Fire Sprinkler, Alarm, and Hood Plan Review Permit — Springville, Utah · Requirements sheet
Reviewed 2026-07-20 · Source: https://www.springvilleutah.gov/fire-rescue/inspections-permits/fire-inspection/fire-inspection-plans/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Sprinkler, Alarm, and Hood Plan Review Permit in Springville, Utah
Required for fire alarm systems, fire sprinkler systems, and hood extinguishing systems in Springville. Per the city's own Fire and Rescue 'Fire Sprinkler, Alarm and Hood Plan Inspections' page, the Springville City Fire Marshal — not the Building Division — reviews these plans directly, and 'Upon approval construction permits will be issued.' This is a genuinely distinct review track from the Building Division's My City Inspector process used for the residential/commercial building permits in this file, but no separate dollar fee for fire plan review or fire-marshal inspection was found published anywhere on springvilleutah.gov or in the FY2025 Comprehensive Fee Schedule (Exhibit B) as of 2026-07-20 — that schedule's only fire-adjacent 'Alarm Permit Fee' ($25.00, line 103) is filed under 'Public Safety Fees' immediately after Dog License/Animal Shelter fees and billed under Resolution No. 98-35, which is the Police Department's burglar/security alarm registration permit, not a fire-marshal life-safety-system fee — it is NOT included here as it would misattribute an unrelated fee. Re-chased 2026-07-20: located and checked the newer FY2026 Comprehensive Fee Schedule (published 2025-09, springvilleutah.gov/wp-content/uploads/sites/6/2025/09/FY-2026-Comprehensive-Fee-Schedule.pdf), which supersedes the FY2025 edition — it shows the same unrelated $25.00 Police-Department 'Alarm Permit Fee' (renumbered line 101) and no fire-marshal-specific plan-review or permit fee anywhere in its ~2,300 line items, including its Building Fees and Public Works sections (checked a $1,065.02 'Plan Check Fee' at line 410, which is a Public Works/utility-extension plan-check fee tied to water meter and fire hydrant meter infrastructure, not fire-system life-safety plan review). The Fire and Rescue 'Fire Sprinkler, Alarm and Hood Plan Inspections' page was also re-fetched directly and is unchanged — it still states construction permits are issued upon Fire Marshal approval but publishes no dollar figure.
Reviewed 2026-07-20 · Source
When you need this permit
- Applies to fire alarm systems, fire sprinkler systems, and hood extinguishing systems, plus related preliminary site plans, fire department apparatus accessibility, fire flow requirements, and new fire hydrant placement
- Plans reviewed directly by the Springville City Fire Marshal, separate from the Building Division's plan review
- Plans must be submitted electronically by email (via the Fire and Rescue department's 'Email Plans' link)
- Construction permits are issued only upon the Fire Marshal's approval of submitted plans
- Inspections must be requested at least two days before the intended inspection date, by phone or email to the Fire Marshal
- Inspections are not conducted on Mondays (to accommodate a required 24-hour battery test); Friday inspections are by request only
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Fire Marshal Plan Review
Springville City Fire Marshal reviews submitted fire alarm, fire sprinkler, and/or hood extinguishing system plans; construction permits are issued upon approval, per the Fire and Rescue department's Fire Sprinkler, Alarm and Hood Plan Inspections page.
- 2
Field Inspection
Scheduled by contacting the Fire Marshal at least two days in advance. Not conducted on Mondays (to allow a required 24-hour battery test); Friday inspections are by request only.
See the full Springville inspection guide — scheduling & re-inspection fees →
Tips
- Fire sprinkler, alarm, and hood system plans in Springville go to the Fire Marshal directly (by email), not through the My City Inspector portal used for the building permit itself — budget for two separate submittal tracks on projects that need both.
- As of 2026-07-20, Scott Nagle is Springville's Fire Marshal: (801) 491-5602 office, (435) 655-5071 cell.
- No inspections are conducted on Mondays because of a required 24-hour battery test cycle, and Friday inspections are by request only — plan scheduling accordingly and request an inspection at least two business days ahead.
- Do not confuse the FY2025/FY2026 Comprehensive Fee Schedule's $25.00 'Alarm Permit Fee' with a fire alarm system permit — that line item sits in the 'Public Safety Fees' section next to Dog License and False Alarm Response fees and is the Police Department's burglar/security-alarm registration fee, unrelated to Fire Marshal life-safety plan review.
- Re-chased 2026-07-20 against the newer FY2026 Comprehensive Fee Schedule (published 2025-09) and the live Fire and Rescue page directly — both confirm the same result as the FY2025 pass: no fire-marshal-specific plan-review or permit fee is published anywhere by the city. This fee genuinely appears to be assessed case-by-case rather than posted, unlike Springville's other published fee tables.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Springville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Springville
Fire Sprinkler, Alarm, and Hood Plan Review Permit in other cities
Compare fire sprinkler, alarm, and hood plan review permit fees across Utah →