Eagle Mountain building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Eagle Mountain, Utah.
Verified 2026-06-30 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 3726 E Campus Drive, Suites D & H, Eagle Mountain, Utah 84005
- Phone
- (801) 789-6600
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- Cancel inspection requests before 9 AM to avoid being charged — cancellations received after 9 AM are processed on the next business day. (Residential Building Permit)
- All inspections must be scheduled via email to buildinginspections@eaglemountain.gov. (Basement Finish Permit)
- All inspections must be scheduled via email to buildinginspections@eaglemountain.gov. (Deck Permit)
- Power inspections must include the Rocky Mountain Power (RMP) work order number in the inspection request email. (Residential Solar Permit)
- All inspections must be scheduled via email to buildinginspections@eaglemountain.gov. (Residential Pool Permit)
- All inspections in Eagle Mountain must be scheduled via email to buildinginspections@eaglemountain.gov — walk-ins are not accepted. Power inspections must include the Rocky Mountain Power (RMP) work order number. Cancel requests before 9 AM or they are processed the next business day. (General)
Inspection sequence
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, and egress window openings verified before walls are closed
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and roof — before insulation
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete, ready for occupancy — certificate of occupancy issued upon passing
Applies to: Residential Pool Permit
- 1
Pre-Gunite / Shell
Steel reinforcement and plumbing before gunite or shell installation
- 2
Electrical / Bonding
Pool bonding, grounding, and electrical connections
- 3
Barrier
Pool fence/barrier compliance — gates, latches, minimum 6-foot height
- 4
Final
All work complete, pool filled, equipment operational
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour. Eagle Mountain does not publish a separate commercial-specific inspection checklist distinct from its general building inspection sequence.
- 2
Framing
After framing, sheathing, and roof — before insulation.
- 3
Final
All work complete, ready for occupancy — certificate of occupancy issued upon passing (see Eagle Mountain's separate Commercial Certificate of Occupancy Checklist).
Applies to: Deck Permit
- 1
Footings
Footing excavation to required depth, rebar, and forms before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete
Applies to: Retaining Wall Permit
- 1
Footing
Footing excavation, rebar, and forms before concrete pour
- 2
Backfill / Drainage
Drainage gravel, pipe, and filter fabric before backfill
- 3
Final
Wall complete, drainage functional, site graded
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural
Where structural or MEP changes are part of the tenant-improvement scope, before close-in.
- 2
Final
All work complete, ready for occupancy — see Eagle Mountain's separate Commercial Certificate of Occupancy Checklist.
Applies to: Residential Solar Permit
- 1
Rough Electrical
Conduit runs, wire sizing, and disconnect placement before energizing
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Accessory Dwelling Unit (ADU) Permit, Change of Use / Change of Occupancy Permit, EV Charger / EVSE Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagle Mountain building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Eagle Mountain building permits
Get alerts for Eagle Mountain
We'll email you when Eagle Mountain's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.