Change of Use / Change of Occupancy (Certificate of Occupancy) in Glasgow, Montana
Glasgow does not have a standalone Change of Use or Certificate of Occupancy application, product, or fee. A 'CHANGE OF OCCUPANCY FROM ____ TO ____ OCCUPANCY' field is built directly into the City's standard Application for Building Permit -- the same combined form used for all new construction, additions, and alterations -- confirmed by direct text extraction of the current, live Building Permit Packet PDF (page 6, Legal Description section of the application form). This means a change of use/occupancy in Glasgow is processed as a Building-Permit-class action through the Public Works/Building Codes Department, not through a separate certificate-of-occupancy office or process. Montana state law, MCA 50-60-107, separately establishes that 'a certificate of occupancy for a building constructed in accordance with the provisions of the state building code or county, city, or town building code must certify that the building conforms to the requirements of the building regulations applicable to it,' and that such a certificate, once issued, is binding and conclusive on all local agencies unless set aside by a court.
Verified 2026-07-22 · Source
When you need this permit
- File the standard Application for Building Permit, completing the 'CHANGE OF OCCUPANCY FROM ___ TO ___ OCCUPANCY' field in the Legal Description section, alongside standard owner/contractor/architect contact information and the class-of-work designation
- Same supporting materials as any other Building Permit application apply where relevant to the change (e.g., plot plan, construction/floor plan) if the change of occupancy involves any physical alteration; per MCA 50-60-107 the certificate must certify the building conforms to applicable building regulations for the new occupancy
- No separate change-of-use or certificate-of-occupancy fee, form, or office was found distinct from the general Building Permit process -- this KB's residential-building-permit entry documents the same unresolved fee-schedule gap that would apply here
- Because Glasgow is Building-certified but not Electrical/Plumbing-certified (see codesAdopted), a change of occupancy involving those trades would still require separate State DLI-issued Electrical/Plumbing permits per this KB's electrical-permit-state and plumbing-permit-state entries
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Glasgow inspection guide — scheduling & re-inspection fees →
Tips
- Glasgow does not issue a separate 'Certificate of Occupancy' document or maintain a distinct change-of-use office -- a change of occupancy is simply a field on the same Application for Building Permit used for new construction, additions, and alterations.
- Under Montana state law (MCA 50-60-107), a properly issued certificate of occupancy is binding on all local agencies -- keep your issued Building Permit/occupancy documentation on file as your proof of compliance for the approved occupancy classification.
- If your change of use also involves physical alteration work (walls, additions, etc.) or trade work outside the City's Building-only certification, budget for the corresponding separate City Building Permit requirements and/or State DLI Electrical/Plumbing/Mechanical permits documented elsewhere in this KB.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glasgow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Glasgow
Change of Use / Change of Occupancy (Certificate of Occupancy) in other cities
Compare change of use / change of occupancy (certificate of occupancy) fees across Montana →
Look up this fee in a different city →
Now live
Build your Glasgow project checklist
Describe your project once and get every permit, document, and fee it triggers in Glasgow — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →