Pleasant Grove building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Pleasant Grove, Utah.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 70 S 100 East, Pleasant Grove, UT 84062
- Phone
- 801-785-5045
- Office hours
- Mon–Thu 7:30 AM – 5:30 PM; Fri 8:00 AM – 12:00 PM, per pgcityutah.gov/departments/community_development/building.php. Fax: 801-785-8925 (published on the same page as a fax number, not an email address — no department email address is published on the Building Division page).
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Single Family)
- 1
Foundation / Footing
Before concrete pour, per standard IRC inspection sequence enforced by Pleasant Grove Building Division.
- 2
Framing
After framing, sheathing, and roof installed; includes MEP rough-in.
- 3
Insulation
After insulation installed, before drywall.
- 4
Final
All work complete before occupancy.
Applies to: New Commercial Shell Building Permit, Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour, per standard IBC inspection sequence.
- 2
Framing
After framing, sheathing, and roof installed.
- 3
Final
All work complete before occupancy.
Applies to: Certificate of Occupancy and Zoning Compliance
- 1
Fire Self-Inspection (with photos) / Battalion Chief Review
Required for both home and commercial business license applicants. The Battalion Chief reviews the self-inspection form and may order an on-site inspection; fire inspections must be completed before the license -- and lawful occupancy -- can be granted. Contact: 385-248-0070.
- 2
Zoning/Building Compliance Verification
Community Development confirms the location is properly zoned for the proposed use and that the building meets applicable code, per the Business License Application Requirements PDF's stated licensing rationale.
Applies to: Commercial Remodel / Tenant Improvement Permit, Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural
Wall sections and rebar verified per submitted plans before close-in.
- 2
Final
All work complete before occupancy.
Applies to: Solar / Basement Finish / Addition / Pool / Plan Revision Permit
- 1
Rough-In
Electrical/plumbing/structural rough-in as applicable to scope (solar electrical, basement MEP, pool bonding, etc.).
- 2
Final
Completed work verified before closeout.
Final inspection only: EV Charger / EVSE Permit, Fire Sprinkler & Fire Alarm Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant Grove building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Pleasant Grove building permits
Get alerts for Pleasant Grove
We'll email you when Pleasant Grove's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.