Accessory Dwelling Unit (ADU) Permit in Syracuse, Utah

Required for construction or conversion of an Accessory Dwelling Unit in Syracuse, governed by Municipal Code § 10.30.020. A recorded owner-occupancy Deed Restriction must be completed and submitted to the Community Development Office before the building permit can be signed off.

Reviewed 2026-07-07 · Source

When you need this permit

  • Recorded Deed Restriction (Declaration of Owner Occupancy Restriction for Accessory Dwelling) required prior to building permit issuance for: (a) a new accessory dwelling, (b) a new principal dwelling unit with an accessory unit, or (c) conversion of part of an existing structure to an ADU
  • Property owner must reside on the premises in either the principal or accessory dwelling
  • Deed restriction must be signed by all property owners, notarized, and recorded at the Davis County Recorder's Office (Davis County Administration Building, Farmington, UT) before the underlying building permit can be signed off
  • A copy of the RECORDED restriction must be submitted to the Community Development Office as evidence

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Filing fee
Not published — contact the department

Review timeline

Plan review
Not published — contact the department

How long did your Accessory Dwelling Unit (ADU) Permit permit actually take in Syracuse?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full Syracuse inspection guide — scheduling & re-inspection fees →

    Tips

    • The deed restriction step is a hard blocker in Syracuse: the official instructions state the building permit 'cannot be signed off' until the Community Development Office receives a copy of the RECORDED restriction from the Davis County Recorder's Office.
    • If the owner becomes unable to reside on the premises (outside narrow exceptions like military service or medical care, capped at 3 years), continued two-unit occupancy becomes invalid and illegal, and the second unit must be de-converted (kitchen cooking capability removed, plumbing fixtures reduced to 2 or fewer) to remain a legal accessory building.
    • The deed restriction is a covenant running with the land — it binds all future owners of the property, not just the applicant.

    Frequently asked questions

    Syracuse requires an accessory dwelling unit (adu) permit for: Recorded Deed Restriction (Declaration of Owner Occupancy Restriction for Accessory Dwelling) required prior to building permit issuance for: (a) a new accessory dwelling, (b) a new principal dwelling unit with an accessory unit, or (c) conversion of part of an existing structure to an ADU; Property owner must reside on the premises in either the principal or accessory dwelling; Deed restriction must be signed by all property owners, notarized, and recorded at the Davis County Recorder's Office (Davis County Administration Building, Farmington, UT) before the underlying building permit can be signed off; A copy of the RECORDED restriction must be submitted to the Community Development Office as evidence. If your project isn't listed, confirm with Syracuse City Building Department (Community & Economic Development Department) at 801-825-1477, option 4 (Building Inspections Scheduling); Building Department direct line 801-614-9670 before starting work.

    Syracuse does not publish a plan-review timeline for this permit. Contact Syracuse City Building Department (Community & Economic Development Department) at 801-825-1477, option 4 (Building Inspections Scheduling); Building Department direct line 801-614-9670 for current turnaround.

    You'll need: Declaration of Owner Occupancy Restriction for Accessory Dwelling (Deed Restriction form); Building Permit Application (CivicReview online portal). See the required-documents checklist on this page for details on each.

    Apply through Syracuse City Building Department (Community & Economic Development Department) at 1979 W 1900 S, Syracuse, UT 84075. Phone: 801-825-1477, option 4 (Building Inspections Scheduling); Building Department direct line 801-614-9670. Office hours: Not published on the official Building Department page as of 2026-07-07; permit applications are submitted digitally via the CivicReview online portal rather than in person.. Official information: https://www.syracuseut.gov/160/Building.

    Syracuse, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026 (confirmed by direct fetch of the live statute 2026-07-16). Supersedes the 2021 IBC, which governed through 6/30/2026. Matches Syracuse's own Building Department page (live-checked via browser 2026-07-16), which lists '2024 IBC' among its currently-adopted codes.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle (confirmed by direct statute fetch 2026-07-16). NOTE (2026-07-16 city-page discrepancy): Syracuse's own Building Department page (syracuseut.gov/160/Building), live-checked via browser 2026-07-16, states verbatim: 'Syracuse City has adopted minimum design and construction requirements found in the 2024 IBC, IPC, IMC and IRC, as well as the 2023 NEC (Please note, starting July 1, 2026, the state of Utah will be adopting the 2024 International Building Codes, IBC, IPC, IMC, IFC, IFGC, IEBC, and IECC, while the International Residential Code (IRC) will remain 2024, and the National Electrical Code (NEC) will remain 2023).' The city's own page appears to have an error here, listing IRC as 2024 both currently and going forward. Utah is a statewide-mandatory-code state — Utah Code § 15A-1-204 requires the state and every political subdivision to follow the State Construction Code, and a municipality cannot unilaterally adopt a different IRC edition than the state. This JSON follows the statute (2021 IRC, confirmed directly against the live Utah Code) rather than propagating the city page's apparent error; the discrepancy is recorded here rather than silently corrected on the city's behalf.; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026. Matches Syracuse's own Building Department page.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026. Matches Syracuse's own Building Department page.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle. Confirmed live on Syracuse's Building Department page (re-fetched 2026-07-16: '...as well as the 2023 NEC').; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). ONE statewide edition — no residential/commercial split. Supersedes the 2021 IECC, which governed through 6/30/2026.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IEBC, which governed through 6/30/2026.; NOTE (2026-07-16 corpus-staleness fix, including correction of a known IFC error): A prior version of this file correctly anticipated that '2024 International Building Codes' would take effect 7/1/2026, but the codesAdopted entries above had not been flipped to reflect that the date has now passed — IBC/IPC/IMC were still incorrectly stated as '2021 ... currently in effect.' That has been corrected above (IFGC and IEBC entries have also been added, since the statute adopts both). Separately, the prior version's forecast NOTE listed IFC among the codes 'taking effect' 7/1/2026 — that was WRONG and has been removed here: Utah Code § 15A-2-103 contains NO International Fire Code subsection at all and does not adopt any IFC edition, in any year. (Syracuse's own Building Department page does independently mention IFC in its own forecast language, quoted above — that is the city's own text, not something §15A-2-103 adopts, so no IFC entry appears in this codesAdopted array.); Syracuse Municipal Code Chapter 9.15 (Construction Codes, §§ 9.15.010-9.15.070) codifies adoption by reference of the building code, Uniform Plumbing Code, National Electrical Code, and Uniform Mechanical Code 'as published by' the respective national code bodies 'and currently adopted by the state of Utah,' with successive state amendments/editions incorporated automatically upon their Utah State statutory effective date — consistent with the statewide framework under Utah Code Title 15A. Confirmed by direct browser fetch of the live codepublishing.com page (2026-07-16); the site returns HTTP 403 to curl/plain fetch (Cloudflare WAF challenge) but renders normally in a browser. The live chapter also includes § 9.15.070, Adoption of the 2006 Edition of the Utah Wildland Urban Interface Code (Ord. 25-42 § 1), not previously captured in this file.; Syracuse Municipal Code § 9.15.050 adopts by reference the ICC's Building Valuation Data for determining new-construction valuation, consistent with the city's Consolidated Fee Schedule building-value permit-fee tiers.. Local amendments apply — see the Syracuse overview page for the full list.

    Per Syracuse Municipal Code § 10.30.020, a recorded owner-occupancy Deed Restriction must be completed, notarized, and recorded at the Davis County Recorder's Office before the building permit for the ADU can be signed off. The property owner must reside on the premises in either the principal or accessory dwelling.

    Sources & verification

    Key facts verified against official sources. Last reviewed 2026-07-07.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Syracuse building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.