When you need this permit
- Complete roof replacement (tear-off and re-roof)
- Overlay of new roofing over existing (where allowed)
- Structural roof repairs or modifications
- Changes to roofing material type
Required documents
- Req
Roofing Application
Scope of work, square footage, and material specifications
- Req
Contractor License
Valid Utah roofing contractor license (DOPL)
- Opt
Manufacturer Specs
Product data for roofing material and underlayment
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roof Permit | $193 | — |
Review timeline
~1–3 business days
Typical estimate — confirm current times with the South Jordan building department
Inspection process
- 1
Deck/Substrate
After tear-off — verify sheathing condition, replace damaged decking
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, ventilation, and nailing pattern
Tips
- South Jordan allows a maximum of two roofing layers — if you already have two, a full tear-off is required.
- Ice and water shield is required in valleys, eaves (first 24 inches), and around penetrations.
- Roofing permits in South Jordan are typically reviewed same-day or next-day — fastest permit type.
- Schedule the deck inspection before installing underlayment — inspectors need to see the sheathing.
Frequently asked questions
- Do I need a permit to replace my roof in South Jordan?
- Yes. South Jordan requires a roofing permit for all roof replacements and re-roofing projects. The permit covers inspections of the roof deck and final installation to ensure code compliance.
- How long does a roofing permit take in South Jordan?
- Roofing permits in South Jordan are typically approved within 1-3 business days, often same-day. They are the fastest residential permit type to obtain.
Sources & verification
Key facts verified against official sources. Last reviewed 2026-06-27.
- South Jordan Building Department — official building department
- South Jordan FY2025-2026 Fee Schedule
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the South Jordan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in South Jordan
Related guides
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.