Unincorporated Bernalillo County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Bernalillo County, New Mexico.

Verified 2026-07-02 · Source

How to schedule

Inspections are requested through the building department below.

Address
415 Silver Ave SW, 2nd Floor, Albuquerque, NM 87102
Phone
(505) 314-0351 (Building Services / Inspection Line); (505) 314-0350 (Planning & Development Services main line / Permitting & Development Center)
Office hours
Monday–Friday 8:00 AM – 4:30 PM (Building Services page separately lists 8–5 p.m.; the FAQ and Residential Building Packet both confirm 8:00 AM–4:30 PM for permit submittal)

Published scheduling rules

  • Inspection requests for all trades go through the same Inspection Line: (505) 314-0351. (General)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Foundation/Footing

    Before concrete pour — verify excavation, forms, rebar, footing dimensions

  2. 2

    Framing

    Structural members, headers, beams, truss details, wall/roof framing before cover

  3. 3

    Rough MEP (Mechanical/Electrical/Plumbing)

    Rough-in inspections for mechanical, electrical, and plumbing systems before concealment

  4. 4

    Insulation

    After insulation installed, before drywall — verify R-values match IECC compliance certificate

  5. 5

    Final

    All work complete; smoke/CO detectors installed hard-wired with battery backup

Applies to: Accessory Dwelling Unit (Secondary Dwelling Unit / Accessory Living Quarters)

  1. 1

    Foundation

    Footings, forms, rebar before concrete pour

  2. 2

    Framing

    Structure, fire separation, egress

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors installed

Applies to: Swimming Pool Permit

  1. 1

    Public Works Development Review Site Visit

    Required before permit issuance — Development Review Inspector visits site to determine if a Grading and Drainage Plan is required

  2. 2

    Excavation/Steel

    Pool shell excavation, rebar, plumbing before gunite/shotcrete

  3. 3

    Electrical/Bonding

    Pool bonding grid, equipment connections, GFCI protection

  4. 4

    Building Final

    Pool complete, barrier/fence in place per the Pool Barrier Responsibility Statement — Public Works final inspection required before Building Final

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed

  2. 2

    Service/Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, panel labeled, GFCI/AFCI protection verified. Inspection Phone: (505) 314-0351.

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, no leaks, proper venting verified. Inspection Phone: (505) 314-0351.

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects before work begins

  2. 2

    Final/Site Clear

    Site cleared, foundation removed or capped

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring/conduit installed, before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/equipment installed, breaker sized correctly, GFCI/AFCI protection verified where required. Inspection Phone: (505) 314-0351.

Applies to: Fence / Wall Permit

  1. 1

    Footing

    Footing excavation, rebar, forms before concrete pour

  2. 2

    Final

    Wall/fence complete, height and construction verified against approved plans

Applies to: Fire Sprinkler System / Fire Alarm & Detection System Permit

  1. 1

    Final Installation Approval

    Before requesting final approval, the installing contractor must furnish a written statement to the fire code official that the fire protection system was installed per the approved plans and tested per the manufacturer's specifications and the appropriate installation standard; any deviations must be noted with approvals attached

  2. 2

    Fire Alarm Final Inspection / Acceptance Test

    Required prior to building occupancy for fire alarm/detection systems specifically — a Record of Completion (NFPA 72 Ch. 1 Sec. 1.7.2.1) and as-built plans must be available; the acceptance test verifies initiating devices, control panels, and appliances, with smoke detectors tested using 'test smoke'

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested. Inspection Phone: (505) 314-0351.

Applies to: Re-Roof Permit

  1. 1

    Frame Inspection

    Required whenever structural modifications have been made or re-sheathing of the roof deck is part of the scope of work

  2. 2

    Final Inspection

    Required for all permitted work when the job is complete

Applies to: Sign Permit

  1. 1

    Footing

    Required for signs having footings, at the discretion of the CBO or authorized representative (Ordinance 2024-8, Sec. 110.5.6.1)

  2. 2

    Final

    Required for all signs for which a permit was issued; the permittee must notify Bernalillo County Building Department when the sign is complete. Signs may be re-inspected at the discretion of the CBO or authorized agent (Ordinance 2024-8, Sec. 110.5.6.2)

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final/Structural

    Panel mounting, racking attachment, roof penetration weatherproofing, and electrical connections verified

Re-inspection fees

Residential Building PermitRe-inspection Fee · Resolution 25-2009, Table 3-A, Item 2
$47.00 each
Electrical PermitAdministrative Charge (applies to all electrical permit applications) · Resolution 25-2009, Table 3-B, Item 1 (exception: re-inspection fees)
$23.50 each
Electrical PermitRe-inspection Fee · Resolution 25-2009, Table 3-B (continuation page)
$47.00 each
Plumbing PermitAdministrative Charge (all plumbing permit applications) · Resolution 25-2009, Table 3-D, Item 1 (exception: re-inspection fee)
$23.50 each
Plumbing PermitRe-inspection Fee · Resolution 25-2009, Table 3-D (continuation page)
$47.00 each
Mechanical / HVAC PermitRe-inspection Fee · Resolution 25-2009, Table 3-C, Other Inspections and Fees, Item 2
$47.00 per hour
Re-Roof PermitRe-inspection Fee · Resolution 25-2009, Table 3-A
$47.00 each
Water Heater PermitRe-inspection Fee · Resolution 25-2009, Table 3-D
$47.00 each
Sign PermitRe-inspection Fee · Resolution 25-2009, Table 3-E, Other Inspections and Fees, Item 2
$47.00 each

Sources & verification

Verified against official sources. Last reviewed 2026-07-02.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Bernalillo County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Bernalillo County building permits

Get alerts for Unincorporated Bernalillo County

We'll email you when Unincorporated Bernalillo County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.