Excavation, Grading, and Road Cut Permits in North Ogden, Utah

North Ogden requires separate permits and fees for excavation, grading, blasting, and road cuts, published in the Building Department section of the Consolidated Fee Schedule. These are distinct from the general Building Permit Fee.

Verified 2026-07-13 · Source

When you need this permit

  • Excavation work requires an Excavation Permit
  • Grading work requires a Grading Permit
  • Blasting requires a Blasting Permit
  • Cutting into a public road/right-of-way requires a Road Cut Fee payment plus bonding

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Excavation PermitCORRECTED 2026-07-13: this entry previously listed a standalone 'Excavation Permit' fee of $1,000.00, but that figure does not appear in either the Resolution 03-2026 or Resolution 05-2026 (current, adopted May 12, 2026, effective May 13, 2026) editions of the Consolidated Fee Schedule. Direct visual inspection of the Building Permit Fees table (page 3) in both editions shows 'Excavation Permit' and 'Road Cut Fee' sharing a single merged fee cell — '$75.00 + Road Cut Fee' / '$2.50 per Sq Ft' — with no distinct dollar figure for Excavation Permit alone. The $1,000.00 previously recorded here most likely came from a mis-mapped extraction (the same $1,000.00 value that correctly belongs to the separate 'Mining/Crushing Permit' line item). Corrected to match the actual published fee structure rather than carrying forward an unsupported figure, per the zero-fabrication policy.
$75.00 + Road Cut Fee ($2.50 per sq ft) — shares the Road Cut Fee formula below; no separate flat Excavation Permit fee is published
Grading PermitNorth Ogden City Consolidated Fee Schedule, Resolution 05-2026 (adopted May 12, 2026, effective May 13, 2026 — current edition, superseding Resolution 03-2026), Building Permit Fees section: 'Grading Permit ... $150.00.' Figure unchanged between the 03-2026 and 05-2026 editions (confirmed 2026-07-13).
$150.00
Blasting PermitNorth Ogden City Consolidated Fee Schedule, Resolution 05-2026 (adopted May 12, 2026, effective May 13, 2026 — current edition, superseding Resolution 03-2026), Building Permit Fees section: 'Blasting Permit ... $50.00.' Figure unchanged between the 03-2026 and 05-2026 editions (confirmed 2026-07-13).
$50.00
Road Cut FeeNorth Ogden City Consolidated Fee Schedule, Resolution 05-2026 (adopted May 12, 2026, effective May 13, 2026 — current edition, superseding Resolution 03-2026), Building Permit Fees and North Ogden City Street Cuts Fee sections. Fee applies to rights-of-way 60 feet or less; 66-foot rights-of-way are 15% more; 80-foot-plus rights-of-way are 30% more. All figures unchanged between the 03-2026 and 05-2026 editions (confirmed 2026-07-13).
$75.00 + Road Cut Fee ($2.50 per sq ft); Taxing Entities (Special Districts & Government) pay 75% of standard fee; Cash Bond $300.00; Performance Bond $2,000.00; New Road Cut Additional Fee $500.00 (roads two years old or less)
Mining/Crushing PermitNorth Ogden City Consolidated Fee Schedule, Resolution 05-2026 (adopted May 12, 2026, effective May 13, 2026 — current edition, superseding Resolution 03-2026), Building Permit Fees section. Figure unchanged between the 03-2026 and 05-2026 editions (confirmed 2026-07-13).
$1,000.00

Review timeline

Plan review
Not published — contact the department

How long did your Excavation, Grading, and Road Cut Permits permit actually take in North Ogden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full North Ogden inspection guide — scheduling & re-inspection fees →

    Tips

    • A new pavement cut fee of $500.00 applies for cuts into roads that are two years old or less, per the official Street Cuts Fee note on Consolidated Fee Schedule page 14.
    • Special districts and government taxing entities receive a 25% discount (pay 75% of the standard Road Cut Fee).
    • There is no standalone flat fee for an Excavation Permit — it shares the same '$75.00 + Road Cut Fee ($2.50/sq ft)' fee structure as the Road Cut Fee itself, per the official Building Permit Fees table.

    Frequently asked questions

    North Ogden requires an excavation, grading, and road cut permits for: Excavation work requires an Excavation Permit; Grading work requires a Grading Permit; Blasting requires a Blasting Permit; Cutting into a public road/right-of-way requires a Road Cut Fee payment plus bonding. If your project isn't listed, confirm with North Ogden City Building Department at (801) 737-9837 or (801) 737-2218 before starting work.

    In North Ogden, the published Excavation Permit is: $75.00 + Road Cut Fee ($2.50 per sq ft) — shares the Road Cut Fee formula below; no separate flat Excavation Permit fee is published. Additional published fees: Grading Permit — $150.00; Blasting Permit — $50.00; Road Cut Fee — $75.00 + Road Cut Fee ($2.50 per sq ft); Taxing Entities (Special Districts & Government) pay 75% of standard fee; Cash Bond $300.00; Performance Bond $2,000.00; New Road Cut Additional Fee $500.00 (roads two years old or less); Mining/Crushing Permit — $1,000.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    North Ogden does not publish a plan-review timeline for this permit. Contact North Ogden City Building Department at (801) 737-9837 or (801) 737-2218 for current turnaround.

    You'll need: Excavation/Grading Permit Application (iWorQ portal or Building Department). See the required-documents checklist on this page for details on each.

    Apply through North Ogden City Building Department at 505 E 2600 North, North Ogden, UT 84414. Phone: (801) 737-9837 or (801) 737-2218, email: building@northogdencity.gov. Office hours: Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 1:00 PM, per the city's official Building Codes page and Finance Department contact block (consistent hours published city-wide).. Official information: https://northogdencity.gov/departments/building/building_codes.php.

    North Ogden, Utah has adopted: North Ogden City's official Building Codes page states only that the city 'recognizes the current adopted Utah State Building Code' — it does not itemize individual code titles or edition years on its own page (confirmed on repeated fetches of northogdencity.gov/departments/building/building_codes.php).; Statewide framework per Utah Code § 15A-2-103: as of the code cycle effective July 1, 2026 (confirmed current as of this 2026-07-16 re-verification), the State of Utah has adopted the 2021 International Residential Code (IRC, continuing from the prior cycle, § 15A-2-103(1)(b)), the 2024 International Building Code (IBC, § 15A-2-103(1)(a)), the 2023 National Electrical Code (NEC, continuing from the prior cycle, § 15A-2-103(1)(g)), and other 2024 International Codes (IPC, IMC, IFGC, IEBC, IECC, and the residential provisions of the ISPSC, per § 15A-2-103(1)(d)/(e)/(f)/(i)/(h)/(n)) — the same statewide cycle documented on Highland City's official Building Division page. North Ogden's own site does not confirm city-level adoption of each title by name; this entry cites the statewide framework North Ogden explicitly says it follows ('recognizes the current adopted Utah State Building Code'), without asserting North Ogden has separately re-published each edition/year. This entry was already correctly stated in present tense as of the prior verification and required no substantive correction on this pass.; Design criteria published on North Ogden's official Building Codes page: Seismic Design Category D or E; Basic Wind Speed 115 mph; Exposure Category C; roof snow load calculated via the state-adopted snow load calculator; minimum footing frost depth of 30 inches; weathering condition classified as 'severe.'. Local amendments apply — see the North Ogden overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-13.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Ogden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.