Plumbing Permit (Water Lateral / Sewer Lateral / Septic) in Yerington, Nevada
Required for plumbing installation, water/sewer lateral connections, and septic systems in Yerington, governed by the 2018 Uniform Plumbing Code (UPC) as adopted by the City. Standalone site-utility plumbing work (water lateral, sewer lateral, septic) has dedicated flat inspection fees.
Verified 2026-07-03 · Source
When you need this permit
- Plumbing permit required for installation, alteration, or repair of plumbing fixtures, water heaters, gas piping, or sewer/water service lines, governed by the 2018 UPC as adopted by the City of Yerington
- Apply via the universal Building Permit Application (PW106), checking 'Sewer,' 'Water,' 'Septic,' or 'Well' under the For Office Use category block as applicable
- Plumbing Contractor section of the application (name, address, phone, NV Contractors License Number, Yerington Business License Number) must be completed Contractor
- Sewer Lateral Service Permit and Water Lateral Service Permit are each their own dedicated $100.00 inspection fee; Septic Permit (new and replacement) is a dedicated $160.00 inspection fee
- Commercial/industrial sewer fees and connection fees are determined using the Council-approved Uniform Plumbing Code Table 7.3 to calculate Sewer Fixture Units (SFU)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Underground/Slab
Before concrete pour or backfill — verify pipe slope, materials, cleanouts
- 2
Rough-In
After pipes installed, before walls closed
- 3
Final
All fixtures connected and verified per the adopted 2018 UPC
See the full Yerington inspection guide — scheduling & re-inspection fees →
Tips
- No plumbing-permit-specific review timeline is published by the City of Yerington beyond the general application-level language ('up to ten days' residential / 'up to ninety days' commercial). Confirm current turnaround directly with the Building Department at (775) 463-3511.
- Water Lateral and Sewer Lateral Service Permits are each a flat $100.00 inspection fee; a new or replacement Septic Permit is a flat $160.00 inspection fee — all distinct from the project's overall valuation-based building permit fee.
- All fee-schedule utility connection prices assume a 50-foot maximum pipe length; lengths over 50 feet are billed to the contractor/homeowner at the City's actual cost, per the Fee Schedule's Note 2.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Yerington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Yerington
Plumbing Permit (Water Lateral / Sewer Lateral / Septic) in other cities
Compare plumbing permit (water lateral / sewer lateral / septic) fees across Nevada →
Look up this fee in a different city →
Related guides
Now live
Build your Yerington project checklist
Describe your project once and get every permit, document, and fee it triggers in Yerington — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →