North Ogden has no distinct EV charger/EVSE permit type or fee line item — installing electric vehicle charging equipment is electrical work billed under the city's single integrated Building Permit Fee (1997 Uniform Building Code, Section 107.2 Table 1A, plus a 20% surcharge), the same valuation-based schedule used for all building, electrical, plumbing, and mechanical work in North Ogden (there is no separate 'Electrical Permit' type in the city's own permit catalog). A direct review of the city's current Consolidated Fee Schedule (Resolution 05-2026, effective document '05-2026 Consolidated Fee Schedule - Permanent.pdf') found no 'EV,' 'electric vehicle,' or 'EVSE' line item anywhere in the document.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in North Ogden
  • New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g))
  • Building Permit Application submitted through North Ogden's Building Department (iworq portal, cityofnorthogden.portal.iworq.net)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, covers electrical/EVSE scope)North Ogden Consolidated Fee Schedule (Resolution 05-2026, '05-2026 Consolidated Fee Schedule - Permanent.pdf'), 'Building Permit Fees' section: 'Single-Family Residential Permit and Commercial Building Permit Fees — 1997 version of the Uniform Building Code, Section 107.2 Table 1A plus 20%' and 'Minimum Building Permit Fee $56.40.' No distinct EV-charger or standalone electrical-permit fee line exists; a related 'Temporary Power Inspection' fee of $56.40 is separately listed under the same Building Permit Fees section.
1997 Uniform Building Code, Section 107.2 Table 1A, plus 20%; Minimum Building Permit Fee $56.40
Plan Check FeeNorth Ogden Consolidated Fee Schedule, Building Permit Fees section.
Residential: 50% of Permit Fee; Commercial: 65% of Permit Fee
State FeeNorth Ogden Consolidated Fee Schedule, Building Permit Fees section.
1% of Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in North Ogden?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Temporary Power / Electrical Inspection

    Electrical inspection of the new circuit and charger connection, administered by the Building Department; billed at the same rate as the city's Temporary Power Inspection ($56.40) where applicable.

See the full North Ogden inspection guide — scheduling & re-inspection fees →

Tips

  • North Ogden does not have a separate 'Electrical Permit' permit type at all — building, electrical, plumbing, and mechanical work (including EV charger installation) are all billed under the single valuation-based Building Permit Fee (1997 UBC Table 1A + 20%).
  • The Minimum Building Permit Fee is $56.40 — a low-valuation scope like a single EV charger circuit would likely be billed at or near this minimum, but confirm with the Building Department (801-737-9800) before applying.
  • A 1% state surcharge and a Plan Check Fee (50% residential / 65% commercial of the permit fee) apply on top of the base valuation-based fee.

Frequently asked questions

North Ogden requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in North Ogden; New dedicated electrical circuit and/or panel capacity to serve the charger, regulated by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g)); Building Permit Application submitted through North Ogden's Building Department (iworq portal, cityofnorthogden.portal.iworq.net). If your project isn't listed, confirm with North Ogden City Building Department at (801) 737-9837 or (801) 737-2218 before starting work.

No. North Ogden's Consolidated Fee Schedule has no distinct EV-charger or electrical-permit fee line item — EV charger/EVSE installation is billed under the city's single integrated Building Permit Fee (1997 UBC Section 107.2 Table 1A plus 20%, minimum $56.40), the same valuation-based schedule used for all trades.

North Ogden does not publish a plan-review timeline for this permit. Contact North Ogden City Building Department at (801) 737-9837 or (801) 737-2218 for current turnaround.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

North Ogden requires 1 inspection(s) for an ev charger / evse permit, in order: Temporary Power / Electrical Inspection. Schedule each through North Ogden City Building Department ((801) 737-9837 or (801) 737-2218).

Apply through North Ogden City Building Department at 505 E 2600 North, North Ogden, UT 84414. Phone: (801) 737-9837 or (801) 737-2218, email: building@northogdencity.gov. Office hours: Monday–Thursday 8:00 AM – 5:00 PM; Friday 8:00 AM – 1:00 PM, per the city's official Building Codes page and Finance Department contact block (consistent hours published city-wide).. Official information: https://northogdencity.gov/departments/building/building_codes.php.

North Ogden, Utah has adopted: North Ogden City's official Building Codes page states only that the city 'recognizes the current adopted Utah State Building Code' — it does not itemize individual code titles or edition years on its own page (confirmed on repeated fetches of northogdencity.gov/departments/building/building_codes.php).; Statewide framework per Utah Code § 15A-2-103: as of the code cycle effective July 1, 2026 (confirmed current as of this 2026-07-16 re-verification), the State of Utah has adopted the 2021 International Residential Code (IRC, continuing from the prior cycle, § 15A-2-103(1)(b)), the 2024 International Building Code (IBC, § 15A-2-103(1)(a)), the 2023 National Electrical Code (NEC, continuing from the prior cycle, § 15A-2-103(1)(g)), and other 2024 International Codes (IPC, IMC, IFGC, IEBC, IECC, and the residential provisions of the ISPSC, per § 15A-2-103(1)(d)/(e)/(f)/(i)/(h)/(n)) — the same statewide cycle documented on Highland City's official Building Division page. North Ogden's own site does not confirm city-level adoption of each title by name; this entry cites the statewide framework North Ogden explicitly says it follows ('recognizes the current adopted Utah State Building Code'), without asserting North Ogden has separately re-published each edition/year. This entry was already correctly stated in present tense as of the prior verification and required no substantive correction on this pass.; Design criteria published on North Ogden's official Building Codes page: Seismic Design Category D or E; Basic Wind Speed 115 mph; Exposure Category C; roof snow load calculated via the state-adopted snow load calculator; minimum footing frost depth of 30 inches; weathering condition classified as 'severe.'. Local amendments apply — see the North Ogden overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Ogden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.