EV Charger / EVSE Permit — Heber City, Utah · Requirements sheet
Reviewed 2026-07-20 · Source: https://heber.municipalcodeonline.com/book?type=fees
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Heber City, Utah
Heber City does not publish a distinct EV-charger/EVSE permit or fee line item. The city's Consolidated Fee Schedule (Ordinance 2025-15, Exhibit A, Building Fees table) lists standalone electrical inspection fees — 'Temporary Power Pedestal Inspection' ($60.00), 'Electrical Service Change-Out Inspection' ($60.00), and 'Other (Electrical, Building, Mechanical, and Plumbing)' ($60.00) — and prices new-construction building permits on the ICC Building Safety Journal valuation table. A standalone EV charger installation not tied to new construction would most likely fall under the $60.00 'Other (Electrical...)' inspection fee or the general valuation-based Building Permit fee, but no source explicitly names EV chargers, so this is not asserted as certain.
Reviewed 2026-07-20 · Source
When you need this permit
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in Heber City
- Electrical work regulated statewide by the 2023 NEC (Utah Code § 15A-2-103(1)(g))
- Building permit application submitted through Heber City's online permit portal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Inspection
Field inspection of the EV charger circuit and installation, scheduled through the Heber City Building and Safety Division, (435) 654-6330.
See the full Heber City inspection guide — scheduling & re-inspection fees →
Tips
- Heber City has no EV-charger-specific permit or fee line item — the closest published category for a standalone electrical job is the $60.00 'Other (Electrical, Building, Mechanical, and Plumbing)' inspection fee (Ordinance 2025-15, Exhibit A).
- If the EV charger is installed as part of new construction, it is instead covered by the general ICC-valuation-based Building Permit fee rather than a standalone inspection fee.
- Confirm which fee category applies with the Building and Safety Division, (435) 654-6330, before applying, since no source explicitly names EV chargers.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Heber City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Heber City
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Utah →
Look up this fee in a different city →