Inspection sequence, scheduling, and re-inspection fees for building permits in Yerington, Nevada.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
14 E. Goldfield Avenue, Yerington, NV 89447
Phone
(775) 463-3511
Office hours
Monday-Friday, 8:00 AM - 5:00 PM. Primary contact: Paul Shapiro, (775) 364-8895 or (775) 463-3511, pauls@yerington.net. Secondary contact: Steve Douglas, Building Inspector, (775) 634-7422, steved@yerington.net. Building Department fax: (775) 463-2284. A 24-hour advance notice is required to schedule inspections. Projects outside city limits fall under Lyon County Building Department, (775) 463-6591.

Published scheduling rules

  • The application states the plan review process 'can take up to ten days for [residential] projects,' versus up to ninety days in some cases for commercial projects — call the Building Department 24 hours ahead to schedule any inspection. (Residential Building Permit (New Construction))
  • A 24-hour advance notice is required to schedule inspections, per the Building Department's general inspection policy (Solar Photovoltaic (PV) Permit)
  • A 24-hour advance notice is required to schedule inspections, per the Building Department's general inspection policy (EV Charger / Electric Vehicle Charging Station Permit)
  • A 24-hour advance notice is required to schedule all inspections; a project is not complete until the Permit Final is signed by a City Building Official, after which a Certificate of Occupancy is issued as required (Commercial Building Permit (New Construction, IBC 2018))

Inspection sequence

Applies to: Commercial Building Permit (New Construction, IBC 2018)

  1. 1

    Construction inspections (structural, plumbing, mechanical, electrical)

    The Building Department inspects building construction projects including structural elements, plumbing, heating/cooling, and electrical systems, per its own department page; a 24-hour advance notice is required to schedule each inspection, and the stamped plan set and permit must be available on site

  2. 2

    Permit Final

    A project is not complete until the Permit Final is signed by a City Building Official (PW106); the Building Department retains the original permit on file

  3. 3

    Certificate of Occupancy

    Issued by the Building Department as required upon the signed Permit Final — see the certificate-of-occupancy-permit entry; there is no separate CO application or fee

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring, box placement, and service connections verified before walls are closed

  2. 2

    Electrical Upgrade Inspection

    Dedicated $85.00 inspection for electrical service/panel upgrades, per City Code 9-1-2-C2

  3. 3

    Final

    Devices installed and panel verified per the adopted 2017 NEC

Applies to: Plumbing Permit (Water Lateral / Sewer Lateral / Septic)

  1. 1

    Underground/Slab

    Before concrete pour or backfill — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    All fixtures connected and verified per the adopted 2018 UPC

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing/Foundation

    Required before concrete pour for additions or deck footings

  2. 2

    Framing

    Structural framing and connections to the existing structure

  3. 3

    Final

    Signed off by a City Building Official before the project is considered complete

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing/Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before insulation or wall cover

  3. 3

    Final

    Project is not complete until the Permit Final is signed by a City Building Official; the Building Department retains the original permit on file and issues a Certificate of Occupancy as required

Applies to: Commercial Tenant Improvement (TI) Permit

  1. 1

    Rough inspections (framing, electrical, plumbing, mechanical as applicable)

    The Building Department inspects structural elements, plumbing, heating/cooling, and electrical systems per its department page; 24-hour advance notice required for each inspection, stamped plans kept on site

  2. 2

    Permit Final

    Project is not complete until the Permit Final is signed by a City Building Official; a Certificate of Occupancy is then issued as required — critical for a tenant space before occupancy

Applies to: Fire Sprinkler / Fire Alarm Permit (Mason Valley Fire District Review)

  1. 1

    Fire District Plan Review

    Plan review and sign-off by the Mason Valley Fire District, required before the City will issue the underlying building permit for commercial work

  2. 2

    Fire Final / Sprinkler-Alarm Acceptance Test

    Final acceptance inspection of the installed fire sprinkler or alarm system, conducted by or on behalf of the Mason Valley Fire District per the adopted 2012 International Fire Code

Applies to: Mechanical / HVAC Permit (Including Wood Stoves)

  1. 1

    Rough-In

    Ductwork and mechanical equipment rough-in before walls are closed; gas piping pressure test before concealment

  2. 2

    Final

    Equipment operational and verified per the adopted 2018 UMC

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, per the 2017 NEC as adopted; 24-hour advance notice required to schedule

  2. 2

    Final

    Racking, roof/ground-mount attachment, and electrical connections verified

Re-inspection fees

Electrical PermitRe-inspection Fee (City Code 9-1-2-C2) · City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
$85.00
Mechanical / HVAC Permit (Including Wood Stoves)Re-inspection Fee (City Code 9-1-2-C2) · City of Yerington Fee Schedule (Revision #33, revised 05/26/2026), Building Department section
$85.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Yerington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Yerington building permits

Get alerts for Yerington

We'll email you when Yerington's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.