Inspection sequence, scheduling, and re-inspection fees for building permits in South Jordan, Utah.

Verified 2026-06-30 · Source

How to schedule

Inspections are requested through the building department below.

Address
1600 West Towne Center Drive, South Jordan, UT 84095
Phone
(801) 446-4357
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Published scheduling rules

  • South Jordan uses the CityView online portal for all permit applications and inspection scheduling: cityview.southjordanutah.gov/CityViewPortal. (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Underground / Rough-In (MEP)

    Before backfill and before closing walls or ceilings

  3. 3

    Framing

    After framing, sheathing, and rough-in mechanical/electrical/plumbing

  4. 4

    Fire Sprinkler / Alarm

    Commercial Sprinkler Plan Review and System Inspection, priced per the ICC/SJC Valuation Fee Schedule

  5. 5

    Final

    All work complete — certificate of occupancy issued upon passing final inspection

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls, vapor barrier placement

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Residential Building Permit

  1. 1

    Foundation

    Before concrete pour — forms, rebar, anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before gunite/shotcrete

  2. 2

    Electrical / Bonding

    Pool bonding grid, equipment connections, GFCI protection per 2023 NEC Article 680

  3. 3

    Barrier

    Pool fence/barrier — minimum 48-inch height, self-closing/self-latching gates

  4. 4

    Final

    Pool complete, filled, equipment operational, all barriers in place

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    Before concrete pour — forms, rebar, anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Final

    All work complete, ready for occupancy

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Rough-In (MEP)

    After framing and rough-in mechanical, electrical, and plumbing work

  2. 2

    Fire Sprinkler / Alarm (if applicable)

    Commercial Sprinkler Plan Review and System Inspection where the scope modifies existing fire suppression systems

  3. 3

    Final

    All work complete; space approved for occupancy under the tenant's use classification

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (30-inch frost depth minimum), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Fire Sprinkler & Fire Alarm Permit

  1. 1

    Underground / Rough-In

    Underground sprinkler piping and rough fire alarm wiring — before backfill or concealment

  2. 2

    System Acceptance Test

    Hydrostatic/flow test of the sprinkler system and functional test of the fire alarm system per the adopted fire-protection code

  3. 3

    Final

    South Jordan Fire Department final sign-off, requested by emailing sjcinspections@sjc.utah.gov — required on the Certificate of Occupancy checklist before occupancy is approved

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Residential Addition Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar per frost depth (30 in minimum)

  2. 2

    Framing

    After framing and sheathing — before insulation or wall cover

  3. 3

    Final

    All work complete

Applies to: Retaining Wall Permit

  1. 1

    Footing

    Footing excavation, rebar, and forms before concrete pour

  2. 2

    Backfill / Drainage

    Drainage gravel, pipe, and filter fabric before backfill

  3. 3

    Final

    Wall complete, drainage functional, site graded

Applies to: Shed & Accessory Structure Permit

  1. 1

    Foundation

    Footings or slab prep before concrete pour

  2. 2

    Framing

    Structure framing, sheathing, and anchor connections

  3. 3

    Final

    Structure complete, roofing, siding, and any electrical or plumbing

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and DEQ/SLCO clearances are in hand before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped per approved plan

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support for the EVSE circuit.

  2. 2

    Final

    Charger mounted and energized, GFCI/breaker protection verified per NEC Article 625 (Electric Vehicle Power Transfer System).

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances and support

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition and replace damaged decking before proceeding

  2. 2

    Final

    Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Residential Building PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule, rendered 2026-07-11
$182
Residential Addition PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Electrical PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Plumbing PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule (page 4, rendered 2026-07-01)
$182
Mechanical / HVAC PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule (page 4, rendered 2026-07-01)
$182
Roofing PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Solar Panel PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Deck PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Basement Finish PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Accessory Dwelling Unit (ADU) PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule, page 4, rendered 2026-07-01
$182
Water Heater PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Demolition PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Swimming Pool PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Retaining Wall PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Shed & Accessory Structure PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule
$182
Commercial Building PermitCommercial Sprinkler Plan Review / System Inspection · South Jordan FY 2026-2027 Fee Schedule, Fire Department Fees section; $135 for each re-inspection after the second
Per ICC/SJC Valuation Fee Schedule
Commercial Building PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule, Building & Engineering Fees section
$182
Commercial Tenant Improvement / Tenant Finish PermitCommercial Sprinkler Plan Review / System Inspection · South Jordan FY 2026-2027 Fee Schedule, Fire Department Fees section — applies where the tenant improvement scope modifies existing fire suppression systems; $135 for each re-inspection after the second
Per ICC/SJC Valuation Fee Schedule
Commercial Tenant Improvement / Tenant Finish PermitRe-inspection Fee · South Jordan FY 2026-2027 Fee Schedule, Building & Engineering Fees section
$182
Fire Sprinkler & Fire Alarm PermitCommercial Sprinkler Plan Review / System Inspection · South Jordan FY 2026-2027 Fee Schedule, Fire Department Fees section — 'Commercial Sprinkler Plan Review/System Inspection'; $135 for each re-inspection after the second (this matches the identical grounded fee already recorded on this jurisdiction's commercial-building-permit and commercial-tenant-improvement-permit entries).
Per ICC/SJC Valuation Fee Schedule
Fire Sprinkler & Fire Alarm PermitResidential Sprinkler Plan Review / System Inspection · South Jordan FY 2026-2027 Fee Schedule, Fire Department Fees section — 'Residential Sprinkler Plan Review/System Inspection', with $50 for each re-inspection after the second. FLAGGED: this row is wrapped across multiple lines in the source PDF table and its exact value-to-column attribution is genuinely ambiguous on direct render — confirmed by two independent extraction passes (rendered-image read and pdftotext -layout) on 2026-07-22, both producing slightly different row groupings for the $135/$50 figures. Both figures are real, published numbers on this fee line; only their precise base-fee-vs-re-inspection-fee assignment could not be resolved with full certainty. Contact South Jordan Fire Department at (801) 254-3742 to confirm the exact breakdown.
$135

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Jordan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

South Jordan building permits

Get alerts for South Jordan

We'll email you when South Jordan's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.