Commercial Building Permit in Orem, Utah
Required for new commercial construction in Orem, regulated by the adopted 2024 IBC. Fees are assessed on the same Table 3A, 1997 UAC w/2023 revisions valuation table used for all Orem building permits (no separate commercial valuation table is published); distinct commercial-specific line items exist for Fast Track plan review and Temporary Certificate of Occupancy. All submittals are online only via the CityInspect portal.
Verified 2026-07-19 · Source
When you need this permit
- Online account at utah.cityinspect.com (register once at the direct registration link)
- New commercial construction, shell buildings, or structural alterations to commercial structures
- Electronic copy of plans and engineering, structural calculations
- Site plan showing property boundaries, existing structures, and proposed construction
- Energy compliance documentation (2024 IECC) for the building envelope and mechanical/lighting systems
- Construction valuation for fee assessment
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Orem City FY 2025-2026 Adopted Budget (orem.gov, pp. Show full citationHide
Orem City FY 2025-2026 Adopted Budget (orem.gov, pp. 204–206), Building Safety Permits: Table 3A governs 'Building Permit' fees generically by ICC Building Valuation Table valuation — no separate commercial valuation table is published; the same tier schedule applies regardless of occupancy type.Review timeline
Inspection process
- 1
Footing / Foundation
Before concrete pour; verify setbacks, depth, reinforcement.
- 2
Framing
After rough framing is complete, before insulation or drywall; includes MEP rough-in.
- 3
Insulation
After insulation installed, before drywall.
- 4
Final
All work complete; issues Certificate of Occupancy upon passing.
See the full Orem inspection guide — scheduling & re-inspection fees →
Tips
- Commercial projects valued under $5 million can opt into Fast Track plan review for $811 minimum (+$88/hr over 4 hours) instead of the standard Commercial & Residential 65%-of-permit-fee review.
- A Temporary Certificate of Occupancy for commercial space costs $390 (non-refundable) — this is a separate, higher fee than the residential TCO ($250, with $100 refundable if completed within 30 days).
- Orem's Table 3A valuation-based building permit fee applies identically to commercial and residential construction — there is no separate commercial fee table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Orem building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Orem.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Property Access
Orem's permit history is searchable by address
26,615 permits on record for Orem, 2002–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Orem
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →