EV Charger / Electric Vehicle Charging Station Permit in Glasgow, Montana
Montana has no dedicated EV-charger permit type or line item, and Glasgow is not electrically-certified, so installing a Level 2 (240V) home EV charger or EVSE within Glasgow city limits requires a State of Montana Electrical Permit issued directly by the DLI Building Codes Bureau, billed under the same general residential wiring/circuit line items used for any new dedicated circuit or service upgrade -- there is no separate 'EV charger' or 'EVSE' line item on the state's Residential Electrical Permit application. A City Building Permit is NOT required unless the installation also involves new structural work (e.g., a new carport/canopy). Re-chased 2026-07-20: directly downloaded and text-extracted the live State electrical permit PDF, confirming the $45/$70 additional-circuit lines and $200 up-to-200-amp service line are still current verbatim.
Verified 2026-07-20 · Source
When you need this permit
- Electrical work must be performed and the permit pulled by a Montana-licensed electrical contractor (LCO/UCO), per the Application for Residential Contractor Electrical Permit (Rev 6/24)
- If the EV charger is added as a new dedicated circuit to an existing panel with no service/panel change, this is billed under the form's 'Single Family Interior/Exterior Wire or Rewire' section, line H ('1 additional circuit or piece of equipment') or line G ('2-3 additional circuits or pieces of equipment') depending on scope
- If the installation requires a panel upgrade or new/upsized electrical service to support the charger's amperage draw, it is billed instead under the amperage-based 'Single Family Dwelling or Cabin' service tiers (A-D) rather than the additional-circuit lines
- The state application form has no Alternative-Energy-style checkbox or dedicated question set for EV chargers (unlike its Solar/Wind/Hydro section) -- EVSE is treated as ordinary residential branch-circuit wiring
- Job address, county, and whether the job is inside city limits must be indicated on the application; property owner and licensed electrical contractor information required
- A City of Glasgow Building Permit is required in addition if the EVSE is mounted on, or paired with, new structural construction (e.g., a new carport or accessory structure) per the City's general building-permit trigger list -- not required for a simple wall/pedestal-mounted charger on an existing structure
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed by the Montana Building Codes Bureau's regional electrical inspector; new circuit, breaker sizing, and disconnect (if required by the charger manufacturer) verified before energizing
See the full Glasgow inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated 'EV charger' or 'EVSE' checkbox anywhere on Montana's state electrical permit form -- unlike solar, which gets its own Alternative Energy Source question set, an EV charger circuit is simply billed as ordinary new/additional wiring.
- Whether your job falls under the flat additional-circuit fee ($45-$70) or the amperage-based service tiers depends on whether your existing panel has enough spare capacity -- ask your electrical contractor to specify this on the application.
- Because Glasgow is not electrically-certified, do not attempt to pull this permit from the City -- it must go to the State DLI Building Codes Bureau in Helena, the same office that handles Glasgow's other electrical work.
- No separate City permit is needed for a straightforward wall-mounted or pedestal EV charger with no new structure; only pull a City Building Permit as well if you're also constructing a new carport or similar structure to house it.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Glasgow building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Glasgow
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Montana →
Look up this fee in a different city →