Solar Photovoltaic (PV) Permit in Yerington, Nevada

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Yerington. The City's own universal Building Permit Application (PW106) includes a dedicated 'SOLAR' checkbox as its own recognized project category (alongside New, Addition, Re-Roof, Electric, etc.), confirming the City treats solar as a distinct permit type. However, solar is billed through the same general ledger account (01-13-00-3117, 'Building Permit Fee') and the same valuation-based Building Permit Fee / Plan Check Fee used for other construction — the City's Fee Schedule contains no separate dollar-figure line item specific to solar.

Verified 2026-07-20 · Source

When you need this permit

  • Building permit required for the structural/racking portion, applied for via the universal Building Permit Application (PW106) by checking the 'SOLAR' box under the For Office Use category block
  • Governed by the 2018 IBC (commercial) / 2018 IRC (residential) as adopted by the City, per the application's own code-edition header
  • Electrical work (wiring/interconnection) governed by the 2017 NEC as adopted by the City — apply via the same universal application, additionally checking 'ELECTRIC' if not already covered by the SOLAR category, and completing the Electrical Contractor section (NV Contractors License Number, Yerington Business License Number) Contractor
  • A 24-hour advance notice is required to schedule inspections, per the Building Department's general inspection policy

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (SOLAR category, GL 01-13-00-3117)City of Yerington Fee Schedule (Revision #33, revised 05/26/2026) directs Building Permit and Plan Check fees to the City's Building Valuation Data Sheets; no dedicated dollar-figure solar line item exists separate from this general valuation table, though SOLAR is its own checkbox category on the Building Permit Application (PW106) and is billed under the same GL code as the general Building Permit Fee
Valuation-based; determined from the City's Building Valuation Data Sheets (not published online — located at the Building and Planning Department)
Plan Check Fee (GL 01-13-00-3117)City of Yerington Building Permit Application (PW106, Rev. 6, 03/2021), For Office Use block
Valuation-based, same account code as the Building Permit Fee
Inspection Fee: Electrical Upgrade (if applicable)City of Yerington Fee Schedule (Revision #33), Building Department section — same fee documented in this file's electrical-permit entry
$85.00

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Yerington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover, per the 2017 NEC as adopted; 24-hour advance notice required to schedule

  2. 2

    Final

    Racking, roof/ground-mount attachment, and electrical connections verified

See the full Yerington inspection guide — scheduling & re-inspection fees →

Tips

  • Yerington's own Building Permit Application (PW106) has a dedicated 'SOLAR' checkbox distinct from 'ELECTRIC,' 'RE-ROOF,' and other categories — confirming the City tracks solar installations as their own project type, even though the fee itself is calculated under the same general ledger account (01-13-00-3117) and valuation-based Building Permit Fee as any other construction.
  • The City's actual Building Valuation Data Sheets (used to calculate the dollar amount owed) are not published online — they are located only at the Building and Planning Department; call (775) 463-3511 or (775) 364-8895 for a current valuation-based estimate before applying.
  • Projects outside Yerington city limits fall under the separate Lyon County Building Department, (775) 463-6591 — confirm which jurisdiction applies before submitting.

Frequently asked questions

Yerington requires a solar photovoltaic (pv) permit for: Building permit required for the structural/racking portion, applied for via the universal Building Permit Application (PW106) by checking the 'SOLAR' box under the For Office Use category block; Governed by the 2018 IBC (commercial) / 2018 IRC (residential) as adopted by the City, per the application's own code-edition header; Electrical work (wiring/interconnection) governed by the 2017 NEC as adopted by the City — apply via the same universal application, additionally checking 'ELECTRIC' if not already covered by the SOLAR category, and completing the Electrical Contractor section (NV Contractors License Number, Yerington Business License Number); A 24-hour advance notice is required to schedule inspections, per the Building Department's general inspection policy. If your project isn't listed, confirm with City of Yerington Building and Planning Department at (775) 463-3511 before starting work.

In Yerington, the published Building Permit Fee (SOLAR category, GL 01-13-00-3117) is: Valuation-based; determined from the City's Building Valuation Data Sheets (not published online — located at the Building and Planning Department). Additional published fees: Plan Check Fee (GL 01-13-00-3117) — Valuation-based, same account code as the Building Permit Fee; Inspection Fee: Electrical Upgrade (if applicable) — $85.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Yerington does not publish a plan-review timeline for this permit. Contact City of Yerington Building and Planning Department at (775) 463-3511 for current turnaround.

You'll need: Building Permit Application (PW106) — SOLAR category; Construction/Electrical Plans. See the required-documents checklist on this page for details on each.

Yerington requires 2 inspection(s) for a solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through City of Yerington Building and Planning Department ((775) 463-3511).

Apply through City of Yerington Building and Planning Department at 14 E. Goldfield Avenue, Yerington, NV 89447. Phone: (775) 463-3511, email: pauls@yerington.net. Office hours: Monday-Friday, 8:00 AM - 5:00 PM. Primary contact: Paul Shapiro, (775) 364-8895 or (775) 463-3511, pauls@yerington.net. Secondary contact: Steve Douglas, Building Inspector, (775) 634-7422, steved@yerington.net. Building Department fax: (775) 463-2284. A 24-hour advance notice is required to schedule inspections. Projects outside city limits fall under Lyon County Building Department, (775) 463-6591.. Official information: https://www.yerington.net/296/2343/Building-Department.

Yerington, Nevada has adopted: Nevada is a home-rule state for building codes: there is no single mandatory statewide building-code edition — each city and county adopts and amends its own code. The only genuine statewide floor is the energy code, referenced through NRS 701.220, which directs the State Office of Energy to adopt and update energy-efficiency standards for new construction. Always confirm the specific adopted edition for the jurisdiction in question rather than assuming a uniform statewide code. Source: Nevada Legislature NRS Chapter 701 (State Office of Energy).; International Building Code (IBC), 2018 Edition — adopted by the City of Yerington per Yerington City Code Title 1, Chapter 9. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025), cover sheet 'Building Codes Adopted by the City of Yerington.'; International Residential Code (IRC), 2018 Edition — adopted by the City of Yerington per Yerington City Code Title 1, Chapter 9. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; International Existing Building Code (IEBC), 2018 Edition — adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; International Energy Conservation Code (IECC), 2018 Edition — adopted by the City of Yerington (also satisfies the NRS 701.220 statewide energy floor). Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; Uniform Plumbing Code (UPC), 2018 Edition — adopted by the City of Yerington; Nevada jurisdictions commonly use the Uniform Plumbing Code rather than the International Plumbing Code. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; Uniform Mechanical Code (UMC), 2018 Edition — adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; National Electrical Code (NEC), 2017 Edition — adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; International Fire Code (IFC), 2012 Edition — adopted by the City of Yerington; commercial projects are additionally subject to review by the Mason Valley Fire District (775-463-2261), which requires its own separate application, plan submittal, and fee. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; 2018 Northern Nevada Amendments (Northern Nevada Chapter of the International Code Council / NNICC) — incorporated by reference into the codes adopted by the City of Yerington. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).; The City of Yerington is a member of the International Code Council. Code adoption is referenced to Yerington City Code Title 1, Chapter 9. Source: City of Yerington Building Permit Application (PW106, Rev. 7, 06/2025).. Local amendments apply — see the Yerington overview page for the full list.

Yes and no. The City's Building Permit Application (PW106) has its own 'SOLAR' checkbox category, distinct from 'ELECTRIC' and other project types, so the City does formally recognize and track solar installations as their own category. However, there is no separate dollar-figure fee specific to solar — it is billed under the same valuation-based Building Permit Fee and Plan Check Fee (GL code 01-13-00-3117) used for any other construction, calculated from the City's Building Valuation Data Sheets (not published online).

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Yerington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.