Skip to main content
PermitBase

Unincorporated Washington County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Washington County, Utah.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
111 East Tabernacle St., St. George, UT 84770
Phone
(435) 301-7250
Email
Office hours
Mon–Fri, normal business hours (24-hour advance notice required for inspections)

Published scheduling rules

  • 24-hour advance notice is required after work is completed and ready for inspection. A permit number is required when scheduling inspections. (General)

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Foundation

    Footings, forms, rebar — before concrete pour

  2. 2

    Framing

    Structure, fire separation, egress windows

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Insulation

    Insulation and vapor barrier before drywall

  5. 5

    Final

    All work complete, smoke/CO detectors, address posted, ready for occupancy

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Standard IBC inspection sequence before concrete pour.

  2. 2

    Structural / Framing

    Framing and structural elements verified against submitted plans before close-in.

  3. 3

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  4. 4

    Final

    All work complete before occupancy.

Applies to: Residential Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before gunite/shotcrete

  2. 2

    Electrical / Bonding

    Pool bonding grid, equipment connections, GFCI protection per NEC Article 680

  3. 3

    Barrier

    Pool fence/barrier — 48-inch minimum height, self-closing/self-latching gates required

  4. 4

    Final

    Pool complete, filled, equipment operational, all barriers in place

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Wall construction and any structural modifications verified before close-in, where applicable to the scope of work.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  3. 3

    Final

    All work complete before occupancy.

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects complete and any required asbestos clearance obtained before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, site conditions verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Final

    Charger installed and operational, GFCI/AFCI protection verified where required, panel labeled

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Sprinkler System Flush, Rough-In, and Acceptance Test

    Bundled into HVFSSD's single Sprinkler System fee ($1,175.00 commercial / $950.00 residential), which also includes the plan review and, for residential, final occupancy.

  2. 2

    Fire Alarm Inspection and Acceptance Test

    Bundled into HVFSSD's single $350.00 per-system Fire Alarm fee, which also includes the plan review.

Applies to: Manufactured Home Permit

  1. 1

    Foundation / Setup

    Foundation or blocking system, tie-downs/anchoring, and utility connections before occupancy

  2. 2

    Final

    All utilities connected, skirting in place, site complete

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances and support

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition and replace damaged decking before proceeding

  2. 2

    Final

    Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Residential Building PermitRe-Inspection Fee · Washington County Community Development Fees page — 'Re-inspection fees assessed under provisions of section 305.8: $100.00 per hour', verified June 30, 2026.
$100.00 per hour (minimum one hour)
Electrical PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
EV Charger / EVSE PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
Plumbing PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
Mechanical / HVAC PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
Roofing PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
Swimming Pool PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
Demolition PermitRe-Inspection Fee · Washington County Community Development Fees page, verified June 30, 2026.
$100.00 per hour (minimum one hour)
Commercial Building PermitRe-Inspection Fee · Washington County Community Development Fees page — 'Re-inspection fees assessed under provisions of section 305.8: $100.00 per hour', verified 2026-07-19.
$100.00 per hour (minimum one hour)

Unincorporated Washington County building permits

Get alerts for Unincorporated Washington County

We'll email you when Unincorporated Washington County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.