Skip to main content
PermitBase

Commercial Building Permit in Springville, Utah

Required for new commercial construction in Springville. Permits cannot be accepted unless the site has Development Review Committee (DRC) review and approval and all outside fees (irrigation company, SWPPP, etc.) have been paid. A preconstruction meeting is required for all multi-family and commercial projects before construction starts. Per Springville's own Building FAQ, initial commercial plan review takes 21 business days.

Verified 2026-08-16 · Source

When you need this permit

  • Site has DRC (Development Review Committee) review and approval before the building permit can be accepted
  • All outside fees (irrigation company fees, SWPPP fees, etc.) paid before permit submission
  • Completed Building Permit application
  • Plan check fee due in FULL at time of permit submission
  • Water shares tendered, if not previously done with the development
  • Preconstruction meeting required for all multi-family and commercial projects prior to construction start

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 9 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Plan Check Fee
Springville Commercial Building Permit Checklist (2026 edition, rendered page image, 2026-08-16): 'Plan check fee is due in FULL at time of permit submission. Show full citationSpringville Commercial Building Permit Checklist (2026 edition, rendered page image, 2026-08-16): 'Plan check fee is due in FULL at time of permit submission. Contact office staff for amount.' Confirmed unchanged in the Springville City FY 2026 Comprehensive Fee Schedule, Exhibit B, Building Fees, line 410 ('Assessed by Plans Examiner', Resolution No. 97-13). No commercial-specific valuation table is published. Current published edition as of 2026-08-16: the FY 2026 Comprehensive Fee Schedule (Exhibit B to the FY 2025-2026 Final Budget, uploaded 2025-09-25). A newer Fiscal 2026-2027 Comprehensive Fee Schedule exists as Exhibit B to the Springville City FY 2026-2027 INTERIM Budget (published July 2026), whose adopting resolution carries PART VI: 'Authorized fees and charges... during the 2026-2027 fiscal year shall be as shown on the Comprehensive Fee Schedule included in the Tentative Budget document as Exhibit B.' That FY2027 schedule is laid out in two columns — an 'Approved Fee' column and a highlighted 'FY 2027 Proposed Fee' column — and its Approved Fee column reproduces the FY2026 figures exactly. A Truth in Taxation hearing is set for 18 August 2026, with final budget adoption to follow; the resolution number is left blank in the published PDF.
Due in FULL at time of permit submission — contact office staff for the exact amount; no fixed published dollar figure.
Building Permit Fee
Springville City FY 2026 Comprehensive Fee Schedule, Exhibit B, Building Fees, line 411: 'Building Permit Fee — Assessed by Plans Examiner (Resolution No. Show full citationSpringville City FY 2026 Comprehensive Fee Schedule, Exhibit B, Building Fees, line 411: 'Building Permit Fee — Assessed by Plans Examiner (Resolution No. 2007-06)' on 2026-08-16; unchanged from the FY2025 edition (line 410). Current published edition as of 2026-08-16: the FY 2026 Comprehensive Fee Schedule (Exhibit B to the FY 2025-2026 Final Budget, uploaded 2025-09-25). A newer Fiscal 2026-2027 Comprehensive Fee Schedule exists as Exhibit B to the Springville City FY 2026-2027 INTERIM Budget (published July 2026), whose adopting resolution carries PART VI: 'Authorized fees and charges... during the 2026-2027 fiscal year shall be as shown on the Comprehensive Fee Schedule included in the Tentative Budget document as Exhibit B.' That FY2027 schedule is laid out in two columns — an 'Approved Fee' column and a highlighted 'FY 2027 Proposed Fee' column — and its Approved Fee column reproduces the FY2026 figures exactly. A Truth in Taxation hearing is set for 18 August 2026, with final budget adoption to follow; the resolution number is left blank in the published PDF.
Assessed by Plans Examiner — no fixed valuation table published.

Review timeline

Plan reviewSpringville’s published plan-review target
Up to 21 business days

How long did your Commercial Building Permit permit actually take in Springville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footings

    Before concrete pour, if needed.

  2. 2

    Underground Plumbing

    Underground plumbing rough-in inspection.

  3. 3

    Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical)

    Combined rough-in inspection of framing, electrical, plumbing, and mechanical systems.

  4. 4

    Insulation

    After insulation installed, before drywall.

  5. 5

    Drywall / T-Grid

    Drywall and T-bar grid ceiling inspections.

  6. 6

    Power

    Permanent power connection inspection.

  7. 7

    Final

    All work complete before occupancy; the Fire Department may also require periodic inspections and approval at final.

See the full Springville inspection guide — scheduling & re-inspection fees →

Tips

  • Permits cannot be accepted for a commercial project until the site has DRC (Development Review Committee) review and approval and all outside fees (irrigation company, SWPPP, etc.) are paid.
  • A preconstruction meeting is required for all multi-family and commercial projects before construction can start.
  • Initial commercial plan review takes 21 business days per Springville's own Building FAQ — longer than the 14-business-day residential figure.
  • Springville's own fee schedule does not publish a valuation table for the Building Permit Fee or Plan Check Fee for commercial projects, same as residential — both are 'Assessed by Plans Examiner.'

Frequently asked questions

Springville requires a commercial building permit for: Site has DRC (Development Review Committee) review and approval before the building permit can be accepted; All outside fees (irrigation company fees, SWPPP fees, etc.) paid before permit submission; Completed Building Permit application; Plan check fee due in FULL at time of permit submission; Water shares tendered, if not previously done with the development; Preconstruction meeting required for all multi-family and commercial projects prior to construction start. If your project isn't listed, confirm with Springville City Community Development — Building Division at (801) 489-2704 before starting work.

In Springville, the published Plan Check Fee is: Due in FULL at time of permit submission — contact office staff for the exact amount; no fixed published dollar figure.. Additional published fees: Building Permit Fee — Assessed by Plans Examiner — no fixed valuation table published.. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per Springville's Building FAQ, the initial plan review for a commercial application takes place within 21 business days. If corrections are needed, the reviewer usually re-checks resubmittals within 3 business days of your response.

You'll need: Plat or Site Plan (DRC-Approved); Cover Sheet (Code Analysis); Structural Design / Architectural Drawings; Electrical / Mechanical / Plumbing Plans; Heating/Cooling Load Calculations and ComCheck/ASHRAE 90.1 Compliance; Egress Components with Load Calculations; ADA Compliance (2009 ANSI A117.1); Geotechnical Report; Construction Valuation. Depending on your project, Springville may also ask for: Truss Engineering and Layout; Fire Protection Systems / Fire-Resistive Construction. See the required-documents checklist on this page for details on each.

Springville requires 7 inspection(s) for a commercial building permit, in order: Footings, Underground Plumbing, Four-Way (Framing, Rough Electrical, Rough Plumbing, Mechanical), Insulation, Drywall / T-Grid, Power, Final. Schedule each through Springville City Community Development — Building Division ((801) 489-2704).

Apply through Springville City Community Development — Building Division at 110 South Main Street, Springville, UT 84663 (Attn: Building Dept. for permit payments). Phone: (801) 489-2704, email: buildingpermits@springvilleutah.gov. Office hours: Building and Inspections Department: Monday–Friday, 8:00 a.m. to 5:00 p.m., closed all major holidays, per Springville Residential Building Permit Checklist (July 2023). NOTE: Springville's Building FAQ separately states building-division phone coverage (staffer 'Hollie') runs 8:00 a.m.–1:00 p.m. mornings only — the 8 AM–5 PM window is the department's official posted hours per the Permit Checklist, phone/counter availability may be more limited.. Official information: https://www.springvilleutah.gov/community-development/building-division/.

Springville, Utah has adopted: 2024 International Building Code (IBC) — Springville City Code § 10-1-101 adopts 'the International Building Code and the International Residential Code, as published by the International Code Council and adopted by the State of Utah, including all State statutes, amendments and regulations' as the City Building Code; the statewide edition CURRENT as of 7/1/2026 is the 2024 IBC per Utah Code § 15A-2-103(1)(a) (confirmed by direct fetch of the live statute 2026-07-16). The 2021 IBC governed through 6/30/2026. Springville § 10-1-101 last amended by Ordinance 16-2025 (effective 7/15/2025).; 2021 International Residential Code (IRC) — per Springville City Code § 10-1-101 (defers to state-adopted edition) and stated on Springville's own Residential Building Permit Checklist (July 2023) and Basement Improvement Permit Checklist (July 2023): 'Building shall be designed to the 2021 IRC (International Residential Code)' [and, for basements, 'and State Amendments']. Unchanged by the 7/1/2026 code cycle per Utah Code § 15A-2-103(1)(b).; 2024 International Plumbing Code (IPC), International Mechanical Code (IMC), International Fuel Gas Code (IFGC), and International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC) — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(d)/(e)/(f)/(h)/(i) respectively, incorporated by reference via Springville City Code § 10-1-101's adoption of state-amended construction codes (confirmed by direct fetch of the live statute 2026-07-16). The 2021 editions of these five codes governed through 6/30/2026. The IECC is a single statewide edition — the statute contains no residential/commercial split. No Springville-specific edition citation for these individual codes was found beyond the statewide statute and Chapter 10-7 (Building and Construction Standards and Codes) cross-reference. The International Fire Code (IFC) is not adopted anywhere in Utah Code § 15A-2-103 and no Springville-specific IFC citation was found either.; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g), the statewide-mandated edition that supersedes any locally-referenced older edition; UNCHANGED by the 7/1/2026 code cycle. NOTE: Springville's own 'Solar Permit Process' document (springvilleutah.gov, dated 2019) states 'System shall be designed to the 2015 IRC and 2017 NEC' — this document remains STALE relative to the current statewide statute; the 2023 NEC and 2021 IRC (both continuing unchanged past 7/1/2026) govern, per Utah Code § 15A-2-103, which supersedes outdated city documents.; The 2021 editions of IBC/IPC/IMC/IFGC/IECC/IEBC were superseded at the 7/1/2026 statewide transition; the entries above state the 2024 editions as current, with the superseded 2021 editions preserved as historical context. The IRC (2021) and NEC (2023) editions were not affected by that transition. No Springville-specific city page (beyond the 2019-dated, stale Solar Permit Process document) independently states individual code editions for IBC/IPC/IMC/IFGC/IECC/IEBC.. Local amendments apply — see the Springville overview page for the full list.

The project site must have Development Review Committee (DRC) review and approval, and all outside fees (irrigation company fees, SWPPP fees, etc.) must be paid, before a commercial building permit will be accepted. A preconstruction meeting is also required for all multi-family and commercial projects before construction starts.

Sources & verification

Verified against official sources. Last reviewed 2026-08-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Springville.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.

Springville's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Springville yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Springville lands. Privacy.