Fire Alarm System Permit in Orem, Utah
Required for installation of a new fire alarm system, or modification/extension of an existing system, for new construction or a tenant improvement in Orem. As with fire sprinkler systems, plan review, permits, and inspections are handled directly by Orem's own Fire Prevention Division (which also serves as the contracted fire-prevention plan-review and inspection authority for Lindon and Vineyard) — the fees and process below are Orem's own. Fire-alarm review/inspection is separate from, but coordinated with, the Building Safety Division's building-permit plan review for the same project. Fees are assessed by project square footage under the FIRE section of Orem's FY 2025-2026 Adopted Budget Fee Schedule and bundle office plan review, the 24-hour test, and the final inspection; a mandatory third-party code compliance review applies to any project with 5 or more alarm devices.
Verified 2026-07-22 · Source
When you need this permit
- New fire alarm system installation, or modification/extension of coverage to additional floors, for new construction or a tenant improvement in a building located in Orem
- Fire alarm system plans submitted directly to the Orem Fire Prevention Division (fireprevention@orem.gov) for plan review — separate from, but coordinated with, the Building Safety Division's building-permit plan review
- Third-party code compliance review is required for any new-construction or tenant-improvement alarm project involving 5 or more devices, per Orem's own Contractor's Corner guidance (orem.gov/contractors-corner/)
- For a tenant improvement to a building with an existing fire alarm system, any modification to the existing floor plan requires updated coverage plans submitted to Orem Fire Prevention before work begins
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
24-Hour Battery Test
Battery backup test for the fire alarm system panel.
- 2
Notifier Activation, Flow Switch Test, Tamper Test, Smoke Detector Test
Device-level activation and function testing, per Orem Fire Prevention's Contractor's Corner guidance for new-construction alarm systems.
- 3
Address Verification and Signal Transmission Test
Confirms the monitored alarm signal reaches Metro Dispatch, (801) 854-6211.
- 4
Alarm Final
Performed in conjunction with the sprinkler final inspection where both systems are present — both the alarm and sprinkler contractors should be present, per Orem Fire Prevention's guidance.
See the full Orem inspection guide — scheduling & re-inspection fees →
Tips
- Fire alarm plans go directly to the Orem Fire Prevention Division (fireprevention@orem.gov) — this is separate from, but coordinated with, the Building Safety Division's CityInspect plan review for the same project.
- Projects with 5 or more alarm devices require third-party code compliance review in addition to the Fire Prevention Division's own plan review.
- The signal transmission test verifies monitoring through Metro Dispatch, (801) 854-6211 — schedule inspections through Orem's online inspections system (orem.gov/inspections-and-permits/).
- The Orem Fire Prevention Division also serves as the contracted fire-prevention plan-review and inspection authority for Lindon and Vineyard — the fee schedule and process in this entry are Orem's own, not a cross-jurisdiction reference.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Orem building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Orem
Fire Alarm System Permit in other cities
Compare fire alarm system permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Orem project checklist
Describe your project once and get every permit, document, and fee it triggers in Orem — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →