Plumbing Permit in Park City, Utah

Required for plumbing installations and alterations in Park City not incidental to a covered building permit. Fee is valuation-based (1.32% of construction valuation).

Verified 2026-07-08 · Source

When you need this permit

  • New plumbing fixture installations, water heater installation/replacement, or water/sewer/gas line work not covered under an active building permit
  • Application submitted through the City Inspect (MCI) online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plumbing Permit FeePark City Fee Schedule (effective October 20, 2025) § 1.2.6 'Plumbing Permit.'
1.32% of the total valuation of construction, plus 1% state surcharge

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in Park City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough and Final Plumbing

    Scheduled through City Inspect; next-day inspection available when scheduled by 3 p.m. the prior business day, per Park City's official Inspections page.

See the full Park City inspection guide — scheduling & re-inspection fees →

Tips

  • Plumbing work performed as part of new construction or an addition is typically reviewed under the associated Building Permit's trade plan review rather than requiring a separate standalone Plumbing Permit.

Frequently asked questions

Park City requires a plumbing permit for: New plumbing fixture installations, water heater installation/replacement, or water/sewer/gas line work not covered under an active building permit; Application submitted through the City Inspect (MCI) online portal. If your project isn't listed, confirm with Park City Building Department (Community Development) at (435) 615-5101 before starting work.

Per Park City's Fee Schedule (effective October 20, 2025), the Plumbing Permit fee is 1.32% of the total valuation of construction, plus a 1% state surcharge.

Park City does not publish a plan-review timeline for this permit. Contact Park City Building Department (Community Development) at (435) 615-5101 for current turnaround.

You'll need: City Inspect (MCI) Permit Application. See the required-documents checklist on this page for details on each.

Park City requires 1 inspection(s) for a plumbing permit, in order: Rough and Final Plumbing. Schedule each through Park City Building Department (Community Development) ((435) 615-5101).

Apply through Park City Building Department (Community Development) at 445 Marsac Avenue, PO Box 1480, Park City, UT 84060. Phone: (435) 615-5101. Office hours: Monday–Friday 8:00 AM – 5:00 PM. Official information: https://www.parkcity.org/services/building/index.php.

Park City, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J, with Utah amendments — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition previously listed here. Park City's Building Department Forms, Codes & Resources page (live-checked 2026-07-16) states 'All codes to include Utah Amendments' and links to the State of Utah's code list rather than publishing a separate locally-itemized edition, consistent with the statewide adoption model used by other Utah jurisdictions in this corpus (e.g., Murray, Coalville).; 2021 International Residential Code (IRC) with Utah amendments — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition.; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized on Park City's own Forms, Codes & Resources page, added here per statute.; 2024 International Plumbing Code (IPC) with Utah amendments — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); supersedes the 2021 edition previously listed here.; 2024 International Mechanical Code (IMC) with Utah amendments — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); supersedes the 2021 edition previously listed here.; 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103(1)(f); not itemized on Park City's own Forms, Codes & Resources page, added here per statute since the City's own materials omit it.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition, with Utah amendments — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); supersedes the 2021 edition previously listed here.; 2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 statewide transition.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not itemized on Park City's own Forms, Codes & Resources page, added here per statute since the City's own materials omit it.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized on Park City's own Forms, Codes & Resources page, added here per statute since the City's own materials omit it.; International Wildland-Urban Interface Code (IWUIC), 2006 edition with State of Utah amendments, further amended and locally adopted by Park City in June 2020 — codified at Park City Municipal Code Sec. 11-21-1. Genuine local amendment: compliance is a required part of the building permit plan review process for applicable properties, per the city's official Wildland Urban Interface Code FAQ page. NOTE: the IWUIC is adopted under Utah Code § 15A-2-103(2), a distinct provision from the Subsection (1) code list above that allows local compliance agencies to adopt the 2006 IWUIC by local ordinance as a local amendment — it is unaffected by the Subsection (1) edition transition on 7/1/2026 and was not touched by this re-verification.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Park City's Forms, Codes & Resources page (parkcity.org/services/building/forms/index.php) was live-checked 2026-07-16 and does not itemize specific code edition years at all — it states generically 'All codes to include Utah Amendments' and links to the state code, so no page-vs-statute lag could be detected; the statute is cited directly as governing throughout. Park City's substantial resort-town local amendments (WUI Code, Land Management Code Title 15, Fee Schedule) are unaffected and left untouched.. Local amendments apply — see the Park City overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Park City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.