Sign Permit — Moab, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://www.moabcity.gov/DocumentCenter/View/2805/Sign-Permit-Application_fillable
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Sign Permit in Moab, Utah
Required in Moab for construction, creation, or installation of a new sign, or structural alteration of an existing sign, per Moab Municipal Code Chapter 17.93 Sign Code. A building permit may also be required. Fee is based on total sign square footage.
Verified 2026-07-20 · Source
When you need this permit
- Construction, creation, or installation of a new sign, or structural alteration of an existing sign
- One sign permit application may cover multiple signs on the same lot
- Detailed scale drawing(s) of all existing and proposed signs on the lot
- UDOT Roadside Advertising Permit required in addition, for signs located along Highway 191
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Moab inspection guide — scheduling & re-inspection fees →
Tips
- All complete sign permit applications are subject to a five (5) day review period (the source does not specify business days vs. calendar days) by city staff, per the Sign Permit Application.
- The Building Official reviews every sign permit application to determine whether a separate building permit is also required — this is marked on the application itself.
- Signs along Highway 191 need a UDOT Roadside Advertising Permit in addition to the city sign permit.
- The $50 minimum fee covers total combined sign area up to 30 square feet; larger or multiple signs on one lot are billed at $0.50 per additional square foot over that threshold.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Moab building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Moab
Sign Permit in other cities
Compare sign permit fees across Utah →