Residential Solar Photovoltaic (PV) Permit — State-Issued Electrical Permit Add-On — Forsyth, Montana · Requirements sheet
Verified 2026-07-20 · Source: https://bsd.dli.mt.gov/building-codes-permits/permit-applications/electrical-permits/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Solar Photovoltaic (PV) Permit — State-Issued Electrical Permit Add-On in Forsyth, Montana
Because Forsyth holds no DLI certification in Electrical (only a residential-only Building certification), rooftop or ground-mount residential solar PV installation within Forsyth city limits is not a separate stand-alone permit — it is billed and processed as an Alternative Energy Source add-on to the state-issued Residential Electrical Permit, issued directly by the Montana Department of Labor & Industry Building Codes Bureau (Helena), the same office that issues all electrical permits for Forsyth addresses. The Bureau's statewide Application for Residential Electrical Permit form (BCP-1) itemizes 'Alternative Energy Source (solar/wind/hydro)' as a fixed $65 fee added on top of whichever base electrical work-type fee applies, and requires the applicant to specify system type (Micro Inverter/AC Module System or PV String System). If the racking/mounting requires structural roof modification, that scope would separately require Forsyth's own residential-certified Building permit (or the state's commercial-building-permit-state entry, for non-residential property).
Verified 2026-07-20 · Source
When you need this permit
- Apply using the same statewide Application for Residential Electrical Permit (BCP-1) used for all Forsyth electrical work, since the state DLI Building Codes Bureau (not the city) issues electrical permits for Forsyth addresses
- Select the applicable base work-type fee (e.g., service, change of service) and add the Alternative Energy Source line item
- Specify system type: Micro Inverter/AC Module System or PV String System
- Application must be signed and dated by the licensed electrical contractor's person in charge; payment must be submitted with the application
- Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431
- Governed by the 2020 NEC as currently adopted statewide (Forsyth's own local ordinance text at 11-1-1 references the older 2014 NEC for its own — inapplicable to this state-enforced trade — reference)
- If structural roof/mounting modification is needed, that scope separately requires a Forsyth residential Building permit (or the state commercial-building-permit-state track for non-residential property, since Forsyth's Building certification is residential-only)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
Tips
- There is no separate 'solar permit' form or city process in Forsyth — solar PV is a $65 line-item add-on on the same statewide Residential Electrical Permit application used for any other electrical work, filed with the state DLI Building Codes Bureau (not the city), because Forsyth holds no local electrical certification.
- Budget the $65 Alternative Energy Source fee ON TOP OF whichever base electrical fee applies to the underlying work.
- Mail the application and payment to PO Box 200517, Helena, MT 59620-0517, or apply online at ebiz.mt.gov / BuildingPermits.Mt.Gov / aca-prod.accela.com/bcb — not to Forsyth City Hall.
- If your installation requires structural roof/mounting modification, that scope is a separate matter from the electrical permit: on residential property it would fall under Forsyth's own residential-certified Building permit; the City publishes no fee schedule for that permit, so contact City Hall, (406) 346-2521, for a quote.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Forsyth building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Forsyth
Residential Solar Photovoltaic (PV) Permit — State-Issued Electrical Permit Add-On in other cities
Look up this fee in a different city →
Now live
Build your Forsyth project checklist
Describe your project once and get every permit, document, and fee it triggers in Forsyth — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →