Commercial Building Permit (Building, Electrical, Plumbing & Mechanical Permit) — Wells, Nevada · Requirements sheet
Verified 2026-08-26 · Source: https://cityofwellsnv.com/wp-content/uploads/2024/04/Building-Permit-Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (Building, Electrical, Plumbing & Mechanical Permit) in Wells, Nevada
The City of Wells has no application dedicated to commercial work — commercial construction, additions, remodels, and tenant build-outs are filed on the same universal Building, Electrical, Plumbing & Mechanical Permit application used for every occupancy (see building-permit), which itself lists 'Commercial' as one of three project-type checkboxes alongside Residential and Manufactured Home. What is genuinely commercial-specific: the City's adopted technical code is the 2012 International Building Code (City Code of Wells, Title 4, Chapter 1, Section 4-1-1(A)(1)), the same section that adopts the 2012 International Existing Building Code governing alterations and changes of occupancy in existing buildings; and City Council Resolution No. 19-04 prices Mechanical, Plumbing, and Electrical work done under a 'Commercial occupancy and construction type' classification by a per-square-foot valuation that varies by 2009 IBC occupancy group (Table 7), rather than the flat per-fixture or per-unit charges used for one- and two-family residential work in those same fee tables. The Building Permit Fee itself and its Plan Review Fee (65% of the Building Permit Fee) are billed off one citywide valuation table with no separate, higher commercial rate — unlike some Nevada cities, Wells does not publish a commercial-specific plan-review percentage.
Verified 2026-08-26 · Source
When you need this permit
- Completed universal Building, Electrical, Plumbing & Mechanical Permit application with 'Commercial' selected as the Permit Type, and Building and/or Electrical/Mechanical/Plumbing selected as applicable to the scope
- Assessor's Parcel Number, job site address, and Value of Project Work
- Contractor (with Nevada contractor license number) and, where applicable, Electrical/Mechanical/Plumbing sub-contractor license numbers Contractor
- Engineer of Record and/or Architect of Record license numbers, where applicable to the project
- Construction Type, Occupancy Type, Number of Stories, Occupant Load, and Elevator Flag (office-use fields the Building Department completes to classify the project against the adopted 2012 IBC and against Resolution No. 19-04's occupancy-group valuation tables)
- Applicable special approvals identified: Nevada State Fire Marshal, Nevada State Health, Fire Sprinklers, Engineering, Addressing, and/or Contract Plan Review, as determined by the Building Department
- Work must conform to the adopted 2012 International Building Code and, for alterations or a change of occupancy in an existing structure, the adopted 2012 International Existing Building Code
- A Certificate of Occupancy — the City's own Zoning Code (Title 10, Section 10-2-2) defines this as the Building Department's confirmation that a newly constructed or altered building is complete and safe for occupancy — is the step that actually clears a commercial tenant to open; see occupancy-permit for how it attaches to this same permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
Tips
- There is no separate commercial application at the City of Wells — file the same universal Building, Electrical, Plumbing & Mechanical Permit application used for every project type, selecting 'Commercial' as the Permit Type.
- Wells charges the same Building Permit Fee valuation table and the same 65% Plan Review Fee to commercial, residential, and manufactured-home work — it does not publish a higher commercial plan-review percentage the way some other cities do.
- Commercial mechanical, plumbing, and electrical work is priced differently from residential work within Resolution No. 19-04: a 'Commercial occupancy and construction type' line in each of Tables 3, 4, and 5 bills per square foot at a rate set by 2009 IBC occupancy group (Table 7), rather than the flat per-fixture or per-unit charges used for one- and two-family homes.
- The permit application lists 'Contract Plan Review' as one of several possible 'Special Approvals Required' checkboxes, meaning the Building Department can refer a project's plan review to an outside reviewer at its discretion — but no contracted reviewer, firm, or fee is named anywhere the City publishes, and nothing indicates Elko County's Building and Safety Department performs this role for Wells; confirm directly with the Building Department whether a given commercial project will be referred out.
- Fire review for a commercial project runs through the same channels documented under fire-sprinkler-alarm-permit — the Nevada State Fire Marshal checkbox and/or the City's own Bureau of Fire Prevention under Title 5, Chapter 3 — rather than through a distinct commercial fire-plan-review product or fee.
- A commercial building permit is not the same thing as clearance to open: see occupancy-permit for the Certificate of Occupancy step that the City's Zoning Code (10-2-2) defines as proof a building is complete and safe for use.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-26.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wells building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Wells.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Wells
Commercial Building Permit (Building, Electrical, Plumbing & Mechanical Permit) in other cities
Look up this fee in a different city →
Now live
Build your Wells project checklist
Describe your project once and get every permit, document, and fee it triggers in Wells — in one checklist. Free, for any city and any number of projects.
Get started →