Residential Building Permit in Eagle Mountain, Utah

Required for new residential construction, additions, and structural alterations in Eagle Mountain. Permit fees are valuation-based per the Consolidated Fee Schedule (updated March 3, 2026). Plan review is approximately 14 business days. Applications submitted through the OpenGov portal. Eagle Mountain's Consolidated Fee Schedule (rev. 12/03/2024) prices all building permits — including electrical work — on the same total-valuation table, plus a 'Non-Valuation Based Permit – Inspection Only' fee of $50 per inspection for small standalone jobs; no distinct EV charger/EVSE fee line item was found as of 2026-07-19, so a standalone home EV charger installation would be priced under this general valuation table or the $50 inspection-only fee.

Verified 2026-06-30 · Source

When you need this permit

  • New single-family or multi-family residential construction
  • Additions to existing structures
  • Structural modifications — load-bearing wall removal, foundation alterations
  • Conversion of non-habitable space to habitable space

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation $1.00–$500Eagle Mountain Consolidated Fee Schedule, updated March 3, 2026; building permit fees last revised 12/03/2024 (Section 13.1)
$24
Building Permit — valuation $501–$2,000Eagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$24 for the first $500, plus $3 for each additional $100 or fraction thereof, to and including $2,000
Building Permit — valuation $2,001–$40,000Eagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$69 for the first $2,000, plus $7 for each additional $1,000 or fraction thereof, to and including $40,000
Building Permit — valuation $40,001–$100,000Eagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$335 for the first $40,000, plus $5 for each additional $1,000 or fraction thereof, to and including $100,000
Building Permit — valuation $100,001–$500,000Eagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$635 for the first $100,000, plus $2 for each additional $1,000 or fraction thereof, to and including $500,000
Building Permit — valuation $500,001–$1,000,000Eagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$1,435 for the first $500,000, plus $3 for each additional $1,000 or fraction thereof, to and including $1,000,000
Building Permit — valuation $1,000,001–$5,000,000Eagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$2,935 for the first $1,000,000, plus $3 for each additional $1,000 or fraction thereof, to and including $5,000,000
Building Permit — valuation $5,000,001 and upEagle Mountain Consolidated Fee Schedule, Section 13.1 (revised 12/03/2024)
$14,935 for the first $5,000,000, plus $2 for each additional $1,000 or fraction thereof
Plan Review Fee — ResidentialEagle Mountain Consolidated Fee Schedule, Section 13.3 (revised 05/18/2021)
40% of the permit fee
State SurchargeEagle Mountain Consolidated Fee Schedule, Section 13.1; per Utah Code § 15A-1-209(5)
1% of the permit fee
Reinspection FeeEagle Mountain Consolidated Fee Schedule, Section 13.2 (revised 03/17/2015)
$50 per trade

Review timeline

Plan reviewEagle Mountain’s published plan-review target
14–14 business days

How long did your Residential Building Permit permit actually take in Eagle Mountain?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for occupancy — certificate of occupancy issued upon passing

See the full Eagle Mountain inspection guide — scheduling & re-inspection fees →

Tips

  • All inspections in Eagle Mountain must be scheduled via email to buildinginspections@eaglemountain.gov — walk-ins are not accepted. Power inspections must include the Rocky Mountain Power (RMP) work order number.
  • Cancel inspection requests before 9 AM to avoid being charged — cancellations received after 9 AM are processed on the next business day.
  • Eagle Mountain requires front and side yards to be landscaped before occupancy. In winter, a $2,000 escrow per lot can be paid, with landscaping completed within six months.
  • Eagle Mountain uses the OpenGov portal for permit applications (eaglemountainut.portal.opengov.com/categories/1076).
  • As of July 1, 2026 (now in force), the 2024 IBC, IPC, IMC, IFGC, and IECC govern statewide per Utah Code § 15A-2-103. Plans submitted for review before that date were reviewed under the 2021-edition codes in effect on the submission date.
  • No distinct EV charger/EVSE fee line item appears in Eagle Mountain's Consolidated Fee Schedule (eaglemountain.gov, rev. 12/03/2024, checked 2026-07-19) — a standalone charger circuit not tied to new construction would most likely fall under the 'Non-Valuation Based Permit – Inspection Only' fee ($50 per inspection).

Frequently asked questions

Eagle Mountain requires a residential building permit for: New single-family or multi-family residential construction; Additions to existing structures; Structural modifications — load-bearing wall removal, foundation alterations; Conversion of non-habitable space to habitable space. If your project isn't listed, confirm with Eagle Mountain City Building Department at (801) 789-6600 before starting work.

Eagle Mountain building permit fees are valuation-based per the Consolidated Fee Schedule (updated March 3, 2026, fees last revised 12/03/2024): $24 for projects valued at $500 or less, scaling to $14,935 plus $2 per each additional $1,000 over $5,000,000. Residential plan review adds 40% of the permit fee. A 1% Utah state surcharge applies to the permit fee. A reinspection fee of $50 per trade applies for failed inspections.

Eagle Mountain's typical plan review time for residential permits is approximately 14 business days. The city uses the OpenGov portal for permit applications.

You'll need: Building Permit Application; Building Plans; Residential Document Submittal Checklist; Energy Compliance Documentation. Depending on your project, Eagle Mountain may also ask for: Engineered Truss Plans; Compaction Certificate; Owner/Builder Certification Agreement. See the required-documents checklist on this page for details on each.

Eagle Mountain requires 4 inspection(s) for a residential building permit, in order: Foundation / Footing, Framing, Insulation, Final. Schedule each through Eagle Mountain City Building Department ((801) 789-6600).

Apply through Eagle Mountain City Building Department at 3726 E Campus Drive, Suites D & H, Eagle Mountain, Utah 84005. Phone: (801) 789-6600, email: buildinginspections@eaglemountain.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://eaglemountain.gov/government/building/.

Eagle Mountain, Utah has adopted: 2024 International Building Code (IBC) — governing edition per Utah Code § 15A-2-103(1)(a), effective 2026-07-01, superseded the 2021 edition (which was itself effective July 1, 2023). NOTE (2026-07-16, re-verified live): Eagle Mountain's own Building Department Compliance & Codes page (eaglemountain.gov/government/building/) still lists '2021 International Building Code (IBC)' and has not been updated to reflect the 2026-07-01 statewide transition.; 2021 International Residential Code (IRC) — Eagle Mountain Building Department, Compliance & Codes page; unaffected by the 7/1/2026 statute revision, continues in force per Utah Code § 15A-2-103(1)(b) — Eagle Mountain's page is current on this point; 2024 International Plumbing Code (IPC) — governing edition per Utah Code § 15A-2-103(1)(d), effective 2026-07-01, superseded the 2021 edition. NOTE (2026-07-16, re-verified live): Eagle Mountain's Compliance & Codes page still lists '2021 International Plumbing Code (IPC)' and has not been updated.; 2024 International Mechanical Code (IMC) — governing edition per Utah Code § 15A-2-103(1)(e), effective 2026-07-01, superseded the 2021 edition. NOTE (2026-07-16, re-verified live): Eagle Mountain's Compliance & Codes page still lists '2021 International Mechanical Code (IMC)' and has not been updated.; 2024 International Fuel Gas Code (IFGC) — governing edition per Utah Code § 15A-2-103(1)(f), effective 2026-07-01, superseded the 2021 edition. NOTE (2026-07-16, re-verified live): Eagle Mountain's Compliance & Codes page still lists '2021 International Fuel Gas Code (IFGC)' and has not been updated.; 2021 International Fire Code (IFC) — Eagle Mountain Building Department, Compliance & Codes page; 2024 International Energy Conservation Code (IECC) — governing edition per Utah Code § 15A-2-103(1)(h), effective 2026-07-01, superseded the 2021 edition. NOTE (2026-07-16, re-verified live): Eagle Mountain's Compliance & Codes page still lists '2021 International Energy Conservation Code (IECC)' and has not been updated.; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); unaffected by the 7/1/2026 statute revision, continues in force. NOTE: Eagle Mountain's building page lists 2020 NEC but the statewide-adopted edition is 2023 NEC per Utah Code § 15A-2-103 — the 2020 NEC listing on the city page is stale (re-confirmed live 2026-07-16, unrelated to and predating the 7/1/2026 transition); Eagle Mountain Municipal Code (local building and zoning regulations) — codepublishing.com/UT/EagleMountain/; NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, IECC replaced the 2021 editions per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16); IRC stays 2021; NEC stays 2023. Eagle Mountain's own Compliance & Codes page was checked live 2026-07-16 and still shows the pre-transition 2021 editions across the board — the statute governs regardless of the city page's lag..

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagle Mountain building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.