Commercial Building Permit in Orem, Utah

Required for new commercial construction in Orem, regulated by the adopted 2024 IBC. Fees are assessed on the same Table 3A, 1997 UAC w/2023 revisions valuation table used for all Orem building permits (no separate commercial valuation table is published); distinct commercial-specific line items exist for Fast Track plan review and Temporary Certificate of Occupancy. All submittals are online only via the CityInspect portal.

Verified 2026-07-19 · Source

When you need this permit

  • Online account at utah.cityinspect.com (register once at the direct registration link)
  • New commercial construction, shell buildings, or structural alterations to commercial structures
  • Electronic copy of plans and engineering, structural calculations
  • Site plan showing property boundaries, existing structures, and proposed construction
  • Energy compliance documentation (2024 IECC) for the building envelope and mechanical/lighting systems
  • Construction valuation for fee assessment

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation-based (Table 3A, 1997 UAC w/2023 revisions)Orem City FY 2025-2026 Adopted Budget (orem.gov, pp. 204–206), Building Safety Permits: Table 3A governs 'Building Permit' fees generically by ICC Building Valuation Table valuation — no separate commercial valuation table is published; the same tier schedule applies regardless of occupancy type.
Same valuation-tier schedule as the standard building permit (see residential-building-permit permit type for the full tier breakdown; e.g. $1,065.00 + $7.00 per each $1,000 over $100,000 for the $100,001–$500,000 tier)
Plan Review — Commercial & ResidentialOrem City FY 2025-2026 Adopted Budget, Building Safety Plan Review (p. 205): 'Commercial & Residential — The lesser of 65% of the permit fee or the actual cost.'
Lesser of 65% of the permit fee or actual cost
Plan Review — Fast Track, Commercial (project value under $5M)Orem City FY 2025-2026 Adopted Budget, Building Safety Plan Review (p. 205). Fast Track is an optional expedited-review tier available only for commercial projects valued under $5 million.
$811.00 minimum + $88.00/hr if over 4 hours
Temporary Certificate of Occupancy — CommercialOrem City FY 2025-2026 Adopted Budget, Building Safety Permits (p. 205).
$390.00 (non-refundable)
Re-inspection (Required Inspection Call-back)Orem City FY 2025-2026 Adopted Budget, Building Safety Special Inspections (p. 206).
$125.00

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Orem?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing / Foundation

    Before concrete pour; verify setbacks, depth, reinforcement.

  2. 2

    Framing

    After rough framing is complete, before insulation or drywall; includes MEP rough-in.

  3. 3

    Insulation

    After insulation installed, before drywall.

  4. 4

    Final

    All work complete; issues Certificate of Occupancy upon passing.

See the full Orem inspection guide — scheduling & re-inspection fees →

Tips

  • Commercial projects valued under $5 million can opt into Fast Track plan review for $811 minimum (+$88/hr over 4 hours) instead of the standard Commercial & Residential 65%-of-permit-fee review.
  • A Temporary Certificate of Occupancy for commercial space costs $390 (non-refundable) — this is a separate, higher fee than the residential TCO ($250, with $100 refundable if completed within 30 days).
  • Orem's Table 3A valuation-based building permit fee applies identically to commercial and residential construction — there is no separate commercial fee table.

Frequently asked questions

Orem requires a commercial building permit for: Online account at utah.cityinspect.com (register once at the direct registration link); New commercial construction, shell buildings, or structural alterations to commercial structures; Electronic copy of plans and engineering, structural calculations; Site plan showing property boundaries, existing structures, and proposed construction; Energy compliance documentation (2024 IECC) for the building envelope and mechanical/lighting systems; Construction valuation for fee assessment. If your project isn't listed, confirm with Building Safety Division at (801) 229-7198 before starting work.

Orem assesses commercial building permit fees on the same Table 3A, 1997 Uniform Administrative Code (UAC) w/2023 revisions valuation table used for all building permits, based on ICC Building Valuation Table figures. Plan review is the lesser of 65% of the permit fee or actual cost — or you can opt into Fast Track review for $811.00 minimum plus $88.00/hr if over 4 hours, for projects valued under $5 million.

Orem does not publish a plan-review timeline for this permit. Contact Building Safety Division at (801) 229-7198 for current turnaround.

You'll need: Permit Application; Site Plan; Construction Drawings / Structural Engineering; Energy Compliance (COMcheck or equivalent). See the required-documents checklist on this page for details on each.

Orem requires 4 inspection(s) for a commercial building permit, in order: Footing / Foundation, Framing, Insulation, Final. Schedule each through Building Safety Division ((801) 229-7198).

Apply through Building Safety Division at 56 North State St., 2nd Floor, Orem, UT 84057. Phone: (801) 229-7198, email: help@orem.gov. Office hours: Monday–Friday, 8:00 AM–5:00 PM. Official information: https://orem.gov/buildingpermits/.

Orem, Utah has adopted: 2021 International Residential Code (IRC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b)); 2024 International Building Code (IBC), including Appendices C and J — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect July 1, 2025 – June 30, 2026 (Utah Code § 15A-2-103(1)(a)); 2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect July 1, 2025 – June 30, 2026 (Utah Code § 15A-2-103(1)(e)); 2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect July 1, 2025 – June 30, 2026 (Utah Code § 15A-2-103(1)(d)); 2021 International Fire Code (IFC) — effective July 1, 2025 (not adopted under Utah Code § 15A-2-103, which does not list an IFC edition; edition unconfirmed for the current period); 2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g)); 2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect July 1, 2025 – June 30, 2026 (Utah Code § 15A-2-103(1)(f)); 2024 International Energy Conservation Code (IECC) — currently in effect as of July 1, 2026, superseding the 2021 IECC that was in effect July 1, 2025 – June 30, 2026 (Utah Code § 15A-2-103(1)(h)); Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — currently in effect as of July 1, 2026, superseding the 2021 ISPSC that was in effect July 1, 2025 – June 30, 2026 (Utah Code § 15A-2-103(1)(n)); 2006 Uniform Wildlife Conservation Code (UWUIC); 2009 ANSI A117.1 Accessible and Usable Buildings and Facilities. Local amendments apply — see the Orem overview page for the full list.

Yes. Orem's Fast Track Commercial review option, for projects valued under $5 million, costs $811.00 minimum plus $88.00/hr if the review takes over 4 hours, per the Orem City FY 2025-2026 Adopted Budget.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Orem building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Orem.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.