EV Charger / EVSE Permit — Moab, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://www.moabcity.gov/AgendaCenter/ViewFile/Item/7191?fileID=9321
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Moab, Utah
Moab does not publish a distinct EV-charger fee line item. Per the Moab Municipal Code Chapter 3.50 Master Fee Schedule, a standalone EV charger/EVSE installation is electrical work billed under the city's 'Separate mechanical, electrical, and/or plumbing permits' fee — $65.00 per inspection — rather than the valuation-based Building Permit fee, which applies to work tied to new construction.
Verified 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- New dedicated circuit and/or panel/service capacity to serve the charger
- Building Permit Application submitted to the City of Moab Building Official (permitting@moabcity.gov) or via the City of Moab online portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
Inspection of the installed circuit, panel work, and EVSE equipment; billed at $65.00 under the Separate mechanical/electrical/plumbing permits fee.
See the full Moab inspection guide — scheduling & re-inspection fees →
Tips
- Moab has no distinct EV charger permit category — a standalone charger circuit/panel install is billed as a 'Separate mechanical, electrical, and/or plumbing permit' at $65.00 per inspection.
- The City of Moab operates its own public EV charging infrastructure (Lions Park NEVI fast chargers, downtown Level 2 chargers), but this is a separate program from the private-property EV charger permitting process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Moab building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Moab
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Moab project checklist
Describe your project once and get every permit, document, and fee it triggers in Moab — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →