Demolition Permit in Glasgow, Montana
Required for demolition of any structure within Glasgow city limits. Issued by the City of Glasgow Office of Public Works. Requires documented utility disconnection and inspected removal of footings/foundations and sewer-line plugging before close-out.
Verified 2026-07-03 · Source
When you need this permit
- Demolition permit application must include address/location of demolition, legal description (lot, block, subdivision), owner and contractor contact information, and bonding certificate status
- City sewer lines must be plugged at the property line and inspected
- Footing and foundation must be removed and inspected
- Septic systems addressed per the form's septic line item (coordination with relevant health/septic authority implied)
- Utilities (electrical, gas, telephone, cable, sanitary sewer, water) must be disconnected/turned off, with each utility's disconnection signed and dated directly on the permit form before or upon demolition
- Permit fee must be paid (cash, check, or billed) to the Director of Public Works, Public Works Assistant, or City Clerk
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation Removal and Sewer Line Plugging
City sewer lines must be plugged at the property line and inspected; footing and foundation must be removed and inspected, per the Demolition Permit form
See the full Glasgow inspection guide — scheduling & re-inspection fees →
Tips
- The Demolition Permit form has a dedicated line for 'Bonding Certificate on File yes/no' — confirm with Public Works whether a bond is required for your specific project before applying.
- Utility disconnection must be documented directly on the permit form (electrical, gas, telephone, cable, sanitary sewer, water), each with a signature and date — coordinate with each utility provider in advance of your planned demolition date.
- Commercial demolition fees range from $150 to $500 depending on project specifics per City Code Sec. 8-117 — contact Public Works, (406) 228-2476, for the exact fee applicable to your project.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glasgow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Glasgow
Demolition Permit in other cities
Compare demolition permit fees across Montana →