(c), qualifying commercial projects must also complete required street frontage improvements before a Certificate of Occupancy is issued
See the full Stevensville inspection guide — scheduling & re-inspection fees →
Tips
- A change-of-use permit is separate from the Town's annual general Business License (Chapter 12, $75.00/year) — a business operating in Stevensville may need both a one-time change-of-use/building permit AND the recurring business license.
- If the change of use involves new commercial construction or a substantial remodel (floor area up +20% or modifications exceeding 50% of replacement value), Sec. 10-187(c) requires street frontage improvements (curb, gutter, sidewalk, pavement, storm drainage) to be installed/upgraded at the applicant's sole cost before a Certificate of Occupancy will be issued — budget and plan for this early.
- There is no dedicated change-of-use or Certificate of Occupancy application form; use the standard Building Permit Application and describe the occupancy change in the scope of work.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Stevensville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Stevensville
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Montana →
Look up this fee in a different city →
Now live
Build your Stevensville project checklist
Describe your project once and get every permit, document, and fee it triggers in Stevensville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →