Commercial Building Permit in Eagle Mountain, Utah
Required for new commercial building construction in Eagle Mountain. Plan review is conducted by a third-party plan review contractor (WC3) in parallel with the Planning Department; the Planning Department must issue an approval letter before the building permit application is submitted. Fees are valuation-based per the Consolidated Fee Schedule (updated March 3, 2026), with a Commercial Plan Review Fee of 65% — distinct from the 40% Residential Plan Review Fee in the same schedule.
Verified 2026-07-19 · Source
When you need this permit
- Approval letter from the Eagle Mountain Planning Department obtained before permit application submittal — per the city's official Commercial Building Permit Instructions: 'Please note that we need all approvals before we can issue a permit #'
- Completed building permit application submitted with the approval letter and builder's deposit to 3726 E Campus Dr Suite H
- Builder's deposit of $5,000.00 for a new commercial building, paid by check to Eagle Mountain City
- Complete construction documents submitted electronically to WC3 (permitdeskutah@wc-3.com) and to Planning (planning@eaglemountain.gov) in PDF format
- Written response to each plan review comment on resubmittal, with changes recommended to be clouded on the plans
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Before concrete pour. Eagle Mountain does not publish a separate commercial-specific inspection checklist distinct from its general building inspection sequence.
- 2
Framing
After framing, sheathing, and roof — before insulation.
- 3
Final
All work complete, ready for occupancy — certificate of occupancy issued upon passing (see Eagle Mountain's separate Commercial Certificate of Occupancy Checklist).
See the full Eagle Mountain inspection guide — scheduling & re-inspection fees →
Tips
- Eagle Mountain requires Planning Department approval BEFORE the building permit application is submitted — 'we need all approvals before we can issue a permit #' per the city's Commercial Building Permit Instructions.
- Plan review for commercial projects is handled by a third-party contractor, WC3 (permitdeskutah@wc-3.com), not directly by city staff — direct plan-review-comment questions to the WC3 reviewer named in the Plan Review Response Letter, not the city.
- Commercial Plan Review Fee is 65% of the permit fee — notably higher than the 40% Residential Plan Review Fee in the same Consolidated Fee Schedule (Section 13.3).
- The $5,000 builder's deposit is specific to new commercial buildings; a commercial tenant improvement project instead requires only a $1,000 deposit plus a copy of the lease agreement.
- Fire code enforcement, and fire sprinkler/alarm system plan review, for Eagle Mountain is handled by the Unified Fire Authority (UFA) — Eagle Mountain City is a listed UFA member community (unifiedfireut.gov/prevention/plan-reviews/), not the city's own Building Department. Eagle Mountain's own Consolidated Fee Schedule (updated March 3, 2026, eaglemountain.gov) has no Fire Department fee section at all, and UFA's own published FY2025-26 Adopted Budget Book Appendix A Fee Schedule 'Prevention Fees & Permits' table (unifiedfireut.gov, checked 2026-07-20) lists only hazardous-materials, fireworks, blasting, and special-enforcement permit fees — no fire sprinkler or fire alarm plan-review line item. Per UFA's own Plan Reviews page, automatic fire protection system and fire alarm/detection system plans instead require a mandatory third-party 'technical opinion and report' (peer review) by a UFA-approved third-party review company (exceptions: installations under 20 sprinkler heads or under 5 alarm/notification appliances) — the fee for that review is paid to the third-party reviewer directly, not published as a flat UFA or city fee. Confirm current third-party review costs directly with UFA Fire Prevention (801-743-7200) before budgeting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagle Mountain building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Eagle Mountain.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Eagle Mountain
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →