Commercial Building Permit — Pleasant Grove, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://www.pgcityutah.gov/departments/community_development/fee_schedule.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Pleasant Grove, Utah
Required for new commercial construction in Pleasant Grove, regulated by the state-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 7/1/2026). This entry is the counterpart of Pleasant Grove's 'New Commercial Shell Building Permit' entry (slug new-commercial-shell-permit) — the same real permit, with the same $500 submittal fee and the same underlying sourcing — listed under the standard commercial-building-permit name so lookups by that name resolve to real Pleasant Grove data. Source URLs are the same pgcityutah.gov pages cited there.
Verified 2026-07-19 · Source
When you need this permit
- New commercial shell construction
- Electronic copy of plans and engineering
- Site plan to scale
- Structural engineering plan review
- Gas line layout with pipe sizes called out
- Heat loss analysis
- SWPPP (Storm Water Pollution Prevention Plan)
- Contractor license number or Owner-Builder Certification Form Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
pgcityutah.gov/departments/community_development/fee_schedule.php and building.php: 'New Commercial — $500.' Applied toward the total cost of the building permit. Show full citationHide
pgcityutah.gov/departments/community_development/fee_schedule.php and building.php: 'New Commercial — $500.' Applied toward the total cost of the building permit. The fee_schedule.php table lists 'New Commercial $500' alongside 'New Single Family $250,' 'Commercial Remodel/Tenant Improvement $250,' and 'All Others (Solar, Signs, Basements) $75'.Review timeline
Inspection process
- 1
Foundation / Footing
Before concrete pour, per standard IBC inspection sequence.
- 2
Framing
After framing, sheathing, and roof installed.
- 3
Final
All work complete before occupancy.
See the full Pleasant Grove inspection guide — scheduling & re-inspection fees →
Tips
- This is the same permit as Pleasant Grove's 'New Commercial Shell Building Permit', carrying the same $500 submittal fee, listed here under the commercial building permit name as well.
- The $500 submittal fee applies specifically to new commercial construction; Commercial Remodel/Tenant Improvement is billed separately at $250 (see the commercial-tenant-improvement-permit entry).
- No published commercial-specific plan-review turnaround time exists; the 14-business-day figure on the city's page applies only to single-family residential per Utah Code § 10-6-160.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant Grove building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Pleasant Grove.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Pleasant Grove's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Pleasant Grove yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Pleasant Grove lands. Privacy.
Other permits in Pleasant Grove
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →