Commercial Building Permit — Park City, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.parkcity.org/services/building/permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Park City, Utah
Required for new commercial building construction, commercial shell buildings, and ground-up commercial additions in Park City, regulated by the adopted 2024 IBC. Park City bills the Commercial Permit at the same valuation-based rate as residential construction (0.61% of total valuation) per Fee Schedule § 1.2.2, but requires a larger, $2,000 non-refundable Plan Check Deposit (vs. $500 for residential buildings) given the added complexity of commercial plan review, plus the standard 65% Plan Check Fee. Properties within Park City's Historic District (Old Town / Main Street) additionally require Planning Department Historic Design Review before or alongside building permit issuance.
Verified 2026-07-19 · Source
When you need this permit
- New commercial building construction, commercial shell building, or addition regulated by the adopted 2024 IBC that is not exempt under IBC Sec. 105.2
- Application submitted through the City Inspect (MCI) online portal
- Planning Department review for zoning compliance (setbacks, building height, design, parking) under the Land Management Code, Title 15
- Historic Design Review by the Planning Department/Historic Preservation Board if the property is within Park City's Historic District (Old Town / Main Street), per Fee Schedule § 1.1.7
- Compliance with the Wildland-Urban Interface Code (Sec. 11-21-1) where applicable, determined via the WUI worksheet as part of plan review
- Construction Mitigation Plan reviewed by Community Code Compliance
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Limits of Disturbance (LOD)
Scheduled through the Building Department (435-615-5101) alongside a Pre-Construction meeting once the permit is approved; a passing LOD inspection is required before construction can begin, per Park City's official Permit FAQs.
- 2
Building, Framing, and Trade Inspections
Scheduled through City Inspect. Next-day inspection available when scheduled by 3 p.m. the prior business day. Per Park City's official Inspections page, in accordance with 2024 Senate Bill 185, if an ICC-required inspection is not performed within 3 business days of the requested date, the applicant may contact one of the city's listed third-party inspection agencies (Shums Coda Associates, WC3, Sunrise Engineering).
- 3
Fire Code Compliance
Commercial occupancies are subject to the adopted International Fire Code; an IFC Issuance Fee ($154.00 per Fee Schedule § 1.2.7) applies, and fire-specific sign-off is coordinated as part of the plan review and inspection process. No separate city fee for fire sprinkler/alarm plan review specific to new commercial construction was found in the Fee Schedule — verify current fire-system review requirements with the Building Department.
- 4
Final Inspection / Certificate of Occupancy
Final sign-off scheduled through City Inspect once all trade and Limits of Disturbance items are complete, per Park City's official Building Inspection Process Guide and Certificate of Occupancy Prior to Site Completion Request form.
See the full Park City inspection guide — scheduling & re-inspection fees →
Tips
- Park City bills commercial and residential building permits at the identical 0.61% valuation-based rate, but commercial buildings require a $2,000 non-refundable Plan Check Deposit — four times the $500 residential deposit — reflecting the added complexity of commercial plan review.
- Properties within Park City's Historic District (Old Town / Main Street) require a separate Planning Department Historic Design Review ($497 or $1,518 depending on whether existing area increases) in addition to the Building Permit — budget this into both timeline and cost.
- Large or complex commercial projects may require outside consultants for plan review or inspection, billed at actual cost per Fee Schedule § 1.2.12 — this is uncapped and can be significant for resort-scale construction.
- As with residential permits, renewable energy system value (solar PV, ground source heat pumps, solar hot water) is excluded from the total construction valuation used to calculate the building permit fee.
- No Park City-specific commercial plan-review turnaround time is published anywhere the city's official materials — confirm current timing directly with the Building Department (435-615-5101) before committing to a project schedule.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Park City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Park City.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Park City
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Park City project checklist
Describe your project once and get every permit, document, and fee it triggers in Park City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →