Change of Use / Certificate of Occupancy Permit in Unincorporated Washington County, Utah
Unincorporated Washington County requires a certificate of occupancy before any land or building is used or occupied, and before the character or use of any building or land is changed from one use to another -- directly confirmed by fetching the live text of two real, currently-operative county code sections on 2026-07-22: County Code Section 10-1-7 (OCCUPANCY PERMIT REQUIRED, Title 10 Zoning Regulations, Ord. 2001-815-O as amended by Ord. 2024-1251-O, 2-20-2024) and Section 9-1-9 (CERTIFICATE OF OCCUPANCY, Title 9 Building Code, Ord. 2007-929-O). For new construction, the certificate of occupancy is issued as part of the standard building permit process -- this file's residential-building-permit entry already documents that its Final inspection results in the certificate of occupancy being 'issued upon passing,' with no separate fee beyond the standard valuation-based building permit fee. For a standalone change-of-use application involving no construction (e.g., converting an existing commercial space to a new use), no dedicated application form, checklist, or fee schedule was found published on the county's Planning Applications, Building Permit Documents, or Fees pages (all re-checked 2026-07-22) -- this is a confirmed absence, not an unestimated gap; contact Community Development directly to determine the applicable process.
Verified 2026-07-22 · Source
When you need this permit
- No land may be used or occupied, and no building structurally altered or erected may be used or changed in use, until a certificate of occupancy is issued by the building inspector confirming compliance with Title 10 (Zoning Regulations) -- County Code Section 10-1-7(A), directly quoted from the live code text fetched 2026-07-22
- A permit is also required 'whenever the character or use of any building or land is proposed to be changed from one use to another use' -- County Code Section 10-1-7(B), directly quoted from the live code text fetched 2026-07-22 (amd. Ord. 2024-1251-O, 2-20-2024)
- No certificate of occupancy may be issued for any building constructed, altered, or repaired unless it complies with the building code, the zoning ordinance, the subdivision ordinance, the groundwater protection ordinance, and all other applicable ordinances -- County Code Section 9-1-9, directly quoted from the live code text fetched 2026-07-22 (Ord. 2007-929-O, 2-6-2007)
- For projects involving construction or alteration, the certificate of occupancy is issued at the Final inspection of the associated building permit (see this file's residential-building-permit entry)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final / Compliance Review
Building inspector confirms the building or land use complies with Title 10 (zoning), the subdivision ordinance, the groundwater protection ordinance, and (for constructed/altered/repaired buildings) the building code, before issuing the certificate of occupancy -- per County Code Sections 10-1-7 and 9-1-9.
See the full Unincorporated Washington County inspection guide — scheduling & re-inspection fees →
Tips
- A certificate of occupancy is required not only for new construction but any time the use of a building or land is proposed to change from one use to another -- County Code Section 10-1-7(B), directly quoted from the live code text.
- For projects that also require a building permit (new construction, alteration, or repair), the certificate of occupancy is issued at the Final inspection with no separate fee -- see this file's residential-building-permit entry.
- No standalone application, checklist, or fee schedule is published for a change-of-use request involving no construction -- confirmed absence, re-checked 2026-07-22. Contact Community Development at (435) 301-7250 before assuming no permit is needed; the statute (10-1-7(B)) applies regardless of whether construction is involved.
- Section 10-1-7 was amended as recently as Ord. 2024-1251-O (2-20-2024), so it reflects the current, in-force text as of this entry's 2026-07-22 verification.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Washington County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Washington County
Change of Use / Certificate of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Unincorporated Washington County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Washington County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →