EV Charger / EVSE Permit in Park City, Utah
Park City has no distinct, codified EV charger/EVSE permit type or fee line item — EV charger installation is electrical work billed under the city's standard Electrical Permit (1.32% of construction valuation, plus 1% state surcharge), per the Park City Fee Schedule effective October 20, 2025. Park City's Environmental Sustainability office has separately advertised (via an archived 'Electric Vehicle Charger Incentives' outreach page) that building permit fees for EV charging equipment are waived, but this waiver is NOT reflected in the currently effective codified Fee Schedule, which only excludes on-site renewable energy systems (solar PV, ground source heat pumps, solar hot water) from the building-permit valuation base — not EV chargers. This is a genuine, unresolved discrepancy between city outreach messaging and the codified fee schedule.
Reviewed 2026-07-20 · Source
When you need this permit
- New electrical circuit or panel capacity dedicated to a Level 2 or DC fast EV charger (EVSE), not covered under an active building permit
- Application submitted through the City Inspect (MCI) online portal
- Confirm with the Environmental Sustainability office (435-615-5193) whether an EV-charger permit-fee waiver is currently being honored, since it is not written into the codified Fee Schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough and Final Electrical
Scheduled through City Inspect; next-day inspection available when scheduled by 3 p.m. the prior business day. AM inspections 8 a.m.-noon, PM inspections noon-4 p.m., per Park City's official Inspections page.
See the full Park City inspection guide — scheduling & re-inspection fees →
Tips
- Before applying, ask the Environmental Sustainability office (435-615-5193, celia.peterson@parkcity.org) whether an EV-charger permit-fee waiver is currently being honored — the program was publicly advertised on the city's sustainability pages but is not written into the codified Fee Schedule, so it may be discretionary or no longer active.
- Absent a confirmed waiver, EV charger installation is billed as standard electrical work at 1.32% of construction valuation plus a 1% state surcharge, per § 1.2.5 of the Fee Schedule.
- The codified valuation exclusion in § 1.2.2 covers on-site renewable energy systems (solar, ground source heat pumps, solar hot water) but does NOT name EV charging equipment — do not assume the exclusion extends to EV chargers without confirming with the Building Department.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Park City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Park City
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Park City project checklist
Describe your project once and get every permit, document, and fee it triggers in Park City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →