Orem building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Orem, Utah.
Verified 2026-07-16 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 56 North State St., 2nd Floor, Orem, UT 84057
- Phone
- (801) 229-7198
- help@orem.gov
- Office hours
- Monday–Friday, 8:00 AM–5:00 PM
- Website
- Official site
Published scheduling rules
- Schedule inspections through the Building Permit Portal at utah.cityinspect.com or by calling (801) 229-7198. (Residential Building Permit)
- Inspections must be scheduled at least one day in advance. (Residential Building Permit)
- The signal transmission test verifies monitoring through Metro Dispatch, (801) 854-6211 — schedule inspections through Orem's online inspections system (orem.gov/inspections-and-permits/). (Fire Alarm System Permit)
- Inspections must be scheduled in advance through the Building Permit Portal or by calling (801) 229-7198. (General)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footing / Foundation
Before concrete pour; verify setbacks, depth, reinforcement
- 2
Framing
After rough framing is complete, before insulation or drywall
- 3
Rough-in (Electrical / Plumbing / Mechanical)
After rough-in work is complete and accessible, before covering
- 4
Insulation
After insulation installed, before drywall
- 5
Final
All work complete; issues Certificate of Occupancy upon passing
Applies to: Basement Finish Permit
- 1
Framing
After framing is complete, before insulation or drywall
- 2
Rough-in (Electrical / Plumbing / Mechanical)
All rough-in work complete before walls are closed
- 3
Insulation
Insulation installed before drywall
- 4
Final
All finish work complete including drywall, fixtures, and egress windows
Applies to: Commercial Building Permit
- 1
Footing / Foundation
Before concrete pour; verify setbacks, depth, reinforcement.
- 2
Framing
After rough framing is complete, before insulation or drywall; includes MEP rough-in.
- 3
Insulation
After insulation installed, before drywall.
- 4
Final
All work complete; issues Certificate of Occupancy upon passing.
Applies to: Fire Alarm System Permit
- 1
24-Hour Battery Test
Battery backup test for the fire alarm system panel.
- 2
Notifier Activation, Flow Switch Test, Tamper Test, Smoke Detector Test
Device-level activation and function testing, per Orem Fire Prevention's Contractor's Corner guidance for new-construction alarm systems.
- 3
Address Verification and Signal Transmission Test
Confirms the monitored alarm signal reaches Metro Dispatch, (801) 854-6211.
- 4
Alarm Final
Performed in conjunction with the sprinkler final inspection where both systems are present — both the alarm and sprinkler contractors should be present, per Orem Fire Prevention's guidance.
Applies to: Fire Sprinkler System Permit
- 1
Riser Flush
A bacteria test does not fulfill this requirement, per Orem Fire Prevention's Contractor's Corner guidance for new-construction sprinkler systems.
- 2
Above Grade / Rough Hydrostatic Pressure Test
Verifies piping integrity above grade before concealment.
- 3
Flow Sensors and Tampers
Flow sensor and tamper switch verification.
- 4
Sprinkler Final
Performed in conjunction with the fire alarm final inspection — both the sprinkler and alarm contractors should be present, per Orem Fire Prevention's guidance.
Applies to: Swimming Pool / Hot Tub Permit
- 1
Pre-gunite / Pre-concrete
Steel reinforcement and bonding grid inspected before shell is poured
- 2
Rough-in Electrical / Plumbing
Bonding, conduit, and plumbing rough-in inspected
- 3
Barrier / Fence
Compliant barrier inspected before pool is filled
- 4
Final
Pool complete, all systems operational, barrier confirmed
Applies to: Deck / Patio Cover Permit
- 1
Footing
Holes dug, forms in place, before concrete pour
- 2
Framing / Ledger
Framing complete, ledger attachment inspected
- 3
Final
Decking, railings, and stairs complete
Applies to: Accessory Dwelling Unit (Accessory Apartment) Permit
- 1
Framing / Rough-in
Framing and all trade rough-in work inspected before walls are closed
- 2
Final
All work complete; unit ready for occupancy
Applies to: Change of Use / Change of Occupancy (Business License Application)
- 1
Building Department On-Site Inspection
Confirms zoning and building-code enforcement for the business location, per Orem's Business Licensing FAQ, which states a business license exists in part 'to make sure that zoning and building codes are enforced.'
- 2
Fire Inspection (Orem Fire Prevention Division)
Required for commercial businesses and applicable home occupations at initial licensing and annually thereafter, per Orem's Fire Inspection Requirements/Survey and the FIRE section's Annual Commercial Inspection Fees.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Rough-in (Electrical / Plumbing / Mechanical)
After rough-in work is complete and accessible, before covering.
- 2
Final
All finish work complete; issues Certificate of Occupancy upon passing.
Applies to: Demolition Permit
- 1
Pre-demolition Utility Disconnect
Verify all utilities are disconnected before demolition begins
- 2
Final Site
Site cleared and graded to safe condition
Applies to: Electrical Permit
- 1
Rough-in Electrical
Before walls are closed; inspect wiring, junction boxes, grounding
- 2
Final Electrical
All electrical work complete including fixtures, panels, and connections
Applies to: EV Charger / EVSE Permit
- 1
Rough-in Electrical
Before walls are closed (if applicable); inspect wiring, junction boxes, grounding for the EV charger circuit
- 2
Final Electrical
EV charger connection, panel work, and all electrical fixtures verified complete
Applies to: Mechanical / HVAC Permit
- 1
Rough-in Mechanical
Ductwork and equipment rough-in before walls are closed
- 2
Final Mechanical
Equipment operational, all connections and exhaust verified
Applies to: Plumbing Permit
- 1
Rough-in Plumbing
Before walls are closed; inspect drain, waste, vent, and water supply rough-in
- 2
Final Plumbing
All plumbing fixtures installed and connections complete
Applies to: Solar PV Permit
- 1
Rough-in Electrical
Conduit, wiring, and disconnects before enclosure
- 2
Final Building / Electrical
Modules installed, system operational, all connections verified
Final inspection only: Fence Permit, Roofing Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-16.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Orem building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.