Residential Basement Finish / Remodel / Deck Permit in Heber City, Utah
Required for finishing a basement, remodeling rooms, or building an attached/detached deck meeting the city's permit-trigger criteria in Heber City. Uses the same Plan Review fee structure (25% of building permit fee) and the same 2-week initial-review timeline as new construction, per the city's dedicated submittal checklist.
Verified 2026-07-07 · Source
When you need this permit
- Finished basements: fully dimensioned floor plans, identification of load-bearing walls, window/window-well dimensions for bedrooms (escape ladder required if window well exceeds 44" measured to top of well from sill), smoke/CO alarm layout wired in series across all levels, electrical outlet layout and panel location, plumbing fixture locations
- Room remodels: before/after floor plans, bedroom window size and sill heights if affected, smoke/CO alarm upgrades to all bedrooms and each floor where attics/crawl space/unfinished basements exist (required even if the remodel doesn't touch those spaces)
- Decks (attached, supported by dwelling): permit required if floor area exceeds 70 sq ft, any horizontal dimension exceeds 7 ft, stairs to grade have 4+ risers, deck surface is over 30 inches above grade, or deck is roofed/has a pergola; footings must extend below the 36" frost level
- Decks (detached, not supported by dwelling): permit required if area exceeds 200 sq ft or stairs to grade have 4+ risers; engineering required if roofed, has a pergola, and/or is over 30" above grade; decks over 600 sq ft must be engineered
- Decks that are self-supporting, under 200 sq ft, and low to the ground (beam/joist underside less than 12" from grade, using preservative-treated lumber) are NOT required to be permitted
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Scheduled Inspections (Building/Electrical/Mechanical/Plumbing)
Scheduled via MyCityInspector; inspection hours Monday–Thursday 7:30 a.m.–4:30 p.m.
See the full Heber City inspection guide — scheduling & re-inspection fees →
Tips
- Even a remodel that doesn't touch an attic, crawl space, or unfinished basement still requires smoke and CO alarm upgrades to all bedrooms and each floor if those spaces exist elsewhere in the home, per the city's own checklist.
- A deck under 200 sq ft, self-supporting, low to the ground (beam/joist underside under 12 inches from grade) using preservative-treated lumber, does NOT require a permit at all in Heber City.
- Bedroom window wells taller than 44 inches (measured to the top of the well from the window sill) require an attached escape ladder.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Heber City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Heber City
Compare residential basement finish / remodel / deck permit fees across Utah →