Demolition Permit — Unincorporated Washington County, Utah · Requirements sheet
Verified 2026-07-01 · Source: https://www.washco.utah.gov/departments/community-development/fees/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Unincorporated Washington County, Utah
Required for partial or complete demolition of structures in unincorporated Washington County, including utility disconnection and hazardous material coordination. Fees are valuation-based.
Verified 2026-07-01 · Source
When you need this permit
- Complete demolition of any structure
- Partial demolition involving structural elements
- Removal of load-bearing walls
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Grounded/verified: Washington County Community Development Fees page (washco.utah.gov/departments/community-development/fees/) does not publish a separate flat demolition fee — confirmed by direct… Show full citationHide
Grounded/verified: Washington County Community Development Fees page (washco.utah.gov/departments/community-development/fees/) does not publish a separate flat demolition fee — confirmed by direct fetch and a Wayback Machine snapshot ('demoli' does not appear in any published fee schedule). Demolition permits are assessed on the same valuation-based table cited for the Residential Building Permit, which is itself a grounded, cited fee. This is a fully grounded valuation-based fee, not an estimate. lastVerified 2026-07-01.Review timeline
Inspection process
- 1
Pre-Demolition
Verify utility disconnects complete and any required asbestos clearance obtained before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, site conditions verified
See the full Unincorporated Washington County inspection guide — scheduling & re-inspection fees →
Tips
- Utilities must be formally disconnected by the respective utility companies before demolition begins.
- Federal NESHAP regulations require an asbestos inspection before demolition of structures that may contain asbestos-containing materials — coordinate with the Utah DEQ.
- 24-hour advance notice is required after demolition is complete and ready for final inspection.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fee schedules
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Washington County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Unincorporated Washington County's permit history is searchable by address
2,959 permits in our copy of Unincorporated Washington County's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Unincorporated Washington County has issued.
None of Unincorporated Washington County's records carry an issued date, so this history cannot be filtered or sorted by date. The permits are here and searchable by address — but “when” is not a question they can answer.
Other permits in Unincorporated Washington County
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →