EV Charger / EVSE Permit in Pleasant Grove, Utah

Pleasant Grove has no distinct EV charger/EVSE permit type, fee line item, or dedicated Electrical Permit category — the city's published Building Permit Submittal Fees table (pgcityutah.gov/departments/community_development/fee_schedule.php) groups all construction not otherwise itemized (new single-family, new commercial, commercial remodel/TI) into an 'All Others (Solar, Signs, Basements)' / 'Solar, Basements, Additions, Pools, Plan Revisions' flat $75 submittal-fee category, the same catch-all bucket this dataset already uses for Pleasant Grove's solar-basement-addition-pool-remodel-permit entry. No source found explicitly names EV chargers as belonging to that bucket, so this entry is marked partial confidence rather than assuming the analogy holds.

Reviewed 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Pleasant Grove
  • New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g))
  • Site Plan (per pgcityutah.gov Building Division document list for 'Most Other Types of Construction')
  • Contractor license number or Owner-Builder Certification Form Owner-builderContractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Submittal Fee (Plan Check Fee) — likely 'All Others' catch-all category (unconfirmed for EV specifically)pgcityutah.gov/departments/community_development/fee_schedule.php (fetched 2026-07-20): 'All Others (Solar, Signs, Basements) — $75' and a related listing 'Solar, Basements, Additions, Pools, Plan Revisions — $75.' Neither version of this catch-all category explicitly names EV chargers or electrical work; this figure is included as the most plausible applicable bucket given Pleasant Grove publishes no dedicated Electrical Permit fee, but it is NOT independently confirmed for EV-specific work — confirm with the Community Development Department (801-785-5045) before relying on it.
$75.00 (by analogy to the 'All Others' / 'Solar, Basements, Additions, Pools, Plan Revisions' catch-all bucket)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Pleasant Grove?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Final Electrical

    Electrical rough-in and final inspection of the new EV charger circuit, administered by Pleasant Grove's Building Division.

See the full Pleasant Grove inspection guide — scheduling & re-inspection fees →

Tips

  • Pleasant Grove does not publish a dedicated Electrical Permit fee category or an EV-charger-specific fee line item — the closest published bucket is the $75 'All Others (Solar, Signs, Basements)' / 'Solar, Basements, Additions, Pools, Plan Revisions' submittal fee, but no source explicitly confirms EV chargers belong to it.
  • Confirm the applicable fee category directly with the Community Development Department (801-785-5045) before applying, since EV chargers are not explicitly named in any published Pleasant Grove fee category.
  • All electrical work in Pleasant Grove, including EV charger circuits, must comply with the 2023 NEC as adopted statewide by Utah Code § 15A-2-103(1)(g); Pleasant Grove's own Building Division page still listed a 2020 NEC adoption as of a 2026-07-16 re-check.

Frequently asked questions

Pleasant Grove requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Pleasant Grove; New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g)); Site Plan (per pgcityutah.gov Building Division document list for 'Most Other Types of Construction'); Contractor license number or Owner-Builder Certification Form. If your project isn't listed, confirm with Pleasant Grove City Building Division (Community Development Department) at 801-785-5045 before starting work.

Pleasant Grove does not publish a distinct EV-charger permit type or fee. The city's Building Permit Submittal Fees table has no dedicated Electrical Permit category either — the closest published bucket is the $75 flat 'All Others' submittal fee used for solar, basements, additions, pools, and plan revisions, but no source explicitly confirms EV chargers are billed under it. Confirm with the Community Development Department (801-785-5045).

Pleasant Grove does not publish a plan-review timeline for this permit. Contact Pleasant Grove City Building Division (Community Development Department) at 801-785-5045 for current turnaround.

You'll need: Building Permit Application; Contractor License Number or Owner-Builder Certification Form. See the required-documents checklist on this page for details on each.

Pleasant Grove requires 1 inspection(s) for an ev charger / evse permit, in order: Rough-In / Final Electrical. Schedule each through Pleasant Grove City Building Division (Community Development Department) (801-785-5045).

Apply through Pleasant Grove City Building Division (Community Development Department) at 70 S 100 East, Pleasant Grove, UT 84062. Phone: 801-785-5045. Office hours: Mon–Thu 7:30 AM – 5:30 PM; Fri 8:00 AM – 12:00 PM, per pgcityutah.gov/departments/community_development/building.php. Fax: 801-785-8925 (published on the same page as a fax number, not an email address — no department email address is published on the Building Division page).. Official information: https://www.pgcityutah.gov/departments/community_development/building.php.

Pleasant Grove, Utah has adopted: GOVERNING LAW: Utah Code § 15A-2-103 (le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), version effective 7/1/2026 (amended by Ch. 47, 2026 General Session), sets the statewide-mandatory construction code suite (Utah Code § 15A-1-204 — binds every municipality; local amendments permitted, a different edition is not). Pleasant Grove's own Building Division page (pgcityutah.gov/departments/community_development/building.php) still displays the pre-7/1/2026 edition list; re-checked live 2026-07-16, page text is byte-identical to the 2026-07-04 fetch. State law governs regardless of the page's lag; each line below states current law first, then the page's as-published (stale) text.; 2024 International Building Code (IBC), including Appendices C and J — per Utah Code § 15A-2-103(1)(a), effective 7/1/2026. Pleasant Grove's Building Division page still lists '2021 International Building Code (IBC)' (live re-check 2026-07-16).; 2021 International Residential Code (IRC) with Utah State Amendments, plus Appendix AQ of the 2021 IRC — per Utah Code § 15A-2-103(1)(b)/(c); this edition did NOT change in the 7/1/2026 flip. Matches Pleasant Grove's own page, which lists '2021 International Residential Code w/ Utah State Amendments (IRC)' (live re-check 2026-07-16).; 2024 International Mechanical Code (IMC) — per Utah Code § 15A-2-103(1)(e), effective 7/1/2026. Pleasant Grove's Building Division page still lists '2021 International Mechanical Code (IMC)' (live re-check 2026-07-16).; 2024 International Plumbing Code (IPC) — per Utah Code § 15A-2-103(1)(d), effective 7/1/2026. Pleasant Grove's Building Division page still lists '2021 International Plumbing Code (IPC)' (live re-check 2026-07-16).; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g); this edition did NOT change in the 7/1/2026 flip and has been state law since before this project's original 2026-07-04 review. Pleasant Grove's own Building Division page still lists '2020 National Electrical Code (NEC)' (live re-check 2026-07-16) — a PRE-EXISTING discrepancy that predates and is unrelated to the 2026-07-01 code-cycle flip, of the same kind separately documented for American Fork's Solar checklist and Provo's Building FAQ. Reported here as-published rather than corrected, per grounded-data policy of not inventing a fact the city's own source does not state.; 2024 International Energy Conservation Code (IECC), one statewide edition (no residential/commercial split) — per Utah Code § 15A-2-103(1)(h), effective 7/1/2026. Pleasant Grove's Building Division page still lists '2021 International Energy Conservation Code w/ Utah State Amendments (IECC)' (live re-check 2026-07-16).; 2024 International Fuel Gas Code (IFGC) — per Utah Code § 15A-2-103(1)(f), effective 7/1/2026. Pleasant Grove's Building Division page still lists '2021 International Fuel Gas Code (IFGC)' (live re-check 2026-07-16).; 2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective 7/1/2026. Pleasant Grove's Building Division page still lists '2021 International Existing Building Code (IEBC)' (live re-check 2026-07-16).; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective 7/1/2026. Pleasant Grove's Building Division page lists '2021 International Swimming Pool and Spa Code (ISPSC)' without qualifying it to residential provisions (live re-check 2026-07-16).; Modular Building Institute (MBI) Standards 1200 and 1205 — per Utah Code § 15A-2-103(1)(o), statewide-mandated for modular units. Not mentioned anywhere on Pleasant Grove's Building Division page as of live re-check 2026-07-16; added here as a statute-sourced omission (applies statewide regardless of city publication), not fabricated.; No International Fire Code (IFC) entry: § 15A-2-103 does not adopt the IFC — the IFC is separately governed under Title 15A Chapter 5, outside the scope of this section. Pleasant Grove's Building Division page does not list an IFC edition either, so there is no mis-citation to correct here.. Local amendments apply — see the Pleasant Grove overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant Grove building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.