EV Charger / Electric Vehicle Charging Station Permit in Glasgow, Montana

Montana has no dedicated EV-charger permit type or line item, and Glasgow is not electrically-certified, so installing a Level 2 (240V) home EV charger or EVSE within Glasgow city limits requires a State of Montana Electrical Permit issued directly by the DLI Building Codes Bureau, billed under the same general residential wiring/circuit line items used for any new dedicated circuit or service upgrade -- there is no separate 'EV charger' or 'EVSE' line item on the state's Residential Electrical Permit application. A City Building Permit is NOT required unless the installation also involves new structural work (e.g., a new carport/canopy). Re-chased 2026-07-20: directly downloaded and text-extracted the live State electrical permit PDF, confirming the $45/$70 additional-circuit lines and $200 up-to-200-amp service line are still current verbatim.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical work must be performed and the permit pulled by a Montana-licensed electrical contractor (LCO/UCO), per the Application for Residential Contractor Electrical Permit (Rev 6/24)
  • If the EV charger is added as a new dedicated circuit to an existing panel with no service/panel change, this is billed under the form's 'Single Family Interior/Exterior Wire or Rewire' section, line H ('1 additional circuit or piece of equipment') or line G ('2-3 additional circuits or pieces of equipment') depending on scope
  • If the installation requires a panel upgrade or new/upsized electrical service to support the charger's amperage draw, it is billed instead under the amperage-based 'Single Family Dwelling or Cabin' service tiers (A-D) rather than the additional-circuit lines
  • The state application form has no Alternative-Energy-style checkbox or dedicated question set for EV chargers (unlike its Solar/Wind/Hydro section) -- EVSE is treated as ordinary residential branch-circuit wiring
  • Job address, county, and whether the job is inside city limits must be indicated on the application; property owner and licensed electrical contractor information required
  • A City of Glasgow Building Permit is required in addition if the EVSE is mounted on, or paired with, new structural construction (e.g., a new carport or accessory structure) per the City's general building-permit trigger list -- not required for a simple wall/pedestal-mounted charger on an existing structure

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

1 additional circuit or piece of equipment (e.g., a single EV charger circuit added to an existing panel)Montana Building Codes Bureau, Application for Residential Contractor Electrical Permit (Rev 6/24), line H -- no distinct 'EV charger'/'EVSE' line item exists on the state form; this is the general additional-circuit line an electrical contractor would use for a single new EV charger circuit, confirmed directly against the current fee schedule PDF. Confirm classification with the Building Codes Bureau, (406) 841-2056, before applying, since routing between lines G/H/service-tier depends on the specific scope of work. Re-confirmed live 2026-07-20 via direct PDF text extraction.
$45
2-3 additional circuits or pieces of equipment (e.g., EV charger plus other new circuits in the same job)Application for Residential Contractor Electrical Permit (Rev 6/24), line G Re-confirmed live 2026-07-20 via direct PDF text extraction.
$70
Single Family Dwelling or Cabin -- up to 200-amp service (if the EV charger install requires a new/upgraded service)Application for Residential Contractor Electrical Permit (Rev 6/24), line A -- applies if a panel/service upgrade is needed to support charger load rather than a simple additional circuit Re-confirmed live 2026-07-20 via direct PDF text extraction.
$200
Request Inspection, per hourApplication for Residential Contractor Electrical Permit (Rev 6/24) Re-confirmed live 2026-07-20 via direct PDF text extraction.
$60 (plus $30 per additional 30 minutes or fraction thereof, plus travel time)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / Electric Vehicle Charging Station Permit permit actually take in Glasgow?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Performed by the Montana Building Codes Bureau's regional electrical inspector; new circuit, breaker sizing, and disconnect (if required by the charger manufacturer) verified before energizing

See the full Glasgow inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated 'EV charger' or 'EVSE' checkbox anywhere on Montana's state electrical permit form -- unlike solar, which gets its own Alternative Energy Source question set, an EV charger circuit is simply billed as ordinary new/additional wiring.
  • Whether your job falls under the flat additional-circuit fee ($45-$70) or the amperage-based service tiers depends on whether your existing panel has enough spare capacity -- ask your electrical contractor to specify this on the application.
  • Because Glasgow is not electrically-certified, do not attempt to pull this permit from the City -- it must go to the State DLI Building Codes Bureau in Helena, the same office that handles Glasgow's other electrical work.
  • No separate City permit is needed for a straightforward wall-mounted or pedestal EV charger with no new structure; only pull a City Building Permit as well if you're also constructing a new carport or similar structure to house it.

Frequently asked questions

Glasgow requires an ev charger / electric vehicle charging station permit for: Electrical work must be performed and the permit pulled by a Montana-licensed electrical contractor (LCO/UCO), per the Application for Residential Contractor Electrical Permit (Rev 6/24); If the EV charger is added as a new dedicated circuit to an existing panel with no service/panel change, this is billed under the form's 'Single Family Interior/Exterior Wire or Rewire' section, line H ('1 additional circuit or piece of equipment') or line G ('2-3 additional circuits or pieces of equipment') depending on scope; If the installation requires a panel upgrade or new/upsized electrical service to support the charger's amperage draw, it is billed instead under the amperage-based 'Single Family Dwelling or Cabin' service tiers (A-D) rather than the additional-circuit lines; The state application form has no Alternative-Energy-style checkbox or dedicated question set for EV chargers (unlike its Solar/Wind/Hydro section) -- EVSE is treated as ordinary residential branch-circuit wiring; Job address, county, and whether the job is inside city limits must be indicated on the application; property owner and licensed electrical contractor information required; A City of Glasgow Building Permit is required in addition if the EVSE is mounted on, or paired with, new structural construction (e.g., a new carport or accessory structure) per the City's general building-permit trigger list -- not required for a simple wall/pedestal-mounted charger on an existing structure. If your project isn't listed, confirm with City of Glasgow Public Works Department / Building Codes Department — Rod Dees, Code Compliance Officer; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Glasgow city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 228-2476 before starting work.

If added as a single new circuit to an existing panel, $45 under line H ('1 additional circuit or piece of equipment') of the state's Application for Residential Contractor Electrical Permit (Rev 6/24). If a service/panel upgrade is also needed, the amperage-based service fee tiers ($200-$800) apply instead.

Glasgow does not publish a plan-review timeline for this permit. Contact City of Glasgow Public Works Department / Building Codes Department — Rod Dees, Code Compliance Officer; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Glasgow city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at (406) 228-2476 for current turnaround.

You'll need: Application for Residential (or Commercial) Contractor Electrical Permit. See the required-documents checklist on this page for details on each.

Glasgow requires 1 inspection(s) for an ev charger / electric vehicle charging station permit, in order: State Electrical Inspection. Schedule each through City of Glasgow Public Works Department / Building Codes Department — Rod Dees, Code Compliance Officer; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Glasgow city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. ((406) 228-2476).

Apply through City of Glasgow Public Works Department / Building Codes Department — Rod Dees, Code Compliance Officer; city-certified for Building (B) permits only. Electrical, Plumbing, and Mechanical permits within Glasgow city limits are issued directly by the Montana Department of Labor & Industry Building Codes Bureau, not the City. at 319 3rd Street South, Glasgow, MT 59230. Phone: (406) 228-2476, email: codecompliance@cityofglasgowmt.com. Office hours: City Hall: Monday-Friday, 8:00 AM-12:00 PM and 1:00 PM-5:00 PM, closed federal holidays. Code Compliance Officer Rod Dees: (406) 228-2476 ext. 8, cell (406) 263-3386. Public Works Department can also be reached at (406) 228-2476 ext. 4 for pre-submittal project discussions.. Official information: https://www.cityofglasgowmt.com/public-works-department.

Glasgow, Montana has adopted: Montana has a mandatory statewide building code administered by the Montana Department of Labor & Industry (DLI) Building Codes Bureau, amended by the Administrative Rules of Montana (ARM) Title 24, Chapter 301. Cities, counties, and towns may become 'certified' to locally administer permitting and inspection for all or part of the code; non-certified trades in a partially-certified jurisdiction fall under direct state administration by the DLI Building Codes Bureau. Source: Montana DLI Building Codes Bureau, Certified City, County and Town Programs list (bsd.dli.mt.gov/building-codes-permits).; Glasgow is a Montana DLI-certified jurisdiction for Building (B) ONLY within city limits; certified building official on file with DLI: Rod Dees, (406) 228-2476. Source: Montana DLI Building Codes Bureau, 'Montana Certified Local Government Program' roster, updated 04/22/2026, https://bsd.dli.mt.gov/_docs/building-codes-permits/certified-city.pdf — verified directly against the PDF: 'Glasgow | B | Rod Dees | 228-2476 | City Limits'.; Per the City of Glasgow's own 'General Information for Building Permit Applications' packet (Public Information Sheet GIPBA No. 4, dated 11/17/2021): all building designs and plans must adhere to the 2018 International Residential Code, 2018 International Building Code, 2018 International Mechanical Code, 2018 International Existing Building Code, 2018 International Fuel Gas Code, 2018 International Swimming Pool and Spa Code, 2012 International Energy Code, and the 2018 Uniform Plumbing Code, plus applicable local zoning codes. Source: City of Glasgow Building Permit Packet, cityofglasgowmt.com/_files/ugd/2ff7f3_a263251865d842a9b7db016c72ebf448.pdf; Note on code-edition discrepancy: the City's own packet (last dated 2021) cites 2018-edition I-codes and the 2012 IECC, while the Montana DLI Building Codes Bureau's statewide 'Current Codes' page lists the newer 2021-edition codes (2021 IBC, IRC, IMC, IFGC, ISPSC, IEBC, UPC; 2021 IECC; 2020 NEC) as effective statewide since June 11, 2022. Because Glasgow is a certified local Building program, ARM 24.301.202 requires its adopted code to be one 'adopted by the Building Codes Bureau' — the City's own document may not have been updated to reflect the 2021-cycle codes. This discrepancy is reported as found rather than resolved by assumption; applicants should confirm current code edition in effect with the City Building Codes Department, (406) 228-2476 ext. 8. Source: bsd.dli.mt.gov/building-codes-permits/current-codes vs. City of Glasgow Building Permit Packet.; The City of Glasgow's own Building Permit Packet contains an internal inconsistency regarding Mechanical permits: one bullet in the 'General Information' page states 'The City of Glasgow also issues plumbing/mechanical permits,' while a later 'NOTICE' section in the same packet states plainly: 'The City of Glasgow covers Building Permits and Mechanical Permits; the State of Montana issues plumbing and electrical plans for work in the city.' The DLI's own certified-jurisdictions roster (updated 04/22/2026) lists Glasgow's certification as 'B' ONLY, with no 'M' code shown (contrast with e.g. Havre or Choteau, also 'B' only, or Belgrade/Billings which show explicit 'M' certification). Given the DLI roster is the authoritative statewide certification record, this KB treats Mechanical permits in Glasgow as STATE-ISSUED (routed to the DLI Building Codes Bureau) consistent with the official 'B'-only certification, while flagging the City's own document's contrary claim as an unresolved discrepancy applicants should verify directly with (406) 228-2476 ext. 8 before assuming which office issues a mechanical permit.. Local amendments apply — see the Glasgow overview page for the full list.

No. Neither the State of Montana DLI Building Codes Bureau nor the City of Glasgow has a dedicated EV-charger or EVSE permit type or fee line. A home Level 2 charger is permitted as ordinary residential electrical wiring under the State's standard Residential Electrical Permit (Glasgow is not electrically-certified, so this is state-issued, not city-issued).