Plumbing Permit in Springville, Utah

Required for plumbing installations, alterations, and repairs in Springville. Plumbing permits must be applied for and paid separately from the building permit — not bundled, unlike Provo's ≤4-unit model.

Verified 2026-07-04 · Source

When you need this permit

  • New plumbing fixture installations, water heater replacement, water/sewer line work
  • Plumbing Permits need to be applied and paid for separately by each Subcontractor
  • Underground plumbing and sewer lateral inspections require water testing per Springville Residential Building Permit Checklist

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plumbing Permit FeeSpringville FY2025 Comprehensive Fee Schedule (Exhibit B, Building Fees, lines 395-414) lists no separate 'Plumbing Permit' line item — only 'Building Permit Fee' and 'Plan Check Fee,' both 'Assessed by Plans Examiner.' Confirmed via ordinance-summary source that plumbing permits are charged separately from the building permit; no specific rate was located, so none is asserted.
No fixed dollar figure published for a standalone plumbing permit was found in Springville's Building Fees fee-schedule section.

Review timeline

Plan review
Not published — contact the department

How long did your Plumbing Permit permit actually take in Springville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground / Sewer Lateral

    Requires water testing per Springville Residential Building Permit Checklist.

  2. 2

    Rough Plumbing

    Part of the four-way rough-in inspection.

  3. 3

    Final

    Fixtures connected, no leaks.

See the full Springville inspection guide — scheduling & re-inspection fees →

Tips

  • Sewer lateral inspections in Springville specifically require water testing, per the Residential Building Permit Checklist — plan for this before scheduling the underground inspection.
  • Plumbing permits are separate from the building permit in Springville — confirm your plumbing subcontractor has pulled their own trade permit.

Frequently asked questions

Yes. Plumbing permits must be applied for and paid separately by the subcontractor performing the work — they are not included in the building permit fee.

In Springville, the published Plumbing Permit Fee is: No fixed dollar figure published for a standalone plumbing permit was found in Springville's Building Fees fee-schedule section.. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Springville does not publish a plan-review timeline for this permit. Contact Springville City Community Development — Building Division at (801) 489-2704 for current turnaround.

You'll need: Trade Permit Application. Depending on your project, Springville may also ask for: Plumbing Plan. See the required-documents checklist on this page for details on each.

Springville requires 3 inspection(s) for a plumbing permit, in order: Underground / Sewer Lateral, Rough Plumbing, Final. Schedule each through Springville City Community Development — Building Division ((801) 489-2704).

Apply through Springville City Community Development — Building Division at 110 South Main Street, Springville, UT 84663 (Attn: Building Dept. for permit payments). Phone: (801) 489-2704, email: buildingpermits@springvilleutah.gov. Office hours: Building and Inspections Department: Monday–Friday, 8:00 a.m. to 5:00 p.m., closed all major holidays, per Springville Residential Building Permit Checklist (July 2023). NOTE: Springville's Building FAQ separately states building-division phone coverage (staffer 'Hollie') runs 8:00 a.m.–1:00 p.m. mornings only — the 8 AM–5 PM window is the department's official posted hours per the Permit Checklist, phone/counter availability may be more limited.. Official information: https://www.springvilleutah.gov/community-development/building-division/.

Springville, Utah has adopted: 2024 International Building Code (IBC) — Springville City Code § 10-1-101 adopts 'the International Building Code and the International Residential Code, as published by the International Code Council and adopted by the State of Utah, including all State statutes, amendments and regulations' as the City Building Code; the statewide edition CURRENT as of 7/1/2026 is the 2024 IBC per Utah Code § 15A-2-103(1)(a) (confirmed by direct fetch of the live statute 2026-07-16). The 2021 IBC governed through 6/30/2026. Springville § 10-1-101 last amended by Ordinance 16-2025 (effective 7/15/2025).; 2021 International Residential Code (IRC) — per Springville City Code § 10-1-101 (defers to state-adopted edition) and confirmed directly on Springville's own Residential Building Permit Checklist (July 2023) and Basement Improvement Permit Checklist (July 2023): 'Building shall be designed to the 2021 IRC (International Residential Code)' [and, for basements, 'and State Amendments']. UNCHANGED by the 7/1/2026 code cycle per Utah Code § 15A-2-103(1)(b) — confirmed by direct statute fetch 2026-07-16.; 2024 International Plumbing Code (IPC), International Mechanical Code (IMC), International Fuel Gas Code (IFGC), and International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC) — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(d)/(e)/(f)/(h)/(i) respectively, incorporated by reference via Springville City Code § 10-1-101's adoption of state-amended construction codes (confirmed by direct fetch of the live statute 2026-07-16). The 2021 editions of these five codes governed through 6/30/2026. The IECC is a single statewide edition — the statute contains no residential/commercial split. No Springville-specific edition citation for these individual codes was found beyond the statewide statute and Chapter 10-7 (Building and Construction Standards and Codes) cross-reference. The International Fire Code (IFC) is not adopted anywhere in Utah Code § 15A-2-103 and no Springville-specific IFC citation was found either.; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g), the statewide-mandated edition that supersedes any locally-referenced older edition; UNCHANGED by the 7/1/2026 code cycle. NOTE: Springville's own 'Solar Permit Process' document (springvilleutah.gov, dated 2019) states 'System shall be designed to the 2015 IRC and 2017 NEC' — this document remains STALE relative to the current statewide statute; the 2023 NEC and 2021 IRC (both continuing unchanged past 7/1/2026) govern, per Utah Code § 15A-2-103, which supersedes outdated city documents.; NOTE (2026-07-16 corpus-staleness fix): This file previously stated the 2021 editions of IBC/IPC/IMC/IFGC/IECC/IEBC as current with only a forward-looking mention of the 7/1/2026 flip; the effective date has now passed and the entries above have been corrected to state the 2024 editions as current, with the superseded 2021 editions preserved as historical context. IRC (2021) and NEC (2023) were NOT changed. No Springville-specific city page (beyond the 2019-dated, already-flagged-stale Solar Permit Process document) independently states individual code editions for IBC/IPC/IMC/IFGC/IECC/IEBC, so no additional city-page lag was found to record for those codes.. Local amendments apply — see the Springville overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.