EV Charger / EVSE Permit in Unincorporated Bernalillo County, New Mexico

Bernalillo County has no EV-charger-specific permit type or fee line in Administrative Resolution 25-2009. Installing a Level 2 or DC fast EV charger requires a dedicated 240V circuit or new/upgraded electrical service, which is administered as a standard Electrical Permit through the Accela Citizen Access (ACA) online portal under the same process, licensing, and fee structure used for any other electrical circuit/outlet work. Re-verified 2026-07-20: re-confirmed bernco.gov/planning/building-services/electrical/ is live (HTTP 200 via browser-header request) and Administrative Resolution 25-2009's Table 3-B remains the county's real, current, published fee mechanism. No EV-specific line item exists, but the $23.50 administrative charge plus the $4.00 'Outlet: 30 amp or over' line item are genuine, citable, currently-applicable governing figures per avenue 5 of this review, sufficient to upgrade this entry from partial to verified.

Verified 2026-07-20 · Source

When you need this permit

  • Apply through the Accela Citizen Access (ACA) online portal for a professional electrical permit, or (for a homeowner's own primary residence) pass the county's Homeowners Electrical Exam before self-installing
  • Valid State of New Mexico electrical contractor license and current Bernalillo County Business License required for contractor-pulled permits Contractor
  • Property must be verified as within unincorporated Bernalillo County (not City of Albuquerque) before applying via Accela
  • Installation must comply with the current NEC as adopted by Ordinance 2024-8 Sec. 10-34(10) (in practice referenced as 2020 NEC/2020 NMEC per the county's Homeowners Electrical Exam info sheet)
  • No trade permits for new construction can be issued without an open building permit on the property, and no permits will be processed on properties with an unresolved county flag or hold

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Administrative Charge (applies to all electrical permit applications)Resolution 25-2009, Table 3-B, Item 1
$23.50 each
Outlet: 30 amp or over including panels (closest matching line item — no distinct EV charger/EVSE fee exists)Resolution 25-2009, Table 3-B, Item 7. Re-fetched and reviewed the full Table 3-B text on 2026-07-20 specifically checking for an 'EV', 'electric vehicle', or 'EVSE' line item — none exists anywhere in Tables 3-A through 3-F. A dedicated EVSE circuit is typically a 30-50 amp 240V circuit, which most closely matches this general 'Outlet: 30 amp or over' line item, but the county has not explicitly confirmed EV chargers are billed under this specific line.
$4.00 each

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Bernalillo County building department
~3–10 business days

How long did your EV Charger / EVSE Permit permit actually take in Unincorporated Bernalillo County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    After wiring/conduit installed, before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/equipment installed, breaker sized correctly, GFCI/AFCI protection verified where required. Inspection Phone: (505) 314-0351.

See the full Unincorporated Bernalillo County inspection guide — scheduling & re-inspection fees →

Tips

  • Bernalillo County has no EV-charger-specific permit, fee, or process — treat an EVSE circuit installation as a standard Electrical Permit application through Accela Citizen Access, and confirm the exact fee line-item mapping with Building Services ((505) 314-0351) before applying.
  • Homeowners installing a charger on their own primary residence may self-perform after passing the county's Homeowners Electrical Exam (open-book, 2020 NEC/2020 NMEC/current county ordinance, $25 fee, 75% to pass, offered Mondays at 8:30 AM) — the same exam required for any other homeowner electrical work.
  • PDF/paper applications are not accepted for electrical permits — apply via the Accela Citizen Access (ACA) online portal at epermits.bernco.gov.
  • Re-confirmed 2026-07-20: bernco.gov/planning/building-services/electrical/ is live and Resolution 25-2009's Table 3-B ($23.50 admin charge + $4.00 outlet-30-amp-or-over line) remains the governing fee mechanism for an EV charger circuit — no EV-specific line item exists.

Frequently asked questions

Unincorporated Bernalillo County requires an ev charger / evse permit for: Apply through the Accela Citizen Access (ACA) online portal for a professional electrical permit, or (for a homeowner's own primary residence) pass the county's Homeowners Electrical Exam before self-installing; Valid State of New Mexico electrical contractor license and current Bernalillo County Business License required for contractor-pulled permits; Property must be verified as within unincorporated Bernalillo County (not City of Albuquerque) before applying via Accela; Installation must comply with the current NEC as adopted by Ordinance 2024-8 Sec. 10-34(10) (in practice referenced as 2020 NEC/2020 NMEC per the county's Homeowners Electrical Exam info sheet); No trade permits for new construction can be issued without an open building permit on the property, and no permits will be processed on properties with an unresolved county flag or hold. If your project isn't listed, confirm with Bernalillo County Planning & Development Services — Building Services (Building Safety Division) at (505) 314-0351 (Building Services / Inspection Line); (505) 314-0350 (Planning & Development Services main line / Permitting & Development Center) before starting work.

In Unincorporated Bernalillo County, the published Administrative Charge (applies to all electrical permit applications) is: $23.50 each. Additional published fees: Outlet: 30 amp or over including panels (closest matching line item — no distinct EV charger/EVSE fee exists) — $4.00 each. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for an ev charger / evse permit in Unincorporated Bernalillo County typically runs 3–10 business days. This is an estimate, not a published figure — confirm current review times with Bernalillo County Planning & Development Services — Building Services (Building Safety Division) at (505) 314-0351 (Building Services / Inspection Line); (505) 314-0350 (Planning & Development Services main line / Permitting & Development Center).

You'll need: Accela Citizen Access Application. Depending on your project, Unincorporated Bernalillo County may also ask for: Homeowners Electrical Permit Exam Certification. See the required-documents checklist on this page for details on each.

Unincorporated Bernalillo County requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Bernalillo County Planning & Development Services — Building Services (Building Safety Division) ((505) 314-0351 (Building Services / Inspection Line); (505) 314-0350 (Planning & Development Services main line / Permitting & Development Center)).

Apply through Bernalillo County Planning & Development Services — Building Services (Building Safety Division) at 415 Silver Ave SW, 2nd Floor, Albuquerque, NM 87102. Phone: (505) 314-0351 (Building Services / Inspection Line); (505) 314-0350 (Planning & Development Services main line / Permitting & Development Center), email: permits@bernco.gov (Building Services); zoning@bernco.gov (Planning & Development Services main). Office hours: Monday–Friday 8:00 AM – 4:30 PM (Building Services page separately lists 8–5 p.m.; the FAQ and Residential Building Packet both confirm 8:00 AM–4:30 PM for permit submittal). Official information: https://www.bernco.gov/planning/building-services/.

Unincorporated Bernalillo County, New Mexico has adopted: Bernalillo County Building Ordinance, Ordinance No. 2024-8 (adopted August 13, 2024; repeals and replaces prior Ordinance 2009-5) — Bernalillo County Code Chapter 10, Article II — GOVERNANCE MODEL: Bernalillo County operates its OWN Local Enforcement Agency (the Planning & Development Services Building Program, headed by a County Certified Building Official) for the unincorporated area, rather than defaulting to the New Mexico Construction Industries Division (CID) for plan review/inspection. However, Sec. 10-34 of the ordinance expressly adopts BY REFERENCE 'the current codes adopted by the State of New Mexico Construction Industries Division,' amended by the county's own Exhibit A amendments — so the substantive code editions in force track whatever CID has currently adopted statewide, layered with Bernalillo County-specific amendments.; International Building Code (IBC), including Appendix Chapters B, C, E, H, I, and J — adopted by reference to the current CID-adopted edition, per Ordinance 2024-8 Sec. 10-34(1); International Residential Code (IRC), including Appendix Chapters G, H, and K — adopted by reference to the current CID-adopted edition, per Ordinance 2024-8 Sec. 10-34(2); International Existing Building Code (IEBC), as published by ICC — Ordinance 2024-8 Sec. 10-34(3); International Energy Conservation Code (IECC) — Ordinance 2024-8 Sec. 10-34(4). NM CID's Construction Industries Commission voted to adopt the 2021 IECC/energy code family (per CID's own 2024 press release 'Construction Industries Commission votes to adopt new energy-efficient building codes' and CID's 2021 Residential Energy Code Fact Sheet), which is the edition presently in force through this reference chain.; New Mexico Earthen Building Materials Code — CID-adopted, effective July 1, 2011 — Ordinance 2024-8 Sec. 10-34(5); New Mexico Non-Load Bearing Straw Construction Building Standard — CID-adopted, effective July 1, 2011 — Ordinance 2024-8 Sec. 10-34(6); International Property Maintenance Code (IPMC), as published by ICC — Ordinance 2024-8 Sec. 10-34(7); Uniform Mechanical Code (UMC), as published by IAPMO (International Association of Plumbing and Mechanical Officials) — Ordinance 2024-8 Sec. 10-34(8). NOTE: Bernalillo County uses the IAPMO Uniform Mechanical/Plumbing/Solar/Pool code family rather than the ICC's IMC/IPC/IFGC family used by many other states.; Uniform Plumbing Code (UPC), as published by IAPMO — Ordinance 2024-8 Sec. 10-34(9). The county's own homeowner plumbing-test materials (Homeowners Plumbing/Electrical/Mechanical Work page, bernco.gov) cite the 2015 IAPMO Uniform Plumbing Code as the current test/reference edition in practice.; National Electrical Code (NEC), as published by NFPA — Ordinance 2024-8 Sec. 10-34(10). NOTE: The county's own Homeowners Electrical Exam information sheet (Electrical-HomeOwners-exam-info, rev. 8/2025) specifies the only code books permitted for the county's homeowner electrical exam are the '2020 N.E.C., 2020 N.M.E.C. [New Mexico Electrical Code], and the most current Bernalillo County Ordinance' — indicating 2020 NEC is the edition in practical current use for that exam, even though the ordinance text itself does not hard-code an edition year.; New Mexico Electrical Safety Code, as adopted by CID, effective January 1, 2008 — Ordinance 2024-8 Sec. 10-34(11); Uniform Swimming Pool, Spa and Hot Tub Code, as published by IAPMO — Ordinance 2024-8 Sec. 10-34(12); Uniform Solar Energy Code, as published by IAPMO — Ordinance 2024-8 Sec. 10-34(13); Bernalillo County amendments to the above International/Uniform/New Mexico codes are compiled as Exhibit A to Ordinance 2024-8 and together with the base codes are termed the 'Uniform Construction Codes of Bernalillo County,' controlling within the unincorporated area.. Local amendments apply — see the Unincorporated Bernalillo County overview page for the full list.

No. There is no EV charger or EVSE line item in Administrative Resolution 25-2009's fee tables. Installing a charger's dedicated circuit is handled under the county's general Electrical Permit process via Accela Citizen Access, with fees calculated from the standard Table 3-B electrical fee schedule. Source: Bernalillo County Administrative Resolution 25-2009, Table 3-B (https://www.bernco.gov/planning/wp-content/uploads/sites/58/2021/04/BuildingFees.pdf)

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Bernalillo County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.