Park City building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Park City, Utah.
Verified 2026-07-08 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 445 Marsac Avenue, PO Box 1480, Park City, UT 84060
- Phone
- (435) 615-5101
- Office hours
- Monday–Friday 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- Park City requires ALL permit applications and most inspection scheduling to go through the City Inspect (MCI) online portal — first-time users must register before applying, per the city's official 'How to Register for City Inspect (MCI)' guide. (Residential Building Permit)
- All permit types (building, trade, operational/fire) and most inspection scheduling go through the City Inspect (MCI) online portal — first-time applicants must register before applying. (General)
Inspection sequence
Applies to: Commercial Building Permit
- 1
Limits of Disturbance (LOD)
Scheduled through the Building Department (435-615-5101) alongside a Pre-Construction meeting once the permit is approved; a passing LOD inspection is required before construction can begin, per Park City's official Permit FAQs.
- 2
Building, Framing, and Trade Inspections
Scheduled through City Inspect. Next-day inspection available when scheduled by 3 p.m. the prior business day. Per Park City's official Inspections page, in accordance with 2024 Senate Bill 185, if an ICC-required inspection is not performed within 3 business days of the requested date, the applicant may contact one of the city's listed third-party inspection agencies (Shums Coda Associates, WC3, Sunrise Engineering).
- 3
Fire Code Compliance
Commercial occupancies are subject to the adopted International Fire Code; an IFC Issuance Fee ($154.00 per Fee Schedule § 1.2.7) applies, and fire-specific sign-off is coordinated as part of the plan review and inspection process. No separate city fee for fire sprinkler/alarm plan review specific to new commercial construction was found in the Fee Schedule — verify current fire-system review requirements with the Building Department.
- 4
Final Inspection / Certificate of Occupancy
Final sign-off scheduled through City Inspect once all trade and Limits of Disturbance items are complete, per Park City's official Building Inspection Process Guide and Certificate of Occupancy Prior to Site Completion Request form.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In (Mechanical, Electrical, Plumbing)
After framing and rough-in MEP work — before insulation or wall cover. Scheduled through City Inspect.
- 2
Fire Code Compliance (if applicable)
Required where the TI scope modifies existing fire suppression or alarm systems in the commercial space, coordinated as part of plan review and inspection. No separate city fee specific to TI fire-system plan review was found in the Fee Schedule — only the general IFC Issuance Fee ($154.00, § 1.2.7) is published; confirm current fire-system review costs with the Building Department.
- 3
Final Inspection / Certificate of Occupancy
Final sign-off scheduled through City Inspect once all trade items are complete, per Park City's official Building Inspection Process Guide.
Applies to: Residential Building Permit
- 1
Limits of Disturbance (LOD)
Scheduled through the Building Department (435-615-5101) alongside a Pre-Construction meeting once the permit is approved; a passing LOD inspection is required before construction can begin, per Park City's official Permit FAQs.
- 2
Building, Framing, and Trade Inspections
Scheduled through City Inspect. Next-day inspection available when scheduled by 3 p.m. the prior business day. AM inspections run 8 a.m.–noon; PM inspections run noon–4 p.m. Per Park City's official Inspections page, in accordance with 2024 Senate Bill 185, if an ICC-required inspection is not performed within 3 business days of the requested date, the applicant may contact one of the city's listed third-party inspection agencies (Shums Coda Associates, WC3, Sunrise Engineering).
- 3
Final Inspection / Certificate of Occupancy
Final sign-off scheduled through City Inspect once all trade and Limits of Disturbance items are complete, per Park City's official Building Inspection Process Guide and Certificate of Occupancy Prior to Site Completion Request form.
Applies to: Change of Use / Change of Occupancy Permit
- 1
Building / Fire / Planning Sign-Off Review
Same parallel review disciplines used for other Park City commercial permits (Building, Fire Safety, Planning/zoning, Engineering) confirm the space meets applicable code requirements for its new occupancy classification before a Certificate of Occupancy is issued.
- 2
Final Inspection / Certificate of Occupancy
Per the adopted IBC Sec. 111, no change of occupancy may occur until the Building Official issues a Certificate of Occupancy, scheduled through City Inspect once all upgrade work and sign-offs are complete.
Applies to: Solar PV Permit
- 1
Solar Installation Site Visit
Park City Building Department staff follow an inspection checklist as part of a site visit conducted during and/or after the solar installation process, to confirm all applicable codes have been followed, per the city's official Solar PV Permitting Info page.
- 2
Net Metering Final Sign-Off
Not a code inspection but a required prerequisite to final project approval: Rocky Mountain Power must complete the Net Metering Agreement and set up the appropriate meter for grid-connected systems before Park City grants final sign-off.
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Park City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Park City building permits
Get alerts for Park City
We'll email you when Park City's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.