Required for rooftop-mounted or ground-mounted solar photovoltaic (PV) systems, including battery backup, in Moab. Moab runs a genuinely distinct solar permitting track from its general Building Permit: a dedicated digital-only Solar PV Plan Review Packet (compiled from the 2014 NEC and 2015 IRC) and its own flat, non-valuation-based fee line items in the Master Fee Schedule (Moab Municipal Code § 3.50.165), most recently raised by Ordinance #2025-08 (adopted June 24, 2025). Moab holds a SolSmart Bronze designation for streamlining residential/commercial solar permitting.

Verified 2026-07-19 · Source

When you need this permit

  • Roof-mounted or ground-mounted solar PV system installation, using micro-inverters or a string inverter (with or without battery backup)
  • Digital-only submittal of the Solar PV Plan Review Packet to inspections@moabcity.org — incomplete or non-digital submittals are returned to the contractor
  • Rapid-shutdown disconnect per NEC 690.12, with location shown on the site plan
  • Design to Moab/Grand County's local structural criteria: 115 mph wind load; ground snow load 36 psf below 5,000 ft or 65 psf at/above 5,000 ft; roof snow load 25 psf below 5,000 ft or 45 psf at/above 5,000 ft
  • Rocky Mountain Power net metering interconnection work order number, if applicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar Permit — roof mount (plus plan review)Moab Municipal Code § 3.50.165 'Building Services' table, as amended by Ordinance #2025-08 (adopted June 24, 2025): 'Solar — roof mount (plus plan review) — update from $130.00/permit to $170.00/permit.' Superseded the $130.00/permit rate shown in the pre-amendment fee schedule still linked from some City agenda archives — confirmed against the ordinance's own itemized change list, not just the after-table.
$170.00/permit
Solar Permit — ground mount (plus plan review)Moab Municipal Code § 3.50.165, per Ordinance #2025-08: 'Solar — ground mount (plus plan review) — update from $195.00/permit to $255.00/permit.'
$255.00/permit
State Building Code Training Fund Surcharge ('State 1%')Statewide surcharge under Utah Code Title 58-56 and Utah Admin. Code R156-15A-230, collected on Moab's official Building Permit Application fee routing box for all permit types including solar.
1% of the building permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Moab?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Per Moab's Solar page, listed as two separate steps: 'Install panels' and 'Have them inspected to ensure they are safe.' Scheduled by calling (435) 259-5129 (24 hours notice required, per the Solar PV Plan Review Packet's building permit application header).

See the full Moab inspection guide — scheduling & re-inspection fees →

Tips

  • Ground-mount solar systems cost more to permit than roof-mount: $255/permit vs. $170/permit, per Ordinance #2025-08 (both up from $130/$195 pre-amendment — verify you're not being quoted the stale pre-2025-08 figures still floating on some older City agenda-archive PDFs).
  • Moab's Solar PV Plan Review Packet is built specifically for MICRO-INVERTER and STRING INVERTER systems (with or without battery backup) — the packet uses green text for micro-inverter-specific items and blue text for string-inverter-specific items.
  • Only digital submittals are accepted; incomplete or paper submittals are returned to the contractor. Many installers submit the permit application on behalf of the homeowner.
  • Moab holds a SolSmart Bronze designation, a national recognition for communities that have streamlined their solar permitting, inspection, and zoning processes.
  • Battery backup systems (Attachment 10) trigger substantially more plan-review documentation than a grid-tied-only system — budget extra lead time if adding storage.

Frequently asked questions

Battery backup is not a separate permit, but it adds Attachment 10 to the Solar PV Plan Review Packet — additional documentation on inverter/battery listings, overcurrent protection, enclosure/ventilation, and required signage at the battery disconnect.

Per Moab Municipal Code § 3.50.165 as amended by Ordinance #2025-08 (June 24, 2025): $170.00/permit for a roof-mount system, or $255.00/permit for a ground-mount system, plus plan review and the statewide 1% surcharge on the building permit fee.

Moab does not publish a plan-review timeline for this permit. Contact Moab City Building Safety / Building Inspection Division (Community Development Department) at (435) 259-5129 for current turnaround.

You'll need: Solar PV Plan Review Packet (Attachments 1-9, plus 10 if battery backup); Building Permit Application. Depending on your project, Moab may also ask for: Battery Backup Supplement (Attachment 10). See the required-documents checklist on this page for details on each.

Moab requires 1 inspection(s) for a solar pv permit, in order: Final Inspection. Schedule each through Moab City Building Safety / Building Inspection Division (Community Development Department) ((435) 259-5129).

Apply through Moab City Building Safety / Building Inspection Division (Community Development Department) at 217 East Center Street, Moab, UT 84532. Phone: (435) 259-5129, email: permitting@moabcity.gov. Office hours: Mon–Thu 8:00 AM – 5:00 PM, Fri 8:00 AM – 12:00 PM. Official information: https://www.moabcity.gov/500/Building-Inspection.

Moab, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a), superseding the 2021 IBC. Moab City's official Building Inspection page (moabcity.gov/500/Building-Inspection) embeds a hidden 'BUILDING CODE' tab whose content is the verbatim text of an old snapshot of Utah Code § 15A-2-103 — live-inspected via DOM extraction 2026-07-16, that embedded text lists only 'Appendix J' (not C and J) and links frozen statute-version pages from 2014-2019, indicating the city's page predates even the pre-7/1/2026 code cycle, let alone the current one. The statute controls regardless of the city page's lag.; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did NOT change this edition in the 7/1/2026 amendment. Matches the (otherwise stale) statute text embedded on Moab's page.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); Moab's embedded page text instead cites 'Appendix Q of the 2021 edition of the International Residential Code' (an older statute numbering, live-inspected 2026-07-16) — reproduced verbatim as history; the current statute's Appendix AQ is added here as the operative citation.; 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d), superseding the 2021 IPC. Moab's embedded page text still shows the 2021 IPC — live-inspected 2026-07-16, confirming lag. The statute controls.; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e), superseding the 2021 IMC. Moab's embedded page text still shows the 2021 IMC — live-inspected 2026-07-16, confirming lag. The statute controls.; 2024 International Fuel Gas Code (IFGC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f), superseding the 2021 IFGC. Moab's embedded page text still shows the 2021 IFGC — live-inspected 2026-07-16, confirming lag. The statute controls.; 2024 International Existing Building Code (IEBC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(i), superseding the 2021 IEBC. Moab's embedded page text still shows the 2021 IEBC — live-inspected 2026-07-16, confirming lag. The statute controls.; 2023 National Electrical Code (NEC) — statewide-mandatory edition per Utah Code § 15A-2-103(1)(g); UNCHANGED by the 7/1/2026 amendment (the 2023 NEC baseline predates this code cycle). Moab's embedded page text still shows the 2020 NEC — live-inspected 2026-07-16, one edition behind the statewide-mandatory floor. Per Utah Code § 15A-1-204 (statewide-mandatory construction code), the 2023 NEC governs regardless of the city's own page.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(h) (no residential/commercial split under current law), superseding Moab's residential/commercial split. Moab's embedded page text still cites 'Residential provisions of the 2015 edition' and 'Commercial provisions of the 2021 edition' of the IECC — live-inspected 2026-07-16, preserved as history — both are now collapsed into the single current 2024 IECC. The statute controls.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not present anywhere in the statute text Moab's own page embeds (live-inspected 2026-07-16 — that embedded text predates the ISPSC's addition to § 15A-2-103 and instead references now-superseded mobile/manufactured-home provisions), added here per the current statute.; Modular Building Institute (MBI) Standards 1200 and 1205 — statewide per Utah Code § 15A-2-103(1)(o); not present in the statute text Moab's own page embeds, added here per the current statute.; All per Moab City's official Building Inspection Department page (moabcity.gov/500/Building-Inspection), consistent with Utah Code § 15A-2-103 statewide code adoption.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Moab's Building Inspection page (moabcity.gov/500/Building-Inspection) was live-inspected 2026-07-16 via DOM extraction of its hidden 'BUILDING CODE' tab panel, which turns out to embed the raw text of an old snapshot of § 15A-2-103 itself (with hyperlinks to frozen statute-version pages dated 2014-2019) rather than a city-authored summary — meaning Moab's page is not merely one cycle behind but reflects a substantially older statute snapshot (pre-dating even the introduction of the residential ISPSC provision). The current statewide statute, read live at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html, controls over this stale embedded text.. Local amendments apply — see the Moab overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Moab building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.