Skip to main content
PermitBase

Solar Panel (PV) Permit in Unincorporated Carbon County, Utah

Required for rooftop and ground-mounted solar photovoltaic system installation on unincorporated Carbon County land. Carbon County's Building Permits service page explicitly lists 'Solar Panels' among the project types requiring a building permit, and — effective January 1, 2025 — names 'New Construction and Solar' building permit applications specifically as requiring a non-refundable $250.00 deposit, applied as a credit toward the final permit fee. The county does not publish a dedicated solar submittal checklist distinct from its standard plan-set requirements, and (consistent with the rest of this record) no dollar-amount valuation-based fee table beyond the $250 deposit could be located on carbon.utah.gov after a direct re-check of the Building Permits page.

Reviewed 2026-07-20 · Source

When you need this permit

  • Solar Panels are explicitly listed on the Carbon County Building Permits page as a project type requiring a building permit
  • Completed and signed Building Permit Application, including contractor name(s)/Utah license number(s) or a signed Owner/Builder Certification Form Owner-builder
  • Complete plan set (PDF only) including a site plan showing panel/array placement
  • Non-refundable $250.00 deposit (New Construction and Solar), applied as a credit toward the final permit fee, effective 1/1/2025
  • Signed Road Encroachment Agreement if the property's access is from a county road, per the same unincorporated-area requirement documented for the residential building permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

New Construction and Solar Deposit
Carbon County Building Permits page: 'New Construction and Solar building permit applications require a non-refundable $250.00 deposit that will be applied as a credit toward your permit,' effective January 1, 2025. Show full citationCarbon County Building Permits page: 'New Construction and Solar building permit applications require a non-refundable $250.00 deposit that will be applied as a credit toward your permit,' effective January 1, 2025. No further figure beyond this deposit is published (see feesNote).
$250.00 (non-refundable, applied as a credit toward the final permit fee)

Review timeline

Plan reviewUnincorporated Carbon County’s published plan-review target
0–14 business days

How long did your Solar Panel (PV) Permit permit actually take in Unincorporated Carbon County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    For occupancy/energization. Call at least 24-72 hours in advance to schedule inspections at (435) 636-3260; the county does not publish a distinct solar inspection sequence (e.g. separate rough electrical step) beyond its standard final inspection.

See the full Unincorporated Carbon County inspection guide — scheduling & re-inspection fees →

Tips

  • Carbon County names 'Solar' specifically (alongside 'New Construction') in its $250 non-refundable deposit requirement, effective 1/1/2025 — this is the clearest evidence the county treats solar as a distinct permit category, even though it folds into the same general Building Permit Application and plan-set process rather than a dedicated solar checklist.
  • No dollar-amount valuation-based fee table for the underlying permit fee (beyond the $250 deposit) could be located on carbon.utah.gov as of 2026-07-19 — contact the Building Department at (435) 636-3260 or planning@carbon.utah.gov for a project-specific quote.
  • Unincorporated-area applicants still need a signed Road Encroachment Agreement if access is from a county road, the same as for new home/cabin construction.

Frequently asked questions

Yes. Carbon County's Building Permits page explicitly lists Solar Panels among the projects requiring a building permit, and requires a non-refundable $250.00 deposit for 'New Construction and Solar' applications, effective January 1, 2025, credited toward the final permit fee.

In Unincorporated Carbon County, the published New Construction and Solar Deposit is: $250.00 (non-refundable, applied as a credit toward the final permit fee). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Carbon County's published plan-review target for a solar panel (pv) permit is 0–14 business days.

You'll need: Building Permit Application; Site Plan (PDF); $250.00 New Construction and Solar Deposit Payment. See the required-documents checklist on this page for details on each.

Unincorporated Carbon County requires 1 inspection(s) for a solar panel (pv) permit, in order: Final Inspection. Schedule each through Carbon County Building & Planning Department (Building Division) — serves unincorporated Carbon County directly, plus all incorporated cities/towns in the county ((435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning)).

Apply through Carbon County Building & Planning Department (Building Division) — serves unincorporated Carbon County directly, plus all incorporated cities/towns in the county at 751 East 100 North, Suite 2600, Price, UT 84501. Phone: (435) 636-3260 (Building Division main line / Administrative Assistant); (435) 636-3261 (Director of Building & Planning), email: planning@carbon.utah.gov. Office hours: Mon–Thu 8:00 AM – 5:00 PM, Fri 8:00 AM – 3:00 PM (Building Department-specific hours per the county's own Building Permits FAQ; distinct from general County Administration hours of Mon–Fri 8:00 AM – 5:00 PM). Official information: https://www.carbon.utah.gov/service/building-permits/.

Unincorporated Carbon County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — governs per Utah Code §15A-2-103(1)(a) (https://le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), in force statewide since 7/1/2026 and binding on counties under §15A-1-204. Carbon County's own Building Permits page 'What codes are enforced?' FAQ still lists the 2021 IBC with Appendix J only (no Appendix C) — the county's own page has not been updated to the current statewide edition.; 2021 International Residential Code (IRC), including Appendix AQ (the FAQ labels it 'Appendix Q') — governs per Utah Code §15A-2-103(1)(b)/(c); this edition is UNCHANGED from the prior code cycle. Carbon County's own FAQ lists the 2021 IRC with Appendix Q — consistent with the current statute on the base edition.; 2024 International Plumbing Code (IPC) — governs per Utah Code §15A-2-103(1)(d). Carbon County's own FAQ still lists the 2021 IPC — this lags the current statewide edition.; 2024 International Mechanical Code (IMC) — governs per Utah Code §15A-2-103(1)(e). Carbon County's own FAQ still lists the 2021 IMC — this lags the current statewide edition.; 2024 International Fuel Gas Code (IFGC) — governs per Utah Code §15A-2-103(1)(f). Carbon County's own FAQ still lists the 2021 IFGC — this lags the current statewide edition.; 2023 National Electrical Code (NEC) — governs per Utah Code §15A-2-103(1)(g); this edition is unchanged from the prior code cycle. Carbon County's own published FAQ lists the 2020 NEC, one cycle behind the current statewide edition.; 2024 International Energy Conservation Code (IECC), one code with no residential/commercial split — governs per Utah Code §15A-2-103(1)(h). Carbon County's own Building Permits FAQ does not list any IECC edition at all — added here per the statute, not omitted.; 2024 International Existing Building Code (IEBC), subject to Utah Code §15A-2-104(2) (the HUD Code) — governs statewide per Utah Code §15A-2-103(1)(i)/(j). Not listed on Carbon County's own Building Permits FAQ.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — governs statewide per Utah Code §15A-2-103(1)(n). Not listed on Carbon County's own Building Permits FAQ.; Modular Building Institute (MBI) Standards 1200 and 1205 — governs statewide per Utah Code §15A-2-103(1)(o). Not listed on Carbon County's own Building Permits FAQ.. Local amendments apply — see the Unincorporated Carbon County overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Carbon County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Property Access

Unincorporated Carbon County's permit history is searchable by address

14,326 permits on record for Unincorporated Carbon County, 1957–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.

97% of Unincorporated Carbon County's records carry a street address to match against, so a search that finds nothing here means we could not look — not that the property is clear.

Start your 7-day free trial7 days free for new customers, then $79/mo · the guide above stays free