Inspection sequence, scheduling, and re-inspection fees for building permits in Moab, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
217 East Center Street, Moab, UT 84532
Phone
(435) 259-5129
Office hours
Mon–Thu 8:00 AM – 5:00 PM, Fri 8:00 AM – 12:00 PM

Published scheduling rules

  • 24-hour advance notice is required to schedule any inspection — call (435) 259-5129. (Residential Building Permit)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Building Department

    Core building inspection and final Building Department approval sign-off, one of seven routing lines on the official Building Permit Application. Inspections scheduled by phone at (435) 259-5129; 24-hour advance notice required.

  2. 2

    Zoning Administrator

    Zoning compliance sign-off, a required routing line on the official Building Permit Application.

  3. 3

    Engineering

    Engineering review and approval sign-off, a required routing line on the official Building Permit Application.

  4. 4

    Public Works & Utility

    Public Works and Utility sign-off, a required routing line on the official Building Permit Application.

  5. 5

    Health Department

    Health Department sign-off, a required routing line on the official Building Permit Application (applicable to septic, water systems, and similar).

  6. 6

    Fire Department

    Fire Department review, marked 'REQUIRED ON ALL COMMERCIAL APPLICATIONS' on the official form; included as a routing line for residential applications as well.

  7. 7

    Floodplain Administrator

    Floodplain Administrator sign-off and comments, required when the Floodplain Status field on the application indicates the parcel is within a mapped floodplain; an Elevation Certificate field is also present on the form.

Applies to: Commercial Building Permit

  1. 1

    Fire Department

    Fire Department review is marked 'REQUIRED ON ALL COMMERCIAL APPLICATIONS' on the official Building Permit Application — a mandatory routing/approval step not required on all residential applications.

  2. 2

    Building Department

    Core building inspection and final Building Department approval sign-off. Inspections scheduled by phone at (435) 259-5129; 24-hour advance notice required.

  3. 3

    Zoning Administrator

    Zoning compliance sign-off.

  4. 4

    Engineering

    Engineering review and approval sign-off.

  5. 5

    Health Department

    Applicable to commercial food service, septic, or water systems.

  6. 6

    Final Inspection

    Completed work verified before occupancy.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Fire Department

    Required on all commercial applications, including tenant-finish projects, per the official Building Permit Application form.

  2. 2

    Rough Electrical / Plumbing / Mechanical

    As applicable to the tenant-improvement scope, before wall closure.

  3. 3

    Final Inspection

    Completed work verified before reoccupancy.

Applies to: Change of Use / Change of Occupancy Permit

  1. 1

    Code Analysis / Occupancy Classification Review

    A change in use or occupancy classification is reviewed as part of the standard Building Permit plan review process, per Moab Municipal Code § 17.06.020's definition of 'building permit.'

  2. 2

    Certificate of Occupancy Sign-off Chain

    Per the official Release for Certificate of Occupancy form: Zoning Director, City Engineer, Public Works Director, and Waste Water/Grand Water Sewer Services approval required for both residential and commercial; Moab Valley Fire Inspector and Southeast Utah Health Department approval additionally required for commercial, before the Building Inspector issues the Certificate of Occupancy.

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Fire Alarm Inspection and Acceptance Test

    Pre-system inspection and acceptance test, billed at $115.00 per hour with a one-hour minimum, per MVFD's fee schedule.

  2. 2

    Moab Valley Fire Inspector — Certificate of Occupancy Sign-off

    Required approval line ('Moab Valley Fire Inspector or Designee: Approved/Denied') on the City's official Release for Certificate of Occupancy form, for all commercial projects.

Re-inspection fees

Residential Building PermitRe-inspection Fee · Moab Municipal Code § 3.50.165, 'Reinspection fees assessed under provisions of Section 305.8 due prior to the reinspection' — 2-hour minimum added by Ordinance #2025-08.
Actual costs plus 10%, 2-hour minimum