Commercial Building Permit (New Construction / Addition / Alteration / Remodel) — Glasgow, Montana · Requirements sheet
Verified 2026-08-26 · Source: https://www.cityofglasgowmt.com/_files/ugd/2ff7f3_a263251865d842a9b7db016c72ebf448.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction / Addition / Alteration / Remodel) in Glasgow, Montana
Required for new commercial construction, additions, alterations, and remodels within Glasgow city limits. Glasgow runs ONE Application for Building Permit covering residential and commercial construction alike -- there is no separate commercial application form -- issued by the City of Glasgow Public Works/Building Codes Department under its DLI-certified local Building (B) program. The City's own Building Permit Packet states plainly that 'Building Permits are issued by the City of Glasgow for all new residential and commercial structures including alterations and additions,' and carries commercial-specific plan-count, drawing-scale, and stamping requirements within that same combined process (see requirements below).
Verified 2026-08-26 · Source
When you need this permit
- Same Building Permit Application used for residential work, completed for a commercial class of work: owner, contractor, and architect/engineer contact information; legal description; valuation of work; type of construction
- Commercial new construction requires 3 complete sets of plans submitted for review; commercial remodel requires 3 complete sets of plans -- both a higher plan-set count than the 2-set minimum for a residential remodel/garage project. Source: City of Glasgow Building Permit Packet, page 2
- Construction/floor plans for a commercial structure must be drawn at a scale not less than 1/8 inch = 1 foot, versus not less than 1/4 inch = 1 foot for residential structures. Source: City of Glasgow Building Permit Packet, page 8 (Construction Plans)
- All commercial plans for public buildings must be wet-stamped (each set original-stamped) by a Montana-licensed architect or engineer. Source: City of Glasgow Building Permit Packet, page 3
- For a commercial building structure, multiple cross sections are required (more than the one or two typically sufficient for a garage or house). Source: City of Glasgow Building Permit Packet, page 2
- Submitted roof truss diagrams must bear the seal of a Montana-licensed professional engineer; a single stamped component (e.g., a truss plan) does not by itself satisfy the requirement that the whole facility was designed by an architect for a commercial building open to the public. Source: City of Glasgow Building Permit Packet, page 5
- As of Ordinance No. 966 (effective July 27, 2020): property pins must be established and clearly visible before permit issuance for any new building project or any project that modifies an existing structure's footprint; the Building Inspector must witness the pins in place, or a licensed surveyor must establish them first
- Projects within the designated 500-foot Critical Zone of the Glasgow/Cherry Creek/Milk River Levee require mandatory additional review by the U.S. Army Corps of Engineers before the City can issue an approved permit
- Electrical, Plumbing, and Mechanical work for a commercial project are not covered by this permit -- Glasgow holds DLI certification for Building (B) only, so those trades require separate permits issued directly by the Montana DLI Building Codes Bureau (see the electrical-permit-state, plumbing-permit-state, and mechanical-permit-state permit types documented separately)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
No fixed valuation-based fee schedule is published for the commercial building permit, the same gap documented on this jurisdiction's residential-building-permit entry. Show full citationHide
No fixed valuation-based fee schedule is published for the commercial building permit, the same gap documented on this jurisdiction's residential-building-permit entry. Checked: City of Glasgow Code of Ordinances Chapter 8 (Buildings and Building Regulations) -- the only codified fee schedule in the chapter is Sec. 8-117, which is limited to demolition permit fees; the City's Building Permit Packet (which contains no dollar figures for any building-permit class); the Public Works Department page; and Municode (library.municode.com/mt/glasgow). No figure is shown rather than an estimate; applicants must contact the Building Codes Department at (406) 228-2476 ext. 8 or codecompliance@cityofglasgowmt.com for a current fee quote. Electrical, Plumbing, and Mechanical permits for the same commercial project are separate state-issued permits with their own fee schedules -- see the electrical-permit-state, plumbing-permit-state, and mechanical-permit-state permit types documented separately.Review timeline
Inspection process
See the full Glasgow inspection guide — scheduling & re-inspection fees →
Tips
- Glasgow has no dedicated commercial application -- the same Application for Building Permit used for residential work is filed for commercial construction, with a commercial class of work and the higher plan-set count (3 sets for both new construction and remodel).
- Commercial construction/floor plans must be drawn at 1/8 inch = 1 foot, twice as fine a scale requirement as the 1/4 inch = 1 foot minimum for residential plans.
- A commercial public building's plans must be wet-stamped (originally stamped, not photocopied) by a Montana-licensed architect or engineer on every set -- one stamped component like a truss plan does not satisfy this for the whole structure.
- Budget for a materially longer review than residential work: the City's own packet states 2-4 weeks for minor commercial projects and 3-6 weeks for major commercial projects, against 4-7 working days for typical residential/accessory work.
- The City of Glasgow does not issue Electrical, Plumbing, or Mechanical permits for a commercial project -- these are obtained separately from the Montana DLI Building Codes Bureau, since Glasgow's DLI certification covers Building (B) only.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-26.
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glasgow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Glasgow.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Glasgow
Commercial Building Permit (New Construction / Addition / Alteration / Remodel) in other cities
Look up this fee in a different city →
Now live
Build your Glasgow project checklist
Describe your project once and get every permit, document, and fee it triggers in Glasgow — in one checklist. Free, for any city and any number of projects.
Get started →