EV Charger / EVSE Permit (NM Construction Industries Division — Electrical Bureau) — Española, New Mexico · Requirements sheet
Verified 2026-07-20 · Source: https://www.rld.nm.gov/construction-industries/forms-and-applications/fees/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (NM Construction Industries Division — Electrical Bureau) in Española, New Mexico
Installation of a Level 2 (or higher) electric vehicle charger/EVSE in Espanola is regulated by the state Construction Industries Division (CID), the same agency that issues all electrical permits for Espanola addresses under the 2020 New Mexico Electrical Code (2020 NEC, NMAC 14.10.4). CID's published statewide Electrical fee table has NO dedicated EV-charger, EVSE, or electric-vehicle line item; a charger circuit is billed under the same general schedule used for other electrical work — the applicable service-amperage tier if a new/upgraded service is involved, or the 'Minimum Inspection Fee for Items Not Listed' if the work is limited to an added circuit on an existing service.
Verified 2026-07-20 · Source
When you need this permit
- All electrical work, including EV charger circuits, must comply with the 2020 New Mexico Electrical Code (2020 NEC), NMAC 14.10.4, including Article 625 (Electric Vehicle Power Transfer System)
- Permit issued by CID, not the City of Española
- A homeowner may apply for a homeowner's electrical permit covering an EV charger for their own primary residence only after submitting plans/drawings and passing CID's homeowner electrical exam with a minimum score of 75% (N.M. Admin. Code 14.5.2.18(N)); otherwise the work must be performed by a New Mexico CID-licensed electrical contractor Owner-builder
- Multi Purpose State Building Application / Electrical Permit Application submitted to CID (Santa Fe office serves Rio Arriba and Santa Fe Counties)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In Inspection
Charger circuit wiring and breaker sizing before concealment, if applicable
- 2
Final Inspection
EVSE installed, GFCI/disconnect verified, system energized per the 2020 NEC Article 625
See the full Española inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'EV charger permit' fee line published by CID — a charger circuit is billed under the Electrical fee table's general schedule (service-amperage tier if a new/upgraded service is needed, otherwise the $27 minimum/not-listed fee), the same office and schedule used for other electrical work in Espanola.
- This mirrors Espanola's own solar-pv-permit entry: CID's Electrical fee table has no dedicated line item for either solar PV or EV chargers, and both fall back to the same general/minimum-fee mechanism.
- Homeowners may self-perform EV charger wiring on their own primary residence only after passing CID's homeowner electrical exam (75% minimum). Owner-builder
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Española building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Española
EV Charger / EVSE Permit (NM Construction Industries Division — Electrical Bureau) in other cities
Look up this fee in a different city →