Springville building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Springville, Utah.
Verified 2026-07-04 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 110 South Main Street, Springville, UT 84663 (Attn: Building Dept. for permit payments)
- Phone
- (801) 489-2704
- Office hours
- Building and Inspections Department: Monday–Friday, 8:00 a.m. to 5:00 p.m., closed all major holidays, per Springville Residential Building Permit Checklist (July 2023). NOTE: Springville's Building FAQ separately states building-division phone coverage (staffer 'Hollie') runs 8:00 a.m.–1:00 p.m. mornings only — the 8 AM–5 PM window is the department's official posted hours per the Permit Checklist, phone/counter availability may be more limited.
- Website
- Official site
Published scheduling rules
- No inspections are conducted on Mondays because of a required 24-hour battery test cycle, and Friday inspections are by request only — plan scheduling accordingly and request an inspection at least two business days ahead. (Fire Sprinkler, Alarm, and Hood Plan Review Permit)
- Inspections must be requested at least two days before the intended inspection date, by phone or email to the Fire Marshal (Fire Sprinkler, Alarm, and Hood Plan Review Permit)
Inspection sequence
Applies to: Residential Building Permit
- 1
Footings
Before concrete pour.
- 2
Foundation
Forms, rebar, anchor bolts verified.
- 3
Temporary Power / Power Trench
Temporary power and power trench inspections per Springville Residential Building Permit Checklist.
- 4
Underground Plumbing / Sewer Lateral
Underground plumbing and sewer lateral inspections; sewer lateral inspections require water testing.
- 5
Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical)
Combined rough-in inspection of framing, electrical, plumbing, and mechanical systems, plus gas line.
- 6
Insulation
After insulation installed, before drywall.
- 7
Drywall, Flashing, Lath
Drywall, flashing, and lath inspections per Springville Residential Building Permit Checklist.
- 8
Permanent Power / Drive Approach
Permanent power connection and drive approach inspections.
- 9
Final
Final inspection for certificate of occupancy.
Applies to: Commercial Building Permit
- 1
Footings
Before concrete pour, if needed.
- 2
Underground Plumbing
Underground plumbing rough-in inspection.
- 3
Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical)
Combined rough-in inspection of framing, electrical, plumbing, and mechanical systems.
- 4
Insulation
After insulation installed, before drywall.
- 5
Drywall / T-Grid
Drywall and T-bar grid ceiling inspections.
- 6
Power
Permanent power connection inspection.
- 7
Final
All work complete before occupancy; the Fire Department may also require periodic inspections and approval at final.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Underground Plumbing
If applicable to the tenant space.
- 2
Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical)
Combined rough-in inspection.
- 3
Insulation
If applicable.
- 4
Drywall / T-Grid
Drywall and T-bar grid ceiling inspections.
- 5
Power
Permanent power connection inspection.
- 6
Final
All finish work complete; the Fire Department may also require periodic inspections and approval at final.
Applies to: Residential Addition / Remodel Permit (includes Basement Finish)
- 1
Footings (if needed)
Required only if new footings are part of the scope.
- 2
Underground Plumbing
Before concrete pour, if applicable.
- 3
Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical)
Combined rough-in inspection, plus gas line.
- 4
Insulation
After insulation installed, before drywall.
- 5
Drywall
Before finishes applied.
- 6
Final
All work complete.
Applies to: Plumbing Permit
- 1
Underground / Sewer Lateral
Requires water testing per Springville Residential Building Permit Checklist.
- 2
Rough Plumbing
Part of the four-way rough-in inspection.
- 3
Final
Fixtures connected, no leaks.
Applies to: Solar Panel (PV) Permit
- 1
Rough Electrical / Interconnection
Conduit runs, wire sizing, and disconnect placement verified before energizing, per the general four-way rough-in inspection process.
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified.
- 3
Production Meter Installation (Springville Power)
Springville Power Standards require a dedicated production meter to be installed as part of the Customer-Owned Generation Agreement, scheduled separately with Springville City Power (801-489-2750) after the building permit's electrical inspections are complete.
Applies to: Electrical Permit
- 1
Rough Electrical
Part of the four-way rough-in inspection (framing, rough electrical, rough plumbing, mechanical) per Springville Residential Building Permit Checklist.
- 2
Permanent Power
Final electrical connection inspection before permanent power is released.
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
Part of the four-way rough-in inspection (framing, rough electrical, rough plumbing, mechanical) if tied to new construction, or a standalone rough inspection for a retrofit EVSE circuit.
- 2
Permanent Power / Final
Final electrical connection inspection before the charger is energized.
Applies to: Fire Sprinkler, Alarm, and Hood Plan Review Permit
- 1
Fire Marshal Plan Review
Springville City Fire Marshal reviews submitted fire alarm, fire sprinkler, and/or hood extinguishing system plans; construction permits are issued upon approval, per the Fire and Rescue department's Fire Sprinkler, Alarm and Hood Plan Inspections page.
- 2
Field Inspection
Scheduled by contacting the Fire Marshal at least two days in advance. Not conducted on Mondays (to allow a required 24-hour battery test); Friday inspections are by request only.
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Part of the four-way rough-in inspection (framing, rough electrical, rough plumbing, mechanical), plus gas line inspection.
- 2
Final
Equipment operational, gas line tested.
Final inspection only: Roofing Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Springville building permits
Get alerts for Springville
We'll email you when Springville's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.