EV Charger / Electric Vehicle Charging Circuit Permit (State-Issued) in Forsyth, Montana

Because Forsyth holds no DLI certification in Electrical (only a residential-only Building certification), an EV charger/EVSE circuit anywhere within Forsyth city limits requires the same state-issued Residential or Commercial Electrical Permit documented in the electrical-permit-state entry, issued directly by the Montana DLI Building Codes Bureau in Helena — not the City of Forsyth. The Bureau's statewide Application for Residential Electrical Permit form (BCP-1, Rev. 11/25) has no line item specifically labeled 'EV charger' or 'electric vehicle'; a retrofit EV charging circuit is billed under the 'Single Family Interior/Exterior Wire or Rewire' category as an additional circuit or piece of equipment, and a charger wired into a new single-family service is folded into the base new-service fee (per the amperage tier).

Verified 2026-07-20 · Source

When you need this permit

  • Application must be signed and dated by the licensed electrical contractor's person in charge, or filed as a homeowner permit for owner-performed work
  • For a retrofit EV charger circuit in an existing single-family home, select 'Single Family Interior/Exterior Wire or Rewire' and check the applicable box: '1 additional circuit or piece of equipment' or '2-3 additional circuits or pieces of equipment'
  • For a new single-family home wired with an EV charger circuit at the same time as the main service, no separate line item applies — it is included in the base new-service fee (per the amperage tier, A-D)
  • Payment must be submitted with the application; incomplete applications are returned unprocessed
  • Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

1 additional circuit or piece of equipment (retrofit EV charger circuit)Montana Building Codes Bureau, Application for Residential Electrical Permit (BCP-1, Rev. 11/25) — 'Single Family Interior/Exterior Wire or Rewire' category, item H; no distinct EV-charger line item exists on the form, so a single dedicated EVSE circuit is billed at this generic per-item rate
$45
2-3 additional circuits or pieces of equipmentMontana Building Codes Bureau, Application for Residential Electrical Permit — item G; applies if the EV charger installation is bundled with other new circuits/equipment
$70
4+ circuits & change of service and/or interior panel (if a panel upgrade is needed to support the charger)Montana Building Codes Bureau, Application for Residential Electrical Permit — item E
$120

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / Electric Vehicle Charging Circuit Permit (State-Issued) permit actually take in Forsyth?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • There is no EV-charger-specific line item on Montana's statewide electrical permit form — an EV charger circuit retrofit is billed as a generic additional circuit/equipment item ($45 for one, $70 for 2-3), the same category used for any other new circuit or equipment addition.
    • Electrical permits for any Forsyth address (residential OR commercial) are issued by the STATE Building Codes Bureau in Helena, not the city — mail applications and payment to PO Box 200517, Helena, MT 59620-0517, or apply online at ebiz.mt.gov / aca-prod.accela.com/bcb.

    Frequently asked questions

    Forsyth requires an ev charger / electric vehicle charging circuit permit (state-issued) for: Application must be signed and dated by the licensed electrical contractor's person in charge, or filed as a homeowner permit for owner-performed work; For a retrofit EV charger circuit in an existing single-family home, select 'Single Family Interior/Exterior Wire or Rewire' and check the applicable box: '1 additional circuit or piece of equipment' or '2-3 additional circuits or pieces of equipment'; For a new single-family home wired with an EV charger circuit at the same time as the main service, no separate line item applies — it is included in the base new-service fee (per the amperage tier, A-D); Payment must be submitted with the application; incomplete applications are returned unprocessed; Apply in accordance with Title 50, Chapter 60, Section 604, MCA and ARM 24.301.431. If your project isn't listed, confirm with City of Forsyth Building Department — city-certified for Building (B), RESIDENTIAL ONLY per the Montana DLI Building Codes Bureau's certified-jurisdiction roster (certified official on file: Gabe Martinsen). Commercial building permits, and Electrical, Plumbing, and Mechanical/HVAC permits of ANY project type, within Forsyth city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. Rosebud County itself performs NO building or electrical permitting function for the city or the unincorporated county — confirmed directly on the Rosebud County Planner page. at (406) 346-2521 before starting work.

    In Forsyth, the published 1 additional circuit or piece of equipment (retrofit EV charger circuit) is: $45. Additional published fees: 2-3 additional circuits or pieces of equipment — $70; 4+ circuits & change of service and/or interior panel (if a panel upgrade is needed to support the charger) — $120. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Forsyth does not publish a plan-review timeline for this permit. Contact City of Forsyth Building Department — city-certified for Building (B), RESIDENTIAL ONLY per the Montana DLI Building Codes Bureau's certified-jurisdiction roster (certified official on file: Gabe Martinsen). Commercial building permits, and Electrical, Plumbing, and Mechanical/HVAC permits of ANY project type, within Forsyth city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. Rosebud County itself performs NO building or electrical permitting function for the city or the unincorporated county — confirmed directly on the Rosebud County Planner page. at (406) 346-2521 for current turnaround.

    You'll need: Application for Residential Electrical Permit. See the required-documents checklist on this page for details on each.

    Apply through City of Forsyth Building Department — city-certified for Building (B), RESIDENTIAL ONLY per the Montana DLI Building Codes Bureau's certified-jurisdiction roster (certified official on file: Gabe Martinsen). Commercial building permits, and Electrical, Plumbing, and Mechanical/HVAC permits of ANY project type, within Forsyth city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. Rosebud County itself performs NO building or electrical permitting function for the city or the unincorporated county — confirmed directly on the Rosebud County Planner page. at City Hall, 247 N 9th Ave, Forsyth, MT 59327. Phone: (406) 346-2521, email: Not published; contact City Hall at (406) 346-2521. Office hours: City Hall, 247 N 9th Ave, Forsyth, MT 59327, Monday-Friday (hours not published online as of this review). City Hall main line (406) 346-2521. The City of Forsyth's own website (forsythmt.info) is a Wix-hosted site whose 'Permit Application' and 'Code Information Consultation' pages are generic Wix Bookings service-page templates with no published fee schedule, application form, or department-specific contact beyond the main city phone number; no dedicated Building Department staff directory, direct-dial extension, or department email was found published anywhere on the site as of this review.. Official information: https://www.forsythmt.info/.

    Forsyth, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; non-certified trades — and, where a city's Building certification is itself partial (e.g. residential-only), non-certified project types — fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs (bsd.dli.mt.gov/building-codes-permits).; Forsyth is a Montana DLI-certified jurisdiction for Building (B), RESIDENTIAL ONLY, within city limits; certified official on file with DLI: Gabe Martinsen, 406-346-2521. Verified directly against the DLI Building Codes Bureau's 'Montana Certified Local Government Program' roster PDF, updated 04/22/2026 (fetched and text-extracted directly from the source PDF): 'Forsyth | B (residential only) | Gabe Martinsen | 406-346-2521 | City Limits'. Note: Gabe Martinsen is ALSO the certified official listed for Miles City, MT (B, M, SP, E (residential only)) on the same roster — a single official serving two separate certified programs is plausible (shared regional building inspector) but was not independently confirmed beyond the roster entry itself. Source: https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf; Colstrip, MT — also within Rosebud County — holds its OWN INDEPENDENT Montana DLI certification for Building (B), RESIDENTIAL ONLY, with a DIFFERENT certified official (Russell Murphy, 853-5084) and a different city-limits jurisdiction line on the same roster: 'Colstrip | B (residential only) | Russell Murphy | 853-5084 | City Limits'. This confirms Forsyth and Colstrip run INDEPENDENT city-level certified Building programs — they do NOT share a single county-level program, despite both being located in Rosebud County. Rosebud County itself does not appear on the DLI roster as a certified jurisdiction in its own right. Source: Montana DLI Building Codes Bureau, Certified Local Government Program roster PDF (updated 04/22/2026); Rosebud County's own Planning & Permitting department (County Planner page, rosebudcountymt.gov) explicitly states: 'Building and electrical permits are not required through Rosebud County, but may be required by the State of Montana.' The County Planner's office assists the City of Forsyth, City of Colstrip, unincorporated communities, and independent boards within Rosebud County with subdivision, flood plain, zoning, and septic permitting only — NOT building or electrical permitting, which is consistent with Forsyth and Colstrip each running their own independent city-level DLI-certified Building programs rather than a county-administered one. Source: https://rosebudcountymt.gov/departments/county-planner/; Forsyth, MT Code of Ordinances, Title 11 Building Regulations, Chapter 1 Building Code, Section 11-1-1 'Building Codes Adopted' (current through Ord. 2024-11, passed 12-16-2024; section itself amended by Ord. 01-2014 1-12-2015, amd. Ord. 2020-01 6-8-2020, Res. 2021-R04 4-12-2021) adopts by reference: International Building Code 2012 edition (per ARM 24.301.131, including Appendix Chapter C group U agricultural buildings, and ARM 24.301.146); Residential Building Code 2018 edition; International Energy Conservation Code 2018 edition (per ARM 24.301.161); International Existing Building Code 2012 edition (per ARM 24.301.171); National Electric Code 2014 edition (NFPA 70, per ARM 24.301.401); International Mechanical Code 2012 edition (per ARM 24.301.172); International Fuel Gas Code 2012 edition (per ARM 24.301.173); Uniform Plumbing Code 2012 edition (per ARM 24.301.301); Building Accessibility Rules per ARM 24.301.901-905; and Optional Appendix Chapters B (Board of Appeals) and H (Signs) per ARM 24.301.134. Section 11-1-1(B) states these codes 'are applicable to all buildings within the building code enforcement area of Forsyth as provided by section 50-60-102, Montana Code Annotated.' Note the adopted code editions (2012 IBC/IMC/IFGC/UPC/IEBC, 2014 NEC, 2018 IRC/IECC) are OLDER than the state's current statewide-effective editions (2021 IBC/IRC/IEBC/IMC/IFGC/IECC/ISPSC/UPC, 2020 NEC per the DLI Building Codes Bureau's Current Codes page effective June 11, 2022) — Forsyth's local ordinance text has not been updated to match the state's most recent code-adoption cycle, though the state-enforced trades (Electrical, Plumbing, Mechanical) in Forsyth are governed by whatever edition the state DLI Building Codes Bureau currently applies statewide, not this local ordinance text. Source: https://codelibrary.amlegal.com/codes/forsythmt/latest/forsyth_mt/0-0-0-1929; Per the Montana DLI Building Codes Bureau's Current Codes page (statewide effective date June 11, 2022, applicable to all state-enforced trades and jurisdictions, including Forsyth's state-routed commercial building and its Electrical/Plumbing/Mechanical permits): 2021 IBC, 2021 IRC, 2021 IEBC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 ISPSC, 2021 UPC, 2020 NEC, 2017 ICC A117.1 Accessibility. Source: bsd.dli.mt.gov/building-codes-permits/current-codes. Local amendments apply — see the Forsyth overview page for the full list.

    No. There is no EV-specific permit or fee. An EV charger circuit is billed and processed as a generic additional-circuit item ($45 for one circuit, $70 for 2-3) on the same statewide Residential Electrical Permit application used for any other electrical work, issued by the Montana DLI Building Codes Bureau since Forsyth holds no local Electrical certification.