Fire Sprinkler & Fire Alarm Permit in Pleasant Grove, Utah
Pleasant Grove Fire Department, led by City Fire Marshal Battalion Chief Jake Larsen, enforces the fire code and reviews fire protection system plans for new construction. The city does not perform fire sprinkler and alarm plan review in house: submit plans to one of the city's approved third-party fire engineering reviewers for review and stamping, then route them to the Fire Marshal's office for final approval. Budget the third-party review fee and its lead time separately.
Verified 2026-07-20 · Source
When you need this permit
- Fire sprinkler system plans for new commercial construction
- Fire alarm system plans for new commercial construction
- Underground fire protection piping
- Fire pump installation
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Fire Department Acceptance Testing
Per the Fire Inspections FAQ: "All acceptance testing per the International Fire Code to include underground piping, fire sprinkler systems, fire alarm systems, fire pumps etc." must be witnessed by the Fire Department.
See the full Pleasant Grove inspection guide — scheduling & re-inspection fees →
Tips
- Fire sprinkler and alarm plans for Pleasant Grove are NOT reviewed in-house by the city — submit them to one of the city's approved 3rd-party fire engineering reviewers (e.g., PCI/Protection Consultants Inc., Superior Fire Protection Services, Resolut Group, Craig Blue PE Inc., or West Coast Code Consultants), then contact the Fire Marshal's office for final approval once the third party has stamped the plans.
- Fire Department inspections themselves carry no city fee, but the third-party plan review fee is separate and set by the private reviewing firm.
- Contact Battalion Chief Jake Larsen (City Fire Marshal) at 385-248-0073 for construction inspections and fire prevention questions; requests should be made 24-48 hours in advance, Monday through Thursday.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant Grove building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Pleasant Grove's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Pleasant Grove yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Pleasant Grove lands. Privacy.
Other permits in Pleasant Grove
Fire Sprinkler & Fire Alarm Permit in other cities
Compare fire sprinkler & fire alarm permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Pleasant Grove project checklist
Describe your project once and get every permit, document, and fee it triggers in Pleasant Grove — in one checklist. Free, for any city and any number of projects.
Get started →