Change of Use / Change of Occupancy Permit in Park City, Utah
Park City has no distinct standalone 'change of use' or 'change of occupancy' application or fee — confirmed by direct review of the Building Department's official Permits page, its Forms, Codes & Resources page (which lists every official Building form and includes no such document), and the full-text Fee Schedule (effective October 20, 2025), none of which itemize a change-of-use product. Park City has adopted the 2024 International Existing Building Code (IEBC) statewide per Utah Code § 15A-2-103(1)(i), whose Chapter 10 'Change of Occupancy' provisions govern any building or space changing use or occupancy classification, and the adopted IBC Sec. 111 requires that no building or portion be used, occupied, or have its occupancy changed until the Building Official issues a Certificate of Occupancy. A change of use is therefore processed as an application under the existing Commercial Building Permit or Commercial Tenant Improvement Permit (whichever matches the scope of work), billed at that permit's standard valuation-based fee, with no separate line item — consistent with this file's own Commercial Tenant Improvement Permit entry, which already notes that 'a change of occupancy classification (e.g., retail to restaurant) may trigger additional code requirements under the adopted 2024 IEBC.'
Verified 2026-07-22 · Source
When you need this permit
- Any change in use or occupancy classification of an existing building or tenant space that would place it in a different IBC/IEBC occupancy group requires compliance with the adopted 2024 IEBC Chapter 10 'Change of Occupancy' provisions, subject to Building Official review
- No building, structure, or portion may be used, occupied, or have its occupancy changed until the Building Official issues a Certificate of Occupancy, per the adopted IBC Sec. 111
- Application submitted through the City Inspect (MCI) online portal as a Commercial Building Permit or Commercial Tenant Improvement Permit application (whichever matches the scope of work), since Park City does not offer a distinct 'change of use' application type
- Planning Department zoning compliance review for the new use under the Land Management Code, Title 15
- Any upgrade work identified as necessary to bring the space into compliance with the new occupancy classification requires its own building/trade permits
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building / Fire / Planning Sign-Off Review
Same parallel review disciplines used for other Park City commercial permits (Building, Fire Safety, Planning/zoning, Engineering) confirm the space meets applicable code requirements for its new occupancy classification before a Certificate of Occupancy is issued.
- 2
Final Inspection / Certificate of Occupancy
Per the adopted IBC Sec. 111, no change of occupancy may occur until the Building Official issues a Certificate of Occupancy, scheduled through City Inspect once all upgrade work and sign-offs are complete.
See the full Park City inspection guide — scheduling & re-inspection fees →
Tips
- Park City does not offer a distinct 'change of use' or 'change of occupancy' permit application or fee — it is processed as a standard Commercial Building Permit or Commercial Tenant Improvement Permit application through City Inspect (MCI), confirmed by the absence of any such form on the Building Department's official Forms, Codes & Resources page.
- The adopted 2024 International Existing Building Code (IEBC) Chapter 10 governs change-of-occupancy compliance — a change to a higher-hazard occupancy classification can trigger substantial upgrade requirements (egress, fire-resistance, accessibility) that are not automatically grandfathered.
- No space may be occupied under a new use until the Building Official issues a Certificate of Occupancy, per the adopted IBC Sec. 111 — budget time for this even if no physical construction is otherwise required.
- Because there is no distinct change-of-use fee line item, budget for the full 0.61% Commercial Permit rate (or Commercial Tenant Improvement rate) applied to whatever upgrade work your occupancy-classification change requires, plus the $2,000 commercial Plan Check Deposit and 65% Plan Check Fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Park City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Park City
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Park City project checklist
Describe your project once and get every permit, document, and fee it triggers in Park City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →