Required for fire alarm systems, fire sprinkler systems, and hood extinguishing systems in Springville. Per the city's own Fire and Rescue 'Fire Sprinkler, Alarm and Hood Plan Inspections' page, the Springville City Fire Marshal — not the Building Division — reviews these plans directly, and 'Upon approval construction permits will be issued.' This is a genuinely distinct review track from the Building Division's My City Inspector process used for residential/commercial building permits, but no separate dollar fee for fire plan review or fire-marshal inspection is published anywhere on springvilleutah.gov or in the FY2025 Comprehensive Fee Schedule (Exhibit B) — that schedule's only fire-adjacent 'Alarm Permit Fee' ($25.00, line 103) is filed under 'Public Safety Fees' immediately after Dog License/Animal Shelter fees and billed under Resolution No. 98-35, which is the Police Department's burglar/security alarm registration permit, not a fire-marshal life-safety-system fee — it is NOT included here as it would misattribute an unrelated fee. The newer FY2026 Comprehensive Fee Schedule (published 2025-09, springvilleutah.gov/wp-content/uploads/sites/6/2025/09/FY-2026-Comprehensive-Fee-Schedule.pdf), which supersedes the FY2025 edition, shows the same unrelated $25.00 Police-Department 'Alarm Permit Fee' (renumbered line 101) and no fire-marshal-specific plan-review or permit fee anywhere in its ~2,300 line items, including its Building Fees and Public Works sections (the $1,065.02 'Plan Check Fee' at line 410 is a Public Works/utility-extension plan-check fee tied to water meter and fire hydrant meter infrastructure, not fire-system life-safety plan review). The Fire and Rescue 'Fire Sprinkler, Alarm and Hood Plan Inspections' page states construction permits are issued upon Fire Marshal approval but publishes no dollar figure.

Reviewed 2026-08-16 · Source

When you need this permit

  • Applies to fire alarm systems, fire sprinkler systems, and hood extinguishing systems, plus related preliminary site plans, fire department apparatus accessibility, fire flow requirements, and new fire hydrant placement
  • Plans reviewed directly by the Springville City Fire Marshal, separate from the Building Division's plan review
  • Plans must be submitted electronically by email (via the Fire and Rescue department's 'Email Plans' link)
  • Construction permits are issued only upon the Fire Marshal's approval of submitted plans
  • Inspections must be requested at least two days before the intended inspection date, by phone or email to the Fire Marshal
  • Inspections are not conducted on Mondays (to accommodate a required 24-hour battery test); Friday inspections are by request only

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Fire Plan Review / Inspection Fee
Springville's 'Fire Sprinkler, Alarm and Hood Plan Inspections' page (springvilleutah.gov/fire-rescue/inspections-permits/fire-inspection/fire-inspection-plans/) states plans are reviewed by the Fire… Show full citationSpringville's 'Fire Sprinkler, Alarm and Hood Plan Inspections' page (springvilleutah.gov/fire-rescue/inspections-permits/fire-inspection/fire-inspection-plans/) states plans are reviewed by the Fire Marshal and permits issued upon approval, but publishes no fee amount. The FY2025 Comprehensive Fee Schedule (Exhibit B, Public Safety Fees, line 103) lists only an unrelated 'Alarm Permit Fee — $25.00' under Resolution No. 98-35, which context (adjacent Dog License and False Alarm Response line items) identifies as the Police Department's burglar/security-alarm registration fee, not a fire-system plan-review fee. The newer FY2026 Comprehensive Fee Schedule (springvilleutah.gov/wp-content/uploads/sites/6/2025/09/FY-2026-Comprehensive-Fee-Schedule.pdf, published 2025-09, superseding the FY2025 edition) carries the same unrelated $25.00 Police-Department fee (renumbered line 101) as the only 'alarm' line item in the entire ~2,300-line schedule — no fire-marshal plan-review or permit fee appears there either, and no dedicated fire-fee PDF exists outside the Comprehensive Fee Schedule. Springville City Code Chapter 3-4 (Fire Code, hosted at codepublishing.com) contains no fire sprinkler/alarm/hood permit fee section; its only fee reference, for underground LPG storage tank permits, states the fee is 'to be set by the City Council from time to time' — confirming fees for fire-related permits are set by Council resolution (the Comprehensive Fee Schedule) rather than codified in the Fire Code itself. No City Council resolution or Utah Public Meeting Notice posting specifically setting a Fire Marshal plan-review fee has been adopted or published. The Fiscal 2026-2027 Comprehensive Fee Schedule in the Springville City FY 2026-2027 Interim Budget (published July 2026) likewise contains no fire-marshal plan-review, sprinkler, alarm or hood permit fee anywhere in the 289-page document; the only 'Alarm Permit Fee' remains the $25.00 line under Resolution No. 98-35, and that budget's own narrative section states outright: 'Police — the department proposes doubling the alarm permit fee from $25', which independently confirms that line belongs to the Police Department rather than to fire-system review. It is possible fire-system review costs are absorbed into the general Building Permit Fee / Plan Check Fee ('Assessed by Plans Examiner,' per the residential/commercial permit entries), but no Springville-published source confirms that mechanism specifically for fire-marshal review. No published dollar figure for Fire Marshal plan review or inspection exists; the fee appears to be assessed case-by-case by the Fire Marshal. Confirm directly with the Fire Marshal's office, (801) 491-5602.
No fire-marshal-specific dollar figure was found published on springvilleutah.gov or in any of the FY2025, FY 2026 or Fiscal 2026-2027 Comprehensive Fee Schedules.

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler, Alarm, and Hood Plan Review Permit permit actually take in Springville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire Marshal Plan Review

    Springville City Fire Marshal reviews submitted fire alarm, fire sprinkler, and/or hood extinguishing system plans; construction permits are issued upon approval, per the Fire and Rescue department's Fire Sprinkler, Alarm and Hood Plan Inspections page.

  2. 2

    Field Inspection

    Scheduled by contacting the Fire Marshal at least two days in advance. Not conducted on Mondays (to allow a required 24-hour battery test); Friday inspections are by request only.

See the full Springville inspection guide — scheduling & re-inspection fees →

Tips

  • Fire sprinkler, alarm, and hood system plans in Springville go to the Fire Marshal directly (by email), not through the My City Inspector portal used for the building permit itself — budget for two separate submittal tracks on projects that need both.
  • As of 2026-07-20, Scott Nagle is Springville's Fire Marshal: (801) 491-5602 office, (435) 655-5071 cell.
  • No inspections are conducted on Mondays because of a required 24-hour battery test cycle, and Friday inspections are by request only — plan scheduling accordingly and request an inspection at least two business days ahead.
  • Do not confuse the Comprehensive Fee Schedule's $25.00 'Alarm Permit Fee' with a fire alarm system permit — that line item sits in the 'Public Safety Fees' section next to Dog License and False Alarm Response fees and is the Police Department's burglar/security-alarm registration fee, unrelated to Fire Marshal life-safety plan review. The Springville City FY 2026-2027 Interim Budget settles this outright: its narrative reads 'Police — the department proposes doubling the alarm permit fee from $25.'
  • Both the FY2026 Comprehensive Fee Schedule (published 2025-09) and the city's Fire and Rescue page confirm the same result as the FY2025 schedule: no fire-marshal-specific plan-review or permit fee is published anywhere by the city. This fee genuinely appears to be assessed case-by-case rather than posted, unlike Springville's other published fee tables.

Frequently asked questions

Springville requires a fire sprinkler, alarm, and hood plan review permit for: Applies to fire alarm systems, fire sprinkler systems, and hood extinguishing systems, plus related preliminary site plans, fire department apparatus accessibility, fire flow requirements, and new fire hydrant placement; Plans reviewed directly by the Springville City Fire Marshal, separate from the Building Division's plan review; Plans must be submitted electronically by email (via the Fire and Rescue department's 'Email Plans' link); Construction permits are issued only upon the Fire Marshal's approval of submitted plans; Inspections must be requested at least two days before the intended inspection date, by phone or email to the Fire Marshal; Inspections are not conducted on Mondays (to accommodate a required 24-hour battery test); Friday inspections are by request only. If your project isn't listed, confirm with Springville City Community Development — Building Division at (801) 489-2704 before starting work.

No fee amount for Fire Marshal plan review or inspection is published on springvilleutah.gov or in the FY2025 or FY2026 Comprehensive Fee Schedule. Contact the Fire Marshal's office at (801) 491-5602 for current pricing before budgeting.

Springville does not publish a plan-review timeline for this permit. Contact Springville City Community Development — Building Division at (801) 489-2704 for current turnaround.

You'll need: Fire Sprinkler / Alarm / Hood Plan Submittal. See the required-documents checklist on this page for details on each.

Springville requires 2 inspection(s) for a fire sprinkler, alarm, and hood plan review permit, in order: Fire Marshal Plan Review, Field Inspection. Schedule each through Springville City Community Development — Building Division ((801) 489-2704).

Apply through Springville City Community Development — Building Division at 110 South Main Street, Springville, UT 84663 (Attn: Building Dept. for permit payments). Phone: (801) 489-2704, email: buildingpermits@springvilleutah.gov. Office hours: Building and Inspections Department: Monday–Friday, 8:00 a.m. to 5:00 p.m., closed all major holidays, per Springville Residential Building Permit Checklist (July 2023). NOTE: Springville's Building FAQ separately states building-division phone coverage (staffer 'Hollie') runs 8:00 a.m.–1:00 p.m. mornings only — the 8 AM–5 PM window is the department's official posted hours per the Permit Checklist, phone/counter availability may be more limited.. Official information: https://www.springvilleutah.gov/community-development/building-division/.

Springville, Utah has adopted: 2024 International Building Code (IBC) — Springville City Code § 10-1-101 adopts 'the International Building Code and the International Residential Code, as published by the International Code Council and adopted by the State of Utah, including all State statutes, amendments and regulations' as the City Building Code; the statewide edition CURRENT as of 7/1/2026 is the 2024 IBC per Utah Code § 15A-2-103(1)(a) (confirmed by direct fetch of the live statute 2026-07-16). The 2021 IBC governed through 6/30/2026. Springville § 10-1-101 last amended by Ordinance 16-2025 (effective 7/15/2025).; 2021 International Residential Code (IRC) — per Springville City Code § 10-1-101 (defers to state-adopted edition) and stated on Springville's own Residential Building Permit Checklist (July 2023) and Basement Improvement Permit Checklist (July 2023): 'Building shall be designed to the 2021 IRC (International Residential Code)' [and, for basements, 'and State Amendments']. Unchanged by the 7/1/2026 code cycle per Utah Code § 15A-2-103(1)(b).; 2024 International Plumbing Code (IPC), International Mechanical Code (IMC), International Fuel Gas Code (IFGC), and International Energy Conservation Code (IECC); 2024 International Existing Building Code (IEBC) — CURRENT as of 7/1/2026 per Utah Code § 15A-2-103(1)(d)/(e)/(f)/(h)/(i) respectively, incorporated by reference via Springville City Code § 10-1-101's adoption of state-amended construction codes (confirmed by direct fetch of the live statute 2026-07-16). The 2021 editions of these five codes governed through 6/30/2026. The IECC is a single statewide edition — the statute contains no residential/commercial split. No Springville-specific edition citation for these individual codes was found beyond the statewide statute and Chapter 10-7 (Building and Construction Standards and Codes) cross-reference. The International Fire Code (IFC) is not adopted anywhere in Utah Code § 15A-2-103 and no Springville-specific IFC citation was found either.; 2023 National Electrical Code (NEC) — per Utah Code § 15A-2-103(1)(g), the statewide-mandated edition that supersedes any locally-referenced older edition; UNCHANGED by the 7/1/2026 code cycle. NOTE: Springville's own 'Solar Permit Process' document (springvilleutah.gov, dated 2019) states 'System shall be designed to the 2015 IRC and 2017 NEC' — this document remains STALE relative to the current statewide statute; the 2023 NEC and 2021 IRC (both continuing unchanged past 7/1/2026) govern, per Utah Code § 15A-2-103, which supersedes outdated city documents.; The 2021 editions of IBC/IPC/IMC/IFGC/IECC/IEBC were superseded at the 7/1/2026 statewide transition; the entries above state the 2024 editions as current, with the superseded 2021 editions preserved as historical context. The IRC (2021) and NEC (2023) editions were not affected by that transition. No Springville-specific city page (beyond the 2019-dated, stale Solar Permit Process document) independently states individual code editions for IBC/IPC/IMC/IFGC/IECC/IEBC.. Local amendments apply — see the Springville overview page for the full list.

The Springville City Fire Marshal reviews all plans for fire alarm systems, fire sprinkler systems, and hood extinguishing systems directly — not the Building Division. Construction permits are issued upon the Fire Marshal's approval, per Springville Fire and Rescue's official Fire Sprinkler, Alarm and Hood Plan Inspections page.

Springville's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Springville yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Springville lands. Privacy.