Residential Building Permit — Unincorporated Washington County, Utah · Requirements sheet
Verified 2026-06-30 · Source: https://www.washco.utah.gov/departments/community-development/fees/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit in Unincorporated Washington County, Utah
Required for new residential construction, additions, and structural alterations in unincorporated Washington County. Permit fees are valuation-based per the Washington County Community Development fee schedule. Applications are accepted electronically only through the county's online permitting portal. Building Official: Kurt Dampf.
Verified 2026-06-30 · Source
When you need this permit
- New single-family or multi-family residential construction
- Additions or structural modifications to existing structures
- Conversion of non-habitable to habitable space
- Work valued over $500 requiring plan review under adopted codes
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 10 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
See the full Unincorporated Washington County inspection guide — scheduling & re-inspection fees →
Tips
- Washington County requires 24-hour advance notice after work is completed and ready for inspection. A permit number is required when scheduling.
- Applications are accepted electronically only through outpost.washco.utah.gov — paper applications are not accepted.
- Valuation is calculated as square footage times average cost per sq ft. Contact Community Development at (435) 301-7250 to confirm the current average cost figure used for valuation.
- A 4-yard-capacity covered dumpster AND a portable sanitary facility (porta-pottie) are both required at the construction site during all phases of construction per Washington County policy.
- Fire special service district impact fees must be paid and the receipt submitted before the building permit is issued — confirm the applicable district with Community Development.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Washington County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Washington County
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →