Required for new commercial construction in Syracuse. The Consolidated Fee Schedule uses the same General Building Valuation table as residential permits but applies a 65% commercial Plan Check Fee, versus 40% for residential — both approved 06-09-2026, effective July 1, 2026.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial construction regulated by the 2024 IBC (Utah Code § 15A-2-103(1)(a))
  • Digital application required via the City's CivicReview online portal
  • Development Application / Site Plan review typically required prior to or alongside the building permit application for new commercial projects
  • Commercial Building Inspection and Commercial Fire Inspection are separately assessed line items distinct from the Plan Check Fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

General Building Permit Fee (by valuation)Syracuse City Consolidated Fee Schedule, Building section, 'General Building Valuation' table, approved 06-09-2026, effective July 1, 2026 — the same table used for residential permits; Syracuse does not publish a separate commercial valuation table.
$100.00 for Building Value $1-$1,000; $100.00 + $2.70 per addl. $100 for $1,001-$2,000; $127.00 + $16.80 per addl. $1,000 for $2,001-$25,000; $513.00 + $12.11 per addl. $1,000 for $25,001-$50,000; $816.00 + $8.40 per addl. $1,000 for $50,001-$100,000; $1,236.00 + $6.72 per addl. $1,000 for $100,001-$500,000; $3,924.00 + $5.70 per addl. $1,000 for $500,001-$1,000,000; $6,774.00 + $4.65 per addl. $1,000 for $1,000,000.00+
Commercial Plan Check FeeSyracuse City Consolidated Fee Schedule, Building section, 'Plan Check Fees': 'Commercial — All Permitted Structures — 65% Permit Fee' (vs. 40% for Residential).
65% of Permit Fee
State Fee (Surcharge)Syracuse City Consolidated Fee Schedule, Building section.
1% of Permit Fee
Commercial Building InspectionSyracuse City Consolidated Fee Schedule, Community Development section, 'Commercial Building Inspection — $100.00 per inspection.'
$100.00 per inspection
Commercial Fire InspectionSyracuse City Consolidated Fee Schedule, Community Development section, 'Commercial Fire Inspection — $100.00 per inspection.'
$100.00 per inspection
Fire Sprinkler/Safety Plans ReviewSyracuse City Consolidated Fee Schedule, Building section, 'Plan Check Fees': 'Fire Sprinkler/Safety Plans — All Permitted Structures — $75.00 Per Hour.'
$75.00 per hour
Commercial Business License Fee (issued alongside occupancy)Syracuse City Consolidated Fee Schedule, Community Development section, 'Commercial Business.'
<5,000 sf: $100.00; 5,001-10,000 sf: $150.00; >10,001 sf: $350.00 per application
Commercial Transportation Impact Fee — General CommercialSyracuse City Consolidated Fee Schedule, Impact Fees section, 'Commercial Transportation ... General Commercial.' Office/Institutional: $3,134.00 per 1,000 sf GFA; Hotel: $2,310.00 per room; Industrial: $974.00 per 1,000 sf GFA — see the city's website for the complete commercial transportation impact fee list.
$9,445.00 per 1,000 sf of Gross Floor Area (GFA)
Public Safety Impact Fee — CommercialSyracuse City Consolidated Fee Schedule, Impact Fees section, 'Public Safety ... Commercial.'
$0.81 per square foot of building
Culinary Water Connection Fee, by meter sizeSyracuse City Consolidated Fee Schedule, Connection Fees section, 'Culinary Water.' Distinct from the separate Culinary Water Impact Fee (per-connection, e.g. 3/4" Line $1,204.00) listed in the Impact Fees section.
3/4" Meter: $519.00; 1" Meter: $618.00; 1.5" Meter: $1,878.00; 2" Meter: $2,114.00; 4" Meter: $4,241.00

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Syracuse?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Before concrete pour, verified against submitted structural drawings.

  2. 2

    Structural / Framing

    Framing and structural connections verified against stamped calculations.

  3. 3

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans. Scheduled via Building Inspections line 801-825-1477, option 4.

  4. 4

    Commercial Fire Inspection

    Separate fire inspection line item ($100.00 per inspection) distinct from the general building inspection sequence.

  5. 5

    Final

    All work complete before occupancy.

See the full Syracuse inspection guide — scheduling & re-inspection fees →

Tips

  • Syracuse charges a 65% commercial Plan Check Fee versus 40% for residential — both computed against the same General Building Valuation table used for all permitted structures.
  • Commercial Building Inspection ($100/inspection) and Commercial Fire Inspection ($100/inspection) are separate, distinctly-billed line items in Syracuse's fee schedule, on top of the Plan Check Fee.
  • Commercial impact fees vary substantially by use — General Commercial Transportation Impact is $9,445 per 1,000 sf GFA, while Office/Institutional is $3,134 and Hotel is $2,310 per room; confirm the applicable use category before budgeting.

Frequently asked questions

Syracuse requires a commercial building permit for: New commercial construction regulated by the 2024 IBC (Utah Code § 15A-2-103(1)(a)); Digital application required via the City's CivicReview online portal; Development Application / Site Plan review typically required prior to or alongside the building permit application for new commercial projects; Commercial Building Inspection and Commercial Fire Inspection are separately assessed line items distinct from the Plan Check Fee. If your project isn't listed, confirm with Syracuse City Building Department (Community & Economic Development Department) at 801-825-1477, option 4 (Building Inspections Scheduling); Building Department direct line 801-614-9670 before starting work.

Per Syracuse City's official Consolidated Fee Schedule, the Commercial Plan Check Fee is 65% of the Permit Fee, computed from the same General Building Valuation table used for residential ($100.00 for the first $1,000 of value, scaling to $6,774.00 plus $4.65 per additional $1,000 above $1,000,000). A 1% State Fee surcharge also applies.

Syracuse does not publish a plan-review timeline for this permit. Contact Syracuse City Building Department (Community & Economic Development Department) at 801-825-1477, option 4 (Building Inspections Scheduling); Building Department direct line 801-614-9670 for current turnaround.

You'll need: Building Permit Application (CivicReview online portal); Site Plan (Development Application). See the required-documents checklist on this page for details on each.

Yes. Syracuse's Consolidated Fee Schedule lists a Commercial Building Inspection fee of $100.00 per inspection and a Commercial Fire Inspection fee of $100.00 per inspection, both distinct from the Plan Check Fee.

Apply through Syracuse City Building Department (Community & Economic Development Department) at 1979 W 1900 S, Syracuse, UT 84075. Phone: 801-825-1477, option 4 (Building Inspections Scheduling); Building Department direct line 801-614-9670. Office hours: Not published on the official Building Department page as of 2026-07-07; permit applications are submitted digitally via the CivicReview online portal rather than in person.. Official information: https://www.syracuseut.gov/160/Building.

Syracuse, Utah has adopted: 2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); CURRENT as of 7/1/2026 (confirmed by direct fetch of the live statute 2026-07-16). Supersedes the 2021 IBC, which governed through 6/30/2026. Matches Syracuse's own Building Department page (live-checked via browser 2026-07-16), which lists '2024 IBC' among its currently-adopted codes.; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); UNCHANGED by the 7/1/2026 code cycle (confirmed by direct statute fetch 2026-07-16). NOTE (2026-07-16 city-page discrepancy): Syracuse's own Building Department page (syracuseut.gov/160/Building), live-checked via browser 2026-07-16, states verbatim: 'Syracuse City has adopted minimum design and construction requirements found in the 2024 IBC, IPC, IMC and IRC, as well as the 2023 NEC (Please note, starting July 1, 2026, the state of Utah will be adopting the 2024 International Building Codes, IBC, IPC, IMC, IFC, IFGC, IEBC, and IECC, while the International Residential Code (IRC) will remain 2024, and the National Electrical Code (NEC) will remain 2023).' The city's own page appears to have an error here, listing IRC as 2024 both currently and going forward. Utah is a statewide-mandatory-code state — Utah Code § 15A-1-204 requires the state and every political subdivision to follow the State Construction Code, and a municipality cannot unilaterally adopt a different IRC edition than the state. This JSON follows the statute (2021 IRC, confirmed directly against the live Utah Code) rather than propagating the city page's apparent error; the discrepancy is recorded here rather than silently corrected on the city's behalf.; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IPC, which governed through 6/30/2026. Matches Syracuse's own Building Department page.; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IMC, which governed through 6/30/2026. Matches Syracuse's own Building Department page.; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IFGC, which governed through 6/30/2026.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 code cycle. Confirmed live on Syracuse's Building Department page (re-fetched 2026-07-16: '...as well as the 2023 NEC').; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). ONE statewide edition — no residential/commercial split. Supersedes the 2021 IECC, which governed through 6/30/2026.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); CURRENT as of 7/1/2026 (confirmed by direct statute fetch 2026-07-16). Supersedes the 2021 IEBC, which governed through 6/30/2026.; NOTE (2026-07-16 corpus-staleness fix, including correction of a known IFC error): A prior version of this file correctly anticipated that '2024 International Building Codes' would take effect 7/1/2026, but the codesAdopted entries above had not been flipped to reflect that the date has now passed — IBC/IPC/IMC were still incorrectly stated as '2021 ... currently in effect.' That has been corrected above (IFGC and IEBC entries have also been added, since the statute adopts both). Separately, the prior version's forecast NOTE listed IFC among the codes 'taking effect' 7/1/2026 — that was WRONG and has been removed here: Utah Code § 15A-2-103 contains NO International Fire Code subsection at all and does not adopt any IFC edition, in any year. (Syracuse's own Building Department page does independently mention IFC in its own forecast language, quoted above — that is the city's own text, not something §15A-2-103 adopts, so no IFC entry appears in this codesAdopted array.); Syracuse Municipal Code Chapter 9.15 (Construction Codes, §§ 9.15.010-9.15.070) codifies adoption by reference of the building code, Uniform Plumbing Code, National Electrical Code, and Uniform Mechanical Code 'as published by' the respective national code bodies 'and currently adopted by the state of Utah,' with successive state amendments/editions incorporated automatically upon their Utah State statutory effective date — consistent with the statewide framework under Utah Code Title 15A. Confirmed by direct browser fetch of the live codepublishing.com page (2026-07-16); the site returns HTTP 403 to curl/plain fetch (Cloudflare WAF challenge) but renders normally in a browser. The live chapter also includes § 9.15.070, Adoption of the 2006 Edition of the Utah Wildland Urban Interface Code (Ord. 25-42 § 1), not previously captured in this file.; Syracuse Municipal Code § 9.15.050 adopts by reference the ICC's Building Valuation Data for determining new-construction valuation, consistent with the city's Consolidated Fee Schedule building-value permit-fee tiers.. Local amendments apply — see the Syracuse overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Syracuse building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Syracuse.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.